Energy Transfer takes FID on South Mississippi pipeline project, reports 19% earnings jump

A binding open season is under way to solicit additional customer commitments and determine final pipeline sizing and capacity. Energy Transfer expects South Mississippi to enter service in 2030.

Energy Transfer LP has taken final investment decision (FID) on its 1.2-bcfd, 215-mile South Mississippi pipeline project, having secured sufficient long-term, demand-based transportation agreements to support its construction. The 36-in. OD pipeline will likely be 51% owned and operated by Energy Transfer, with the remaining ownership coming from shippers, the company said in its third-quarter 2026 earnings report.

A binding open season is underway to solicit additional customer commitments and determine final pipeline sizing and capacity. Energy Transfer expects South Mississippi—running from a connection near the Perryville hub in northeastern Louisiana to an interconnect with Florida Gas Transmission in southern Mississippi—to enter service in 2030.

In Energy Transfer’s earnings conference call, co-chief executive officer Mackie McCrea said that South Mississippi would “drive other upstream opportunities” for the company, noting that “one of the contracts supporting [the pipeline]” was “a long-term deal starting in 2029 for capacity out of Marcellus Utica down our Panhandle trunkline.

The company gathered and shipped record volumes of natural gas in third-quarter 2026. Gathered volumes were up 6% year-on-year and intrastate volumes increased 14%, the latter helped by the 1.5-bcfd Phase I of the Hugh Brinson pipeline entering service on Sept. 1, 2026. The company expects completion of Phase II (700 MMcfd) in first-quarter 2027.

Energy Transfer in third-quarter 2026 also completed a 250-MMcfd expansion of its Rover pipeline system to support a 15-year agreement with a Marcellus producer. The capacity became active Nov. 1.

The company further announced plans for its 200-MMcfd Bear II cryogenic gas processing plant, to be sited in Delaware basin adjacent to its existing Bear plant and expected to enter service third-quarter 2027. Energy Transfer last month placed its 275-MMcfd Mustang Draw II processing plant into service in Midland basin. On the other end of the process, Energy Transfer will build its tenth fractionator, the 200,000-b/d Frac X, at Mont Belvieu, Tex., to be in service first-half 2029.

Energy Transfer reported third-quarter 2026 net income attributable to partners of $1.21 billion compared with $1.02 billion a year earlier.

About the Author

Christopher E. Smith

Christopher E. Smith

Editor in Chief

Chris joined Oil & Gas Journal in 2005 as Pipeline Editor, having already worked for more than a decade in a variety of oil and gas industry analysis and reporting roles. He became editor-in-chief in 2019 and head of content in 2025.

Sign up for our eNewsletters
Get the latest news and updates