Cheniere begins Corpus Christi LNG Train 3 operations

Cheniere Energy Inc. has received approval from the US Federal Energy Regulatory Commission to put the third train at its 15-million tonne/year (tpy) Corpus Christi LNG plant in commercial service.
March 29, 2021

Cheniere Energy Inc. has received approval from the US Federal Energy Regulatory Commission to put the third train at its 15-million tonne/year (tpy) Corpus Christi LNG plant in commercial service. Commissioning of Train 3 is complete, and Bechtel Oil, Gas, and Chemicals Inc. has turned over operations to Cheniere.

The train has been operating for evaluation and testing since August 2020. Trains 1 and 2 entered service in 2019. 

Cheniere is also commercializing Stage 3 expansion at Corpus Christi, which proposes up to seven ​midscale trains that would add 10 million tpy of production.