CNOOC Ltd. has started production from the Bozhong 19-4 oilfield comprehensive adjustment project.
The project lies in the south of Bohai Sea, with average water depth of about 21 m. In addition to fully utilizing the existing processing facilities of Bozhong 25-1 oilfield, the project has built a new eight-legged central equipment platform. A total of 25 development wells are planned, including 18 production wells and 7 water injection wells. The project is expected to reach peak production of 11,000 b/d of crude oil in 2022.
CNOOC is operator of the project with 100% interest.