ConocoPhillips Alaska Inc. plans to drill additional wells and add associated on-pad infrastructure to boost production at its CD5 drill site in Alpine field in the National Petroleum Reserve-Alaska (NPR-A).
The additions, funding of which has been approved, will bring CD5 to its full design and permit capacity. Project work will begin this year, with the start of production from this next phase of drilling expected in third-quarter 2017. The new wells and infrastructure will be completed within the existing CD5 drill site footprint.
The CD5 pad is designed to accommodate 33 wells. The original development funding was for 15 wells, 10 of which have been completed. The cost of the project is estimated at $190 million, which includes construction, drilling, and well tie-ins. The company expects CD5 to meet its production target of 16,000 boe/d gross average for the year.
“The competitiveness of this next phase of CD5 drilling was improved due to the investment climate resulting from the passage of SB21,” said Joe Marushack, ConocoPhillips Alaska president. “We want to continue to invest in production-adding projects like this.”