Nova Gas Transmission Ltd. (NGTL), a wholly owned subsidiary of TC Energy Corp., awarded Macro Enterprises Inc. subsidiary Macro Construction Inc. a contract to build the Deep Valley South and Colt sections of the 2021 NGTL System Expansion project.
Deep Valley South includes 26 km of 48-in. OD pipeline and Colt includes 14 km of 48-in. pipeline and associated tie-ins.
Planning is under way with pre-construction scheduled to start third-quarter 2021 with completion scheduled end first-quarter 2022. The estimated value of the contract is more than $190 million.
The Canadian government earlier this month approved NGTL’s 2023 North Corridor System Expansion project (OGJ Online, May 4, 2021).