Centurion expects December in-service for Permian crude line

Oct. 6, 2020
Centurion Pipeline LP expects to put its 30-mile, 150,000-b/d Augustus crude oil pipeline in service on Dec. 1, 2020.

Centurion Pipeline LP expects to put its 30-mile, 150,000-b/d Augustus crude oil pipeline in service on Dec. 1, 2020. The 20- and 18-in. OD pipeline will move West Texas Intermediate, West Texas Light, and West Texas Sour crude from Midland, Tex., to Crane, Tex., connecting Centurion’s 2-million bbl Midland terminal to multiple transmission pipelines.

Pipelines shipping crude from Crane include Epic Midstream’s 600,000-b/d pipeline to the Port of Corpus Christi, Phillips 66’s 900,000-b/d Gray Oak pipeline to Sweeny, Tex., Corpus Christi, and Ingleside, Tex., and Magellan Midstream Partners’ 275,000-b/d Longhorn and 400,000-b/d BridgeTex pipelines to Houston and surrounding refining complexes.