LNG Canada begins Phase 2 FEED update

Phase 2 would double the plant’s capacity. The award follows the commissioning of Phase 1 with the recent shipment of the p;ant’s first LNG cargo
Aug. 4, 2025

LNG Canada awarded Flour Corp.’s joint venture with JGC Corp. the contract to update the front-end engineering and design (FEED) for a proposed Phase 2 expansion of the 14-million tonne/year LNG Canada liquefaction plant on the traditional territory of Haisla Nation in Kitimat, BC. Phase 2 would double the plant’s capacity.

The award follows the commissioning of Phase 1 with the recent shipment of the plant’s first LNG cargo (OGJ Online, July 1, 2025). The JGC Fluor JV provided Phase 1 engineering, procurement, fabrication management, construction, and commissioning.

LNG Canada—comprised of  Shell PLC, Mitsubishi Corp., Korea Gas Corp., Petroliam Nasional Berhad (Petronas) and PetroChina Co. Ltd.—has not yet reached a final investment decision on Phase 2.

Sign up for Oil & Gas Journal Newsletters