Freeport LNG ships first commissioning cargo

Sept. 4, 2019
Freeport LNG Development LP (FLNG), Houston, has shipped the first LNG commissioning cargo for Train 1 from its liquefaction facility on Quintana Island in Freeport, Tex.

Freeport LNG Development LP (FLNG), Houston, has shipped the first LNG commissioning cargo for Train 1 from its liquefaction facility on Quintana Island in Freeport, Tex. (OGJ Online, Aug. 20, 2019).

Some 150,000 cu m of LNG was loaded aboard the LNG Jurojin, which departed from the Freeport LNG terminal on Sept. 3. The first cargo loading is a step towards the start of commercial operations expected later this month.

FLNG’s Train 2 is advancing the precommissioning phase to support an in-service date of January 2020. Train 3 is nearing completion to support an in-service date of May 2020.