The US Bureau of Land Management (BLM) Sept. 4 offered a new proposal at the request of the Alaska Oil and Gas Association to streamline permitting for oil and gas production sites within the National Petroleum Reserve in Alaska (NPR-A) by switching from project-by-project environmental reviews to a single framework, according to a draft of early chapters of the proposed rule posted on the agency’s website.
The proposal calls for fixed review timelines, with BLM having 60 days to issue final approval or approval with conditions upon receiving a completed application. The proposed rule specifies that BLM’s 2-month decision deadline would override any other individual regulatory components that could delay a decision. Following BLM approval, operators must begin construction within 4 years, according to the draft.
The rule allowing applicants to bypass project-level review under the National Environmental Policy Act (NEPA) only would apply to production sites within 25 miles of existing permanent oil and gas infrastructure and that are outside of designated "no surface occupancy" areas, unless the infrastructure is an essential road or pipeline crossing explicitly permitted by an Integrated Activity Plan (IAP).
In addition to releasing the proposed rule, BLM also unveiled portions of the supporting Environmental Impact Statement (EIS), which it is developing concurrently. The EIS looks at 120 environmental reviews conducted in NPR-A from 1998-2026—10 EISs reviewing land-use plans and substantial infrastructure development proposals and 110 less-stringent Environmental Assessments (EAs) analyzing smaller, localized project requests.
“Responsible development shouldn't be held back by redundant paperwork. By utilizing over 20 years of rigorous environmental data, we are replacing slow, case-by-case reviews with a standardized process that maintains our high environmental standards, while giving operators the predictability they need to build,” BLM Director Steve Pearce said in a press release.