Navitas plans to begin drilling Sea Lion’s first Northern Development Area phase in March 2027, with production expected in first-half 2028.

Navitas Petroleum Ltd. is planning to drill the first phase of the Sea Lion Northern Development Area (NDA1) in North Falkland basin in March 2027.

Development work for NDA1 is progressing as planned, with production anticipated to begin during first-half 2028. Works in the Falkland Islands are currently progressing with the preparation of the jetty, shore base, and helipad to serve the project, as well as the construction of housing for project employees and additional infrastructure works.

The production processes for long-lead items, including flexible flowlines, wellheads, xmas trees, and subsea manifolds, are continuing as planned.

The FPSO is currently anchored in Southeast Asia until it enters the shipyard for preparation work for the installation and integration of the modules and necessary equipment as part of the upgrade and adjustment works. Module and mooring system production also is progressing according to plan.

Concurrently, the partnership is promoting the acceleration of the development of additional resources in the Sea Lion project through the integration of an additional FPSO. Within this framework, a development outline has been created for the Central Development Area (CDA), including, among others, performance of front-end engineering and design (FEED) and ordering of long-lead items.

The CDA development plan is expected to consist of two phases: CDA1 including 20 wells, and CDA2 including 18 wells, for a total of 38 wells. The plan is expected to be ready for approval by the Falkland Islands government and reach a final investment decision (FID) during 2028.

According to the partnership's estimate, the start of production from the CDA1 development is due by yearend 2030.

As part of the preparations for the CDA development, the OSX1 vessel has been purchased to serve in the future stages of the project, after upgrade and adjustment works, as an FPSO with a production capacity of about 125,000 b/d.

With a 65% interest, Navitas is operator at Sea Lion, with partner Rockhopper holding the remaining 35% stake.