An explosion and subsequent fire  occurred on Jan. 13 at the low-density polyethylene (LDPE) unit of Sasol Ltd.’s Lake Charles Chemicals Project (LCCP), an integrated ethane  cracker and downstream derivatives complex under progressive commissioning  since 2019 in Westlake, La., near Lake Charles (OGJ Online, Aug. 30, 2019;  Feb. 14, 2019).
Sasol  has extinguished the fire, with all employees and contractors safe and  accounted for, the operator said on Jan. 14.
The  new LDPE unit—which had not yet achieved beneficial operation (BO) as planned  for in December 2019—was in the final stages of commissioning and start-up when  the incident occurred, Sasol said.
The  LDPE unit has been shut down, and an investigation is now under way to  determine the cause of the incident, the extent of the damage, and resulting  impact on the LDPE unit's BO schedule.
All  other Lake Charles units and previously commissioned LCCP units, including the  ethane cracker, ethylene glycol-ethylene oxide, and linear low-density  polyethylene (LLDPE) units, are unaffected and operating to plan, according to  the operator.
The  1.5 million-tonne/year ethane cracker recently achieved nameplate capacity  following a successful replacement of the acetylene reactor catalyst in the  plant in late 2019 (OGJ Online, Dec. 17, 2019).  
Sasol  said the remaining three downstream units under construction to complete the  integrated LCCP sit—including the Ziegler alcohols and alumina unit, alcohol  ethoxylates unit, and Guerbet alcohols unit—are were unaffected by the incident  and remain within cost and and on schedule.
In  December, Sasol said it expected the timeline for LCCP’s remaining three  units to achieve BO to be as follows:
- Zeigler alcohols unit: January 2020.
 - Guerbet alcohols unit: March 2020.
 - Ethoxylation unit: January 2020.