JSC Yamal LNG has let an engineering, procurement, and construction contract to Technip SA for an LNG facility with a capacity of 16.5 million tons/year (tpy).
The project consists of three 5.5-million tpy liquefaction trains that are among the world’s largest and will make extensive use of modularized construction in yards.
Technip for the past 14 months has been involved in providing project planning, detailed engineering, estimation, and procurement work for JSC Yamal LNG. Handover of the first train is planned for 2017.