Delfin LNG requests FERC extension for offshore liquefaction complex
July 2, 2021
FERC denied a request in June 2019 for an extension to March 2023, granting a 1-year bump to September 2020 instead. The in-service date was subsequently extended to September 2021.
Delfin says it has entered detailed negotiations with potential LNG buyers for the purpose of signing long-term offtake contracts in the next 12 months.
Delfin LNG completed front-end engineering design for the plant’s planned four liquefaction vessels in late 2020 (OGJ Online, Oct. 12, 2020). The ships will be stationed offshore Louisiana.
New onshore components include onshore pipelines, three compressors totaling 74,000 hp, a natural gas supply header, and a meter station. Gas will be shipped offshore via the existing UTOS pipeline, acquired by Delfin in 2014.