FGEN LNG Corp. has named Jacobs owner's engineer for the  engineering, procurement, and construction of FGEN's interim offshore terminal  project at the First Gen Corp. clean  energy complex in Batangas City, Philippines. As owner's engineer, Jacobs will  undertake design review, project management, and supervision of the  construction of the project.
Work comprises modification of an existing liquid fuels  jetty to accommodate a floating storage and regasification unit (FSRU) as well  as LNG carriers. Scope includes modifications to the jetty head, berthing, and  mooring; a trestle bridge with high-pressure gas pipeline and utilities; and a  jetty monitoring building and control room.
The modified terminal will supply existing gas-fired power  plants, which in 2019 were responsible for delivering 13,876 Gw/hr into the  Luzon grid, according to Jacobs.
FGEN earlier in the month leased the terminal’s FSRU from BW  Gas (OGJ  Online, Apr. 5, 2021).