Cheniere Energy Partners LP reported that it expects to export the first LNG commissioning cargo from its Sabine Pass liquefaction project in Cameron Parish, La., in late February or March. The first commissioning cargo was initially expected to occur by late January (OGJ, Aug. 3, 2015, p. 62).
Construction for Train 1 was completed well ahead of the guaranteed contractual schedule and within budget, Cheniere said. “However, instrumentation issues were discovered during the final phases of plant commissioning and cool down that will require some additional work over the next few weeks,” it added.
Neal Shear, who was appointed interim president and chief executive officer at the end of last year (OGJ Online, Dec. 14, 2015), said, “With construction of Train 1 finished, we remain well ahead of the guaranteed contractual schedule with Bechtel and anticipate no issues in meeting all contractual targets and guaranteed completion dates.”