SCOTT FIELD DEVELOPED WITH 'PLUG-IN' PLATFORMS

Phil Shaw Scott Project Manager Amerada Hess Ltd. London When Amerada Hess Ltd. (AHL) and its partners received U.K. Department of Energy approval in August 1990 for development of Scott oil field, the schedule was perceived as somewhat aggressive, if not ambitious. Now the target of first oil by the end of 1993 looks as if it will be beaten by at least a 2 month margin. Furthermore, Scott should reach plateau production of nearly 200,000 b/d of oil within a month of first oil.