RIO DE JANEIRO, Dec. 4 -- BG Group PLC has concluded the expansion and revamping of its natural gas processing plant in La Vertiente, Bolivia.
The project took 10 months and cost $30 million. It increased the plant's capacity to 4.2 million cu m/day (MMcmd) from 1.6 MMcmd.
BG acquired the La Vertiente plant from Tesoro Bolivia Petroleum Co. in 1999 for $100 million. La Vertiente takes gas from Taiguati, El Escondido, and Los Suris fields.
The gas is transported through Transredes-operated pipelines to the border, and then through the Petroleo Brasiliero SA-operated Bolivia-Brazil gas pipeline to the Brazilian delivery points of Comgas, in Sao Paulo.