Aasgard B hull arrives in Stavanger

The steel hull of the semisubmersible Aasgard B floating production unit arrived in Stavangar, on Aug. 31, 1999, aboard Dockwise NV's Mighty Servant 3 heavy transport vessel. The hull's 6-week voyage from Daewoo Heavy Industries' Okpo, South Korea, yard included passage through the Suez Canal.
Oct. 11, 1999
Click here to enlarge image

The steel hull of the semisubmersible Aasgard B floating production unit arrived in Stavangar, on Aug. 31, 1999, aboard Dockwise NV's Mighty Servant 3 heavy transport vessel. The hull's 6-week voyage from Daewoo Heavy Industries' Okpo, South Korea, yard included passage through the Suez Canal.

The diagonal 53.6° setting of the hull on the 40-ft wide Mighty Servant 3 resulted in a 132.78-m width, close to the maximum that can transit the 150- ft wide canal, according to Statoil, operator of the Aasgard development. Dockwise reports that the 18,000-tonne hull's dimensions are 102.4-m long, 96-m wide, and 45-m high.

Timeline

Statoil plans to have the hull mated to the 33,000-tonne topsides in October 1999, with tow out to the field in April 2000. It expects gas production to begin during October 2000.

The Aasgard development includes three fields: Midgard, Smørbukk, and Smørbukk South in the Halten Bank area of the Norwegian Sea. Oil production from the fields began on May 19, 1999, through the Aasgard A floating production, storage, and offloading (FPSO) vessel.

Statoil says Aasgard B will be the world's largest floating offshore gas processing installation, designed to handle 1.4 bcfd, 95 000 b/d of condensate, and 40,000 bo/d.