PIPELINING-WORLDWIDE CONSTRUCTION

Oct. 18, 1993
* Designates projects listed for the first time in the Journal. BLOCK 873 PIPELINE Co. (Partnership). *60 miles, 16 in. line from Gulf of Mexico - Ewing Bank 873 to Ship Shoal 141. Under construction. Completion: 1994. CAJON PIPELINE Co. 122 miles, 20 in. line from offshore Calif. and San Joaquin Valley oil fields to the Los Angeles basin. Completion: Early 1993. CELREON Corp. 1 1 miles, 24 in. line from Gaviota, Calif., to Las Flores, Calif. under construction. CHEVRON PIPE LINE Co. 49 miles,

* Designates projects listed for the first time in the Journal.

U.S. CRUDE LINES

BLOCK 873 PIPELINE Co. (Partnership). *60 miles, 16 in. line from Gulf of Mexico - Ewing Bank 873 to Ship Shoal 141. Under construction. Completion: 1994.

CAJON PIPELINE Co. 122 miles, 20 in. line from offshore Calif. and San Joaquin Valley oil fields to the Los Angeles basin. Completion: Early 1993.

CELREON Corp. 1 1 miles, 24 in. line from Gaviota, Calif., to Las Flores, Calif. under construction.

CHEVRON PIPE LINE Co. 49 miles, 20 in. replacement line from Wink, Tex. to El Paso, Tex. Completion: December 1993.

*3.5 miles, 4 in. line from Keystone, Tex. to Wink, Tex. Design stage. Completion: June 1994.

*97 miles, 26 in. replacement line from Trinity, Tex. to Nederland, Tex. Completion: December 1993.

PERMIAN OPERATING Ltd. PARTNERSHIP. 13 miles, 6 in. from Dolphin field, Divide County, N.D., southeast to an Amoco pipeline in Burke County, N.D.

TRANSMOUNTAIN OIL PIPE LINE. 145 miles, 36 in. line from Low Point, Wash., to Anacortes and Ferndale/Cherry Point, Wash. proposed. Completion: 4th Qtr. 1993. 105 miles, 24 in. line from Burlington, Wash., to Low Point, Wash. proposed. Completion: 4th Qtr. 1993.

10 miles, 22-30 in. line in Washington State.

U.S. PRODUCT LINES

CHASE TRANSPORTATION Co. Ooint venture with Koch Industries - 50/50). 18 miles product line from Aurora, Colo. terminal to Denver airport. Approved,

COASTAL Corp. 40 miles, 8 in. line near Markham, Tex.

CHEVRON PIPE LINE Co. 15 miles, 10 in. line from Mont. Belvieu, Tex. to Deer Park, Tex. Completion: August 1994.

*6 miles, 10 in. line near Brigdeport, Tex. in design stage. Completion: December 1993.

*150 miles, 12 in. line from Weatherford, Tex. to Lufkin, Tex. Design stage. Completion: April 1994.

EXPLORER PIPELINE. 28 in. mainline expansion from Gulf Coast to Dallas-Fort Worth area under study.

KOCH HYDROCARBONS Co. 583 miles, 12 in. replacement line from Medford, Okla., to Mont Belvieu, Tex. completed.

U.S. GAS LINES

ALGONQUIN GAS TRANSMISSION Co. *3.8 miles, 16 in. replacement line in Oakland and Mahwah, N.J. and 4.9 miles, 36 in. replacement line in Southeast N.Y. Before FERC. $35 MM. Completion: 1994.

*1.2 miles, 26 in. line from Lambertville to Flemington. Contr: Napp-Grecco Co. Completion: October 1993.

ALTAMONT GAS TRANSMISSION Co. 620 miles, 36 in. line from Port of Wild Horse, Mont., to Opal, Wyo. Completion: 1996.

AMERICAN PIPELINE, 38 miles, 16 in. in East Texas to connect Union Pacific Resources Carthage gas processing plant with pipelines to the west.

47 miles line in La. connecting its system to the Tennessee Gas Pipeline Co. line.

ANR PIPELINE Co. (Empire State Pipeline) *156 miles, 24 in. line from Grand Island to Syracuse, N.Y. under construction. Contr: Welded Construction Co./Michels Pipeline Construction Co. Completion: November 1993.

ARKLA PIPELINE GROUP. 28 miles, 16 in. replacement of line 2 in Okla., FERC approved. Completion: December 1993.

*79.5 miles, 30 in. and 4.5 miles, 36 in. Line AC Extenstion from Glendale, Ark. to Shaw, Miss. proposed. Completion: September 1994.

CHEVRON PIPE LINE Co. *12 miles, 12 in. line from offshore Block M0861 to Chandeleur Pipeline System near Mississippi. Planned. Completion: Mid-1995.

*20 miles, 16 in. line from Chandeluer Pipeline System at Pascagoula, Miss. refinery to pipeline interconnect. Planned. Cornpietion: Mid-1995.

CITY UTILITIES. 76 miles, 16 in. natural gas line to interconnect with Arkla Energy Pipeline at Jane, Mo. and extend to Springfield, Mo. $25 MM. Design Engr/PM: Trigon Engr. Completion: Late 1993.

CITGO PIPELINE Co. 112 miles, 10-12 in. line from Lake Charles, La. to Mont. Belvieu, Tex. planned. Completion: 1994.

CNG TRANSMISSION Corp. 2.8 miles, 30 in. fine from Rensselaer County, N.Y., to Albany County, N.Y. Approved. Completion: February 1994.

*1 5.1 miles, 24 in. line from Potter County, Penn. to Steuben County, N.Y. FERC approved. Completion: 1994.

*3.7 miles, 30 in. line in Albany, N.Y. Before FERC. Completion: 1994.

*8.8 miles, 30 in. line in Armstrong County, Pa. Before FERC. Completion: October 1994.

COLONIAL PIPELINE Co. 64 miles, 12 in. line planned from Bainbridge, Ga. to Jefferson County, Fla. Completion: 1994.

COLORADO INTERSTATE GAS Co. 23 miles, 4-10 in. line in Converse County, Wyo.

CONSUMERS POWER CO. 1.5 miles, 8 in. line planned from Northville Lyon 29 well site to Lyon 34 well site. Completion: 190-A. 1.5 miles, 16 in. line planned from Haggerty Rd. to Meadowbrook Rd. Completion: 1993.

12 miles, 36 in. line planned from Hackman Rd. valve site to Babcock Rd. valve site. Completion: 1994.

1.8 miles, 10 in. lined planned from N211 well to Northville comp. station. Completion: 1994.

CONOCO Inc. 21 miles, 10 in. Grand Isle project.

EL PASO NATURAL GAS. 3.3 miles, 30 in. line from Monument, N.M. to Eunice, N.M. Before FERC. Completion: 4th Qtr. 1993.

89 miles, 30 in. line from Quartzsite, Ariz. to Yuma, Ariz. Completion: 1994.

ENDEVCO Inc. 44 miles. 24 in. line from Delhi, La., to Vicksburg, Miss. planned.

19 miles, 8-12 in. line in Smith and Simpson Counties, Miss.

ENRON GAS GATHERING. aoint venture with Dauphin Island Gathering Co.) 70 miles, offshore gas gathering system in Mobile Bay, Ala.

ENSERCH EXPLORATION PARTNERS Ltd. *52 miles, 16 in. offshore line from Garden Banks Block 388 to platform on Eugene Island Block 315. DD: Brown & Root. Marine. Completion: Summer 1994.

FLORIDA GAS TRANSMISSION. 10.6 miles, 16 in. line from Hillsborough County, Fla. to Polk County, Fla. Before FERC. Completion: 1994.

164.6 miles, 30 in. line from Suwanee County, Fla., to Hillsborough County, Fla. Before FERC. Completion: November 1994. 16.2 miles, 22 in. line from Polk County, Fla., to Hillsborough County, Fla. Before FERC. Completion: November 1994.

2.9 miles, 20 in. line in Port Everglades, Fla. Before FERC. Completion: November 1994.

415.9 miles, 36 in. line from Washington Parish, La. to Suwanee County, Fla. Before FERC. Completion: November 1994.

114.9 miles, 30 in. line from Orange County, Fla. to Palm Beach County, Fla. Before FERC. Completion: November 1994.

39.4 miles, 26 in. line from Calcasieu Parish, La. to St. Landry Parish, La. Before FERC. Completion: November 1994.

30.1 miles, 30 in. line from Tangipahoa Parish, La. to Washington Parish, La. Before FERC. Completion: November 1994.

7.0 miles, 12 in. line in Polk County, Fla. Before FERC. Completion: November 1994. 2.1 miles, 10 in. line in Polk County, Fla. Before FERC. Completion: November 1994. 4.5 miles, 8 in. line in Polk County, Fla. Before FERC. Completion: November 1994. 2.3 miles, 6 in. line in Osceola County, Fla. to Orange County, Fla. Before FERC. Completion: November 1994.

1.9 miles, 6 in. line in Polk County, Fla. Before FERC. Completion: November 1994.

*3.0 miles, 6 in. line from Pinellas County across Tampa Bay to Hillsborough County, Fla. Planned. Completion: May 1994.

*4.0 miles 18 in. line in Osceola County, Fla. Planned. Completion: 1994,

KN ENERGY Inc. *14.5 miles, 8 in. line from Pfeifer to Toulon, Kan. Pending. Completion: December 1993.

KOCH REFINING Co. 150 miles, 12 in. products and gas liquids pipeline from Corpus Christi, Tex. to Brownsville, Tex. Completion: 4th Qtr. 1993.

LIBERTY PIPELINE Co. 30 miles, 30 in. line offshore and 8 miles, 30 in. onshore gas line from a receipt point near South Amboy, N.J. to delivery point near Long Island. Before FERC. Completion: November 1995.

*10.5 miles, 36 in. line in Lycoming/Clinton County, Pa. Before FERC. $23.1 MM. Completion: 1995.

*6.7 miles, 36 in. line in Lycoming County, Penn. Before FERC. $15.6 MM. Completion: 1995.

*1.1 miles, 26 in. line in South Amboy, N.J. Before FERC. $0.6 MM. Completion: 1995.

MACKENZIE PORCUPINE PIPELINE Co. 750 miles natural gas pipeline planned from McKenzie Delta area in Canada to Kenai, Alas. Completion: Late 1997.

MAGNOLIA PIPELINE Co. (Basin Pipeline Corp. and a unit of Transco Energy Co.) 55 miles intrastate line, 40 miles of laterals from Alabama's Black Warrrior basin to Transco's interstate line in Central Ala. $55 Million.

MICHIGAN GAS STORAGE Co. 22 miles, 36 in. line planned from Muskegon River Comp. Stat. to Herrick Rd . valve site. Completion: 1993.

MISSOURI PIPELINE Co. 22 miles of 1216 in. line from Curryville, Mo., to St. Charles and West Alton, Mo. $15 MM.

Converting 70 miles of existing crude line to gas line in Pike, Lincoln, and St. Charles Counties, Mo.

MOJAVE PIPELINE Co. 300 miles gas pipeline expansion from Topock, Ariz. to Sacramento and the East Bay area of Calif. Contr: Wolder Engr. & Const. $500 MM.

*600 miles, 4-30 in. line from Bakersfield, Calif. to Sacramento & East Bay area. Before FERC. Completion: May 1995.

NOARK PIPELINE SYSTEM. 258 miles gas line across Arkansas under construction. $73MM.

NORTHWEST PIPELINE Corp. 39 miles, 30 in., 6 miles, 20 in., and 15 miles, 24 in. line expansion project in Wash. and Ore. Contr: Gregory & Cook.

ONYX GATHERING Co. 13 miles, 8-12 in. natural gas lines to connect three electrical power plants.

PACIFIC GAS AND ELECTRIC. 294 miles, 42 in. and 110 miles, 36 in. from Malin, Ore., to Fresno County, Calif. $849 MM. Project manager: Bechtel. Completion: November 1993.

PACIFIC GAS TRANSMISSION. 401 miles, 42 in. from Kingsgate, B.C., to Malin, Ore. $841 MM. Engr/PE/CS: Bechtel. Completion: November 1993.

PENINSULA PIPELINE Co. *200 miles, 20-24 in. line from northern Florida to central Florida. $230-320 MM. Completion: 1994.

PHILLIPS PETROLEUM Co. *250 miles, 4-8-10 in. gathering line at San Juan Coal Seam project in Farmington, N.M. under construction. CS: Flint/Four-Way/Foutz &

Bursom. Design: Merrick. Completion: Fall 1993.

SAN DIEGO GAS & ELECTRIC. *80 miles, 36 in. transmission line from South Riverside County to Santee, Calif.

SEAGULL ENERGY Corp. 73 miles, four pipelines from Deer Park, Tex., to Mont Belvieu, Tex.

SHELL PIPELINE Co. 7.3 miles, 121,14 in. line in the Gulf of Mexico from Builwinkle platform to Boxer platform.

SOUTHERN CALIFORNIA GAS Co. *6.3 miles, 24 in. gas line in San Fernando Valley, Calif. Seeking permit. Completion: December 1993.

*6.4 miles, 20 in. gas line between Slauson and Hoillywood stations, Los Angeles, Calif. under construction. Contr: Macco Constructors. Completion: December 1993.

*31.5 miles, 24 in. gas line from Hayfield to Niland, Riverside County, Calif. Planned. Completion: March 1994.

SOUTHERN NATURAL GAS Co. *23.9 miles, 12 in. and 39 miles, 16 in. main line loops at Albany, Ga. Completion: May 1994.

SUNSHINE INTERSTATE TRANSMISSION Co. 170 miles of line near Pascagoula, Miss. to delivery points in Escambia and Okaloosa Counties, Fla. Before FERC.

SUNCOAST PIPELINE Co. Ooint venture of United Gas Pipe Line Co., ANR Pipeline Co., and Florida Power Corp.) 856 miles, 30 in. gas line from Walnut Hill, Fla. to Tampa area to Fort Lauderdale. $1,000 MM.. Completion: Winter 1994-95.

TENNECO GAS. 6.5 miles, 36 in. line in New York. Completion: November 1993.

TENNESSEE GAS PIPELINE Co. *15.6 mile lateral line to a proposed meter station before supplying the Conesville, Ohio power station. Completion: January 1995.

TEXAS EASTERN TRANSMISSION

ooint venture with ANR Pipeline) 204 miles, 30 in. line from existing and proposed gas processing plants in Mobile county, Ala., Northwest to Texas Eastern's main line in Kosciusko, Miss. $153.3 MM. Before FERC.

(Texas Eastern only) 55 mile, 24 in. offshore line from Mobile County, Ala. and future offshore production facilities in the Norphlet trend southwest to a proposed Viosca Knoll extension of the company's Main Pass pipeline system. $72.5 MM.

8 miles of loop and replacement line in Ohio and Penn.

TRANSCANADA PIPELINE (Joint venture with Coastal Corp.)200 miles natural gas line from the Iroquois system at Canajoharie, N.Y. through the southern corner of Vermont to near Boston. Planned. $320 MM.

*200 mile line to extend southeast from the end of the Pacific Gas Transmission Co. system in Oregon through California and Nevada. S130 MM. Completion: 1995.

TRANSCONTINENTAL GAS PIPELINE Co. 23.94 miles, 36 in. loops in Monroe and Luzerne Counties, Pa. Contr: Murphy Bros.

48 miles, 12-30 in. from Edison to Riverdale, N.J. Contr: Napp-Grecco Corp.

5 miles, 36 in. in Morris and Essex Counties, N.J. Contr: Otis Eastern Services Inc.

9.4 miles, 10 in. line on High Island. Tex.

12.2 miles, 16 in. line on Mustang Island, Tex.

47 miles, 30 in. line from pipelines in N.J. across New York Bay to Long Island and into the New York City area terminating near JFK Airport. $115 MM.

*16.48 miles, 30 in. rehab line at Station 50 - MLVSOA10 Opelousas Parish, La. planned. $0.5 MM. Completion: 1994.

*1 6.79 miles, 30 in. rehab line at Sation 80 - MLV8OA1 0 Jones, Jasper and Clark Counties, Miss. Planned. $0.5 MM. Completion: 1994.

*15.13 miles, 30 in. rehab line at Station 100 - MLV10OA10 Chilton and Autuaga County, Ala. Planned. $0.5 MM. Completion: 1994.

*45.77 miles, 30 in. rehab line at Smart Pig Station 190 - Station 195, Howard, Baltimore and Harford, Md. and New York County, Penn. Planned. $6.8 MM. Completion: 1994.

*76.37 miles, 36 in. rehab line at Smart Pig Station 120 - Station 130, Henry, Rockdale, DeKalb, Newton, Walton, Oconee, Clarke and Madison Counties, Ga. Planned. $6.6 MM. Completion: 1994.

*15.39 miles, 30 in. rehab line at Station 120 - MLV12OA10 Henry, Rockdale, Dekalb Counties, Ga. Planned. $0.4 MM. Completion: 1994.

*13.7 miles, 30 in. rehab line at Station 155 - MLV155AlO Davidson County, N.C. Planned. $0.6 MM. Completion: 1994.

*12.9 miles, 36 in. rehab line at Smart Pig MLV20OB27 to Station 505. Planned. $4.2 MM. Completion: 1994.

*9.6 miles, 30 in. rehab replacement line at Rockdale, Henry and Clarke Counties Ga. Planned. $18.3 MM. Completion: 1994.

*30 miles, 42 in. rehab line at Station 205 Morgan, N.J. planned. $1 0 MM. Completion: 1994.

TRANSTEX GATHERING SYSTEM 40 miles, 12 in. from High island block A69 to block Al 09.

UNION PACIFIC RESOURCES. *41 miles, 6-10 in. gathering lines in Uinta County, Wyo. and Rich and Summit Counties, Utah. $44 MM. End 1993.

WILLIAMS NATURAL GAS Co. 30 miles, 6 in. line from Harper, Kan. to Wichita, Kan. Under review.

ABU DHABI

ABU DHABI NATIONAL OIL CO. *153 miles, 10-30 in. line at Habshan. ompletion: December 1995.

*80 miles, 42 in. Bab-Magta-Taweelah Gas Pipeline planned. Completion: December 1994.

ALGERIA

SONATRACH. *90 miles, 8-14 in. gas line from Rhourde Chouff and Rhourde Hamra gas field development in progress. Contr: Snamprogetti. Completion: 1994.

400 miles, 42 in. and 144 miles, 42 in. gas line from Hassi R'Mel to Skikda under construction. Contr: Mannesmann. Completion: 1993.

330 miles gas line of the Maghreb-Europe project to connect with Morocco and Seville, Spain. Algerian portion: Engr/CS: Bechtel. Completion: 1996.

67 miles. 8-12-24 in.-products line under construction. Hamra Natural Gas Process plant. Contr: Snamprogetti. Completion: 1994.

268 miles, LPG line from Alrar-RhourdeHouss to Hassi R'Mel. (phase 1 of a 614 miles of line). Completion: 1996.

ARGENTINA

GOBIERNO PROVINCIA DE CORDOBA. 2.3 miles, 8 in.; 22.9 miles, 6 in.; and 51.6 miles, 3 in. gas line planned from Alma Fuerte to Villa Gral. Belgrano. Contr: Construcciones Protexa. Completion: December 1993.

YFP. Ooint venture with Chile's ENAP) $200 MM trans-Andean oil pipeline project. Completion: Mid-1994

830 miles, 14 in. and 10 miles, 4 in. LPG line under construction from Lugen de Guyo, Medoza to La Metenza, Buenos Aires. Contr: McKee Del Plata SA. Completion: October 1993.

AUSTRALIA

GAS & FUEL CORP OF VICTORIA. 5 miles, 8 in. natural gas line under construction from Dromana to Rosebud. Completion: April 1994.

17 miles, 6 in. natural gas line approved from Paarate to Cobden. Completion: May 1994.

BELGIUM

DISTRIGAZ. 63 miles, 16 in. gas line from Dalhem to Bastogne. Completion: December 1993.

4 miles, 10 in. gas line from Sint-GillisWaas to Sint-Niklaas planned. Completion: December 1993.

4 miles, 10 in. gas line in Gent planned. Completion: December 1994.

19 miles. 12 in. gas line from Lichtervelde to Nieuwpoort. Completion: December 1994.

6 miles, 22-30 in. gas line from Loenhout to Rijkevorsel. Completion: December 1994.

BOLIVIA

YACIMIENTOS PETROLIFEROS FISCALES BOLIVIANOS. Natural gas line from Santa Cruz de la Sierra to Porto Suarez, connecting at Mato Gross do Sul, Brazil.

BRAZIL

PETROLEOS BRASILEIRO. 250 miles, 8-10 in. products line under construction in Madre de Deus/Jequie/itabuna.

165 miles, 8-10 in. products line under construction in Araucaria/Itajai/Florianopolis.

24 miles, 14-16 in. products line under construction in Duque de Caxias/Ilha D'agua.

1,900 miles natural gas line from Santa Cruz, Bolivia to Sao Paulo, Brazil dividing into trunk line near Campinas south to Porto Alegre and spur to existing Rio de JaneiroSao Paulo line. Completion: 1995.

CANADA

ALBERTA GAS TRANSMISSION Div. 51 miles, 4-12 in. line planned in various locations in Alta. Completion: November 1993.

28 miles, 36-42 in. line planned in various locations in Alta. Completion: November 1993.

AMOCO CANADA. 20 miles, 12 in. products line from Edmonton to Fort Saskatchewan. Seeking approval. Completion: December 1993.

BOW RIVER PIPELINE Ltd. 51 miles heavy oil piline to connect with delivery point near Coutts, Alta.

CANADIAN WESTERN NATURAL GAS. 27 miles, 20 in. gas line from Beiseker to East Calgary planned. Contr: MidWest Mgmt. Completion: December 1993.

FOOTHILLS PIPELINES (YUKON) Ltd. 1,429 miles of gas line from the Arctic Coast near Inuvik, North West Territory to Caroline in Central Alberta to connect with existing North American pipeline systems. $4.4 billion. Before NEB. Completion: 1996.

INTERCOASTAL. *to convert 130.3 miles of crude pipeline to a natural gas service at Sarnia, Ont., terminal to Millgrove Juction in Hamilton-Wentworth. Planned.

*12.2 miles, 24 in. line connecting with ANR's system at St. Clair River to IPL's system at Sarnia. Planned.

INTERPROVINCAL PIPE LINE Inc. *422 miles, 16 in. line from Edmonton to Regina, Sask. Seeking permit.

*13.9 miles, 20 in. line to interconnect with Consumers' distribution grid south of Oakville, Ont. Planned.

NOVA CORPORATION OF ALBERTA. *341 miles, 4-12 in. gas line proposed for various locations throughtout Alberta. Completion: December 1994.

*195 miles, 16-48 in. gas line proposed for various locations throughout Alberta. Completion: December 1994.

PACIFIC COAST ENERGY Corp. Ooint venture of Westcoast Energy and Chieftain Development) 118 miles, 10-14 in. Mainland portion of the Vancouver Island pipeline project. Contr: Majestic Contr. Ltd.

PETROLEUM RESOURCES Ltd. 21 miles, sour gas pipeline near Calgary. $14 million. Approval received.

POLAR GAS Ltd. 1,450 miles, 36 in. from Canadian Mackenzie Delta Pipeline Project to Caroline, Alberta planned. Contr: Transcanada Pipelines Ltd./Tenneco Inc./Panarctic Oils Ltd. Completion: 2000-2005.

POUCE COUPE PIPE LNE Ltd. 16 miles of crude line connecting facilities built by Norcen Energy and Canadian Hunter in Northeast B.C. with Peace Pipe system in Northwest Alta.

TRANSCANADA PIPELINES. *19.9 miles, 42 in. natural gas transmission loops near Mattawa, Ont. and Richmond, Ont. Approved. Completion: November 1994.

*65.2 miles, 48 in. natural gas transmission loops between Liebenthal and Grenfell, Sask. Awaiting approval. Completion: November 1994.

*17.5 miles, 48 in. natural gas transmission loops between Arnaud and Emerson, Man, Awaiting approval. Completion: November 1994.

*25.1 miles, 42 in. natural gas transmission loops near Beardmore, Kirkland Lake, and North Bay, Ont. Awaiting approval. Completion: November 1994.

TRANSGAS. 43.5 miles. 8 in. gas line from Wapella, Sask. to Carlyle, Sask. Preliminary design stage. Completion: October 1993.

UNION GAS LTD. *1 1.7 miles, 48 in. gas line from Enniskillen to Brooke, Ont. Planned. Completion: October 1994.

10.9 miles, 48 in. gas line planned from Bright to Cambridge, Ont. Completion: October 1994.

10.2 miles, 20-36 in. gas line from Bickford to Dawn, Ont. planned. Completion: October 1994.

WESTCOAST ENERGY. *28 miles, 24 in. and 14 miles, 12 in. gas line from Sukunka/ Grizzly Area to Chetwynd in design stage. Completion: September 1994.

*101 miles, 20 in. gas line from Tumbler Ridge to Summit Lake, B.C. in planning stage. Completion: 1996.

*20.5 miles, 42 in. gas line looping from Chetwynd to Kamloops, B.C. in planning stage. Completion: October 1994.

CHINA

ARCO CHINA. *438 miles, 28 in. gas submarine line from Yacheng 13-1 production platform to Pearl River Mouth. Design: J.P. Kenny. Contr: Saipem. Completion: 1995.

*44 miles, 28 in. gas submarine line from Pearl River Mouth to Black Point. Design: J.P. Kenny. Completion: 1995.

*62 miles, 14 in. raw gas/gas condensate submarine line form Yacheng 13-1 production platform to Hainan Island. Design: J.P. Kenny. Completion: 1995.

CHINA NATIONAL OIL Corp. 40 miles, 12-20 in. crude and products line planned from Kwang-In to Tau-Yuan. Completion: June 1997.

190 miles, 8-24 in. gas line under construction from Yungan to Tunghsiao. Completion: June 1995.

482 miles, 28 in. trunkline from Yacheun 13-1 field to gas receiving station at Hong Kong.

62 miles, 14 in. gas line to shore base at Sanya on Hainan.

*2,187 miles from Korla in Xinjiang Autonomous Region to Luoyang in Henan Province. Completion: 1997.

CHINA, TAIWAN

CHINESE PETROLEUM Corp. 40 miles, 12-20 in. crude and product line planned in northern oil terminal.

COLOMBIA

ECOPETROL. 17 miles, 8 in. product line from Guacari to Yumbo.

1.6 miles, 24 in. crude line at Pozos Colorados (offshore), planned. Contr: Construcciones Protexa. Completion: February 1994.

72 miles, 12 in. products line planned from Bahja Malaga to Buga (Part 11). Contr: Construcciones Protexa. Completion: March 1994.

PROMIGAS S.A. 373 miles, 20 in. and 2,459 miles, 24 in. gas line from Pajaro to Bogota under study.

7 miles, 4 in. gas line from main gas pipeline to Montelibano planned.

9.3 miles, 3 in. gas line from main gas pipeline to Corozal planned.

12.4 miles, 4 in. gas line from main gas pipeline to Arjona planned.

8.7 miles, 4 in. gas line from Barranquilla to Puerto Colombia planned.

5.4 miles, 3 in. gas line from main gas pipeline to Galapa planned.

COMMONWEALTH OF INDEPENDENT STATES

CASPIAN PIPELINE CONSORTIUM. 500 miles, 42 in. crude line from Grozny to Novorossysk, Russia in preliminary engineering stage. CS Mgr: Willbros. Project Mgr: Bechtel. Completion: Late 1995.

KAZAKHSTAN PIPELINE CO. *1,242 miles oil trunkline under study. Contr: O.T.P. Completion: 1994.

CZECH REPUBLIC

MEROIKL Ltd. Ooint venture of Kaucuk Kralupy and Chemopetrol Litvinov) 211 miles, crude pipeline from lngolstadt, Germany to Kralupy, Czec. Completion: 1995.

DENMARK

DANSK OLIE OG NATURGAS. 5 miles, 12 in. gas line from Kalvebod to HCY power plant. Under design. Completion: 1993 15 miles, 12 in. gas line from Miloy to Svnnemolien under study. Completion: 1993.

ECUADOR

MAXUS ENERGY. 128 miles, 16 in. line from Lago Agrio through Shushutindi in southern part of Block 16. Completion: 1st Qtr. 1995.

91 miles, 4 in. product line for fueling Block 16. Completion: 1st Qtr. 1995.

EGYPT

EGYPTIAN GENERAL PETROLEUM Corp. 119 miles, 16 in. gas line from Shoki6r to Suez under construction. Contr: Petrojet. Completion: December 1993.

*103 miles, 18 in. gas line from El Eaafrana to Kurimat under construction. Contr: Petrojet. Completion: December 1995.

*50 miles, 22 in gas line from Kurimat to Tibeen under construction. Contr: Petrojet. Completion: June 1996.

FINLAND

NESTE OY. 26 mile extension of Nesty Oy's southern Finland gas line into greater Helsinki. Contr: E. M. Pekkinen Oy. Welding and fifting: Zarubezhjneftegasstroi (C.I.S). $10 mm.

FRANCE

ERDGAS VERKAUGS GmbH. *45 miles, 32 in gas line from Lehringen to Kolshorn under construction. Contr: Preussag Aniagenbau/Bohlen. Completion: December 1993.

*30 miles, 24 in, gas line from Kolshorn to Egenstedt planned. Completion: May 1994.

*1 0 miles, 8 in. gas line from Bramsche to Neuenkirchen planned. Completion: November 1993.

GAZ DU SUD OUEST. *110 miles, 32 in. gas line from Toulouse to Narbonne-Argeliers under study. Completion: End 1996.

*30 miles, 12 in. gas line from ToulouseSelih to St. Suipice under study. Completion: End 1994.

*25 miles, 4 in. gas line from Perpignan to Amelie les Bains. Completion: Middle 1994.

SPIE CAPAG. 300 miles, 12 in. product line in the engineering stage. Contr: John Brown. Completion: 1994.

SPMR. 93 miles, 42 in. product line in the engineering stage from La Mede to Buget. Contr: John Brown. Completion: 1993.

GERMANY

BEB. 59 miles, 48 in. gas line (in consortium with Bohlen & Doyen) from Achim to Velzen under construction. Completion: 1993.

46 miles, gas line from Achim to Salzwedel under construction. Contr: Suedrohrbau. Completion: 1991-93.

GASVERSORGUNG SUDDEUTSCHLAND GmbH. 18.6 miles, 20 in. gas line from Pfullendorf to Nenzingen planned. Completion: October 1993.

*16 mile gas line from Scharenstetten to Allmendingen planned. Engr: ILF Munchen. Completion: October 1995.

RHEIN-MAIN-ROHRLEITUNG. 5 miles, 20 in, products line planned/under construction from Koin to Wesseling. Contr: Cryogas Technik. Completion: March 1994.

RUHRGAS AG. 95 miles gas line from Werne to Wefter under construction. Contr: Pipeline Engineering GmbH. Completion: End 1993.

13.8 miles, 24 in. gas line planned from Vinnhorst to Ahlten. Contr: Pipeline Engineering GmbH. Completion: End 1993.

3.7 miles, 12 in. gas line planned from Bonn to Euskirchen. Contr: Pipeline Engineering GmbH. Completion: 1993/94.

102.5 miles, 48 in. gas line planned from Achim to Salzwedel. Completion: End 1993. (Joint venture with BEB Erdgas und Erdol GmbH).

99 miles, 32 in. gas line planned from Breitbrunn to Anawalting. Completion: End 1995. Joint venture with Bayerngas GmbH.

7.9 miles, 12 in. gas line from Rich to Stockstadt planned. Contr: Pipeline Engineering GmbH. Completion: 1993.

7.5 miles, 20 in. gas line planned near Dernbach. Contr: Pipeline Engineering GmbH. Completion: End 1993.

7.7 miles, 12 in. gas line near Messenkamp planned. Contr: Pipeline Engineering GmbH. Completion: End 1994.

16 miles, 16 in. gas line from Laimerstadt to Denkendorf planned. Completion: End 1994.

40 miles, 40 in. gas line from Achim to Wardenburg planned. Completion: End 1994. (Joint venture with BEB Erdgas and Erdol).

124 miles, 44 in. gas line from Salzwedel to Bernau planned. Contr: Pipeline Engineering GmbH. Completion: End 1994. (Joint venture with Verbundnetz Gas).

WINTERSHALL. feasability study for a proposed product line from Wilhelmshaven to Saxony.

397 miles, 32-40 in. Midal gas line between Emden and Ludwigshafen. Ooint venture with Midal GmbH) Completion: 1993.

GREECE

DEPA. *62 miles, 36 in. and 257 miles, 30 in. gas line from Koul'a to Athens under construction. Contr: Machinoimport/Biokat. Completion: End 1994.

HUNGARY

HUNGARIAN OIL AND GAS Co. Ltd. (MOL Ltd.) 43 miles, 30 in. gas line from Gyor to Austrian border in the engineering stage. Completion: 1995.

38 miles, 16 in. gas line under construction from Szank to Kalocasa. Completion: 1994.

INDIA

OIL INDIA Ltd. (Indian Oil Corp.) 840 miles, 22 in. petroleum products line from Kandla, Gujarat, to Bhantinda, Punjab. $240 MM. Consultant: Bechtel. Completion: December 1994.

OIL AND NATURAL GAS COMMISSION.

*60 miles, 4-16 in. products transmission line at Bombay High (South) under construction. $38 MM. Contr: John Brown. CS: Mecon. Completion: 1993.

*48 miles, 4-16 in. products transmission line at Bombay High (South) under construction. $36 MM. Contr: John Brown. CS: L & T. Completion: 1994.

*59 miles, 6-16 in. products transmission line at Bombay High (North & South) under construction. Contr: John Brown. CS: Essar. Completion: 1994.

INDONESIA

650 miles, 10-16 in. products line in the engineering stage in the Trans Java network. Completion: 1993.

ATLANTIC RICHFIELD BALI NORTH Inc. *230 miles, 26 in. gas submarine line from Pagerungan Island to Porong, East Java. Contr: Trans Java Pipeline. Completion: October 1993.

*33 miles, 28 in, gas line from Porong to Gresik. Contr: Trans Java Pipeline. Completion: October 1993.

*2.5 miles, 24 in. and 1.9 miles, 12 in. gas line from Gresik to users. Contr: Trans Java Pipeline. Completion: October 1993.

*5.6 miles, 10 in. subsea and 1.0 mile, 8 in. onshore production gas lines between production wells and Pagerungan Island processing facilities. Contr: P.T. Petrosea. Completion: October 1993.

ATLANTIC RICHFIELD INDONESIA Inc. *17 miles, 18 in. three phrase production line from AVSA field to Zulu Junction. Contr: P.T. McDermott Indonesia. Completion: December 1995.

*5.7 miles 16 in. three phase production line from FSA platform to FFB platform.

Contr: P.T. McDermott Indonesia. Completion: November 1993.

*1.5 miles, 16 in. three phase production line from ZUI platform to Zulu Junction.

Contr: P.T. McDermott Indonesia. Completion: December 1996.

*1.5 miels, 12 in. three phase production line. Contr: P.T. McDermott Indonesia. Completion: December 1996.

*1.9 miles, 12 in. three phase production line. Contr: P.T. McDermott Indonesia. Completion: November 1993.

*1.0 mile, 12 in. three phase production line. Contr: P.T. McDermott Indonesia. Completion: December 1995.

*2.8 miles, 10 in. three phase production line. Contr: P.T. McDermott Indonesia. Completion: November 1993.

*9.7 miles, 10 in. three phase production line. Contr: P.T. McDermott Indonesia. Completion: August 1994.

*1.0 mile, 8 in. three phase production line. Contr: P.T. McDermott Indonesia. Completion: August 1994.

*21 miles. 24 in. produced gas line from NGL B platform to the L Compression platform. Contr: P.T. McDermott Indonesia. Completion: December 1994.

*5.5 miles, 12 in. produced gas line. Contr: P.T. McDermott Indonesia. Completion: November 1993.

*7.6 miles, 8 in. gas lift line. Contr: P.T. McDermott Indonesia. Completion: November 1993.

*1.1 miles, 8 in. produced gas line. Contr: P.T. McDermott Indonesia. Completion: August 1994.

*1.2 miles, 8 in. produced gas line. Contr: P.T. McDermott Indonesia. Completion: 1995.

*4.3 miles, 6 in. gas lift line. Contr: P.T. McDermott Indonesia. Completion: August 1994.

T.B.T. *135 miles, 16 in. Balongan-Jakarta product trunkline under construction. Engr: OTP. Completion: 1994.

IRAN

IGAT 2. 880 miles, 48-56 in. from Kangan gas field on the Persian Gulf to the Soviet Union. Contr: Saipem (will lay 20% of remaining pipeline).

NATIONAL IRANIAN OIL Co. 1,139.6 miles, 12 in. product line from Arak to Malayer and Mamadan.

ITALY

ENEL. 8 miles, 16 in. fuel oil under construction from power station Brinidisi Nord to power station Brindisi Sud. Contr: Techint, Completion: October 1993.

ENICHEM SpA. 139 miles, 8-10 in. product line under construction from Montedison Petrochemical Complex, Ferrara to Enichem Petrochemical Complex, Ravenna.

JAPAN

2,050 miles, plans for a trans-Asian gas pipeline network from Russia and Japan to Indonesia and Australia.

KENYA

KENYA PIPELINES Co. Ltd. 355 miles, 6-8 in. products line from Nairobi to Kisumu/ Eldoret, western Kenya (extension of existing Mombasa to Nairobi pipeline) under construction. Contr: NKK Corp/Lavalin. Completion: 1993.

KUWAIT

Note: Due to the Iraqi invasion/occupation of Kuwait, there has been a lot of damage to the existing pipeline system. Repairing the existing pipelines. Therefore, no plans or projects to construct new cross country pipelines have been made.

LIBYA

416 miles, gas line from Al Brika to Khoms.

MEXICO

PEMEX. 37 miles, 24 in. crude line from Venta de Carpio to Cuemanco under construction.

24 miles, 24 in. gas line from San Pablo to Cuemanco under construction.

77.7 miles, 16 in. gas line from Palmillas to Toluca under construction.

24.2 miles, 24 in. gas line from San Pablo to Cuemanco under construction.

142 miles, 16 in. product line from Salamanca to Tula.

155.3 miles, 12 in. LPG line under construction from Minatitlan to Salina Cruz.

*20.5 miles, 14 in. product line from Minatitlan to Pajaritos under construction.

*144 miles, 12 in. LPG line from Ramal Jaltipan to Salina Cruz under construction.

MOROCCO

900 miles of gas line through Morocco to Tangier to a link across the Strait of Gilbralter to Spain. Completion: 1995.

SOCIETE CHERIFIENNE DES PETROLES. *115 miles, 14 in. oil trunkline under study. Engr: OTP. Completion: 1995.

THE NETHERLANDS

ELF PETROLAND BY. *5 miles, 6 in. gas line from K5D platform to K5A platform in engr. stage. Contr: John Brown. Completion: June 1994.

NY NEDERLANDSE GASUNIE. 7.5 miles, 36 in. natural gas line from Lochem to Lintvelde under construction. Contr: Nacap. Completion: October 1993.

11.4 miles, 48 in. natural gas line from Hommelhof to Schinnen under construction. Contr: Visser & Smit. Completion: October 1993.

4 miles, 42 in. natural gas line from Noordbrock to Midwolda under construction. Contr: Nacap. Completion: October 1993,

12.4 miles, 36 in. natural gas line from

Nispen to Ossendrecht under construction. Completion: October 1993.

*2.8 miles, natural gas line from LNG to Maasviaute under construction. Contr: Visser & Smit Hanab. Completion: October 1993.

*13.7 miles, 36 in. natural gas line from Maasmond to Botlek under construction. Contr: HAK. Completion: October 1993.

*9.6 miles 48 in. natural gas line from Angerlo to Maalderen in design stage. Completion: October 1994.

*15.6 miles, 36 in. natural gas line from Oudisluis to Alkmaar in design stage. Completion: October 1994.

12.4 miles, 18 in. natural gas line from Zegge to Moerdyh in design stage. Completion: October 1994.

*5.4 miles 48 in. natural gas line from Haaldesen to De Grift in design stage. Completion: October 1994.

*3.2 miles, 48 in. natural gas line from Oudbosch to Woezik in functional design stage. Completion: October 1995.

*25 miles, 48 in. natural gas line from Grypskesk to Garrelsweer under study. Completion: October 1996.

UNOCAL TRANSPORTATION. 26 miles, 10 in. gas line from Horizon Platform to Helder Platform in engineering stage. Contr: John Brown/Zeetech Engr. Completion: October 1993.

NIGERIA

NIGERIAN NATIONAL PETROLEUM Corp. 34 miles, 12 in. products line from Port Harcourt to Aba.; 97.5 miles, 12 in. product line from Aba to Enugu; 105.6 miles, 12 in. product line from Enugu to Auchi; 66.9 miles, 12 in. product line from Auchi to Benin City under construction. Contr: Spie-Capag. Completion: February 1994.

*93 miles, 12 in. products trunkline under construction. Engr: OTP. Completion: 1994.

SHELL PETROLEUM DEVELOPMENT.

43 miles, 20-24 in. crude line from Opukushi to Forcados terminal (Trans Ramos Pipeline) under construction. Completion: March 1994.

3.5 miles, 12 in. crude line from Okpokonou flowstation to southern Forcados Pipeline at Ogara Manifold planned. Completion: December 1995.

6 miles, 16 in. crude line from Kanbo flowstation to Trans Ramos Pipeline at Kanbo Manifold planned. Completion: March 1994.

SPIE CAPAG. 300 miles, 12 in. product line in the engineering stage from Port Harcourt to Ore. Contr: OTP. Completion: 1994.

NORWAY

CONOCO NORGE. AS *1.9 miles, 16 in. oil export line and a 1.3 mile, 16 in. gas export line at Heidrun field. $38 MM. Contr: Rockwater Ltd. Completion: April 1994.

STATOIL. (Phase IIA) 186 miles, 40 in. to connect the Troll processing plant at Koilsnes to Sleipner. Engr. stage. Completion: April 1996.

*(Phase IIB) 119 miles, 40 in. gas line from Kollsnes to Heimdal. Pre-engr. stage. Completion: October 1997.

(Phase ill) 31 miles, 42 in. onshore gas line and 375 miles, 40 in. offshore gas line from Dornumersiel to Emden for Europipe Development Project under construction. Engr/PE/CS: Suedrohrbau GmbH. Completion: October 1995.

*157.5 miles. 16 in. gas line from Heidrun to Tjeldbergodden in engr. stage. Completion: December 1996.

*400 miles, 40 in. gas line for the Europipe Development Project from Norway to Germany. Contr: October 1995.

OMAN

PETROLEUM DEVELOPMENT OMAN. 110 mile four pipeline gas system. Contr: Saipem/Consolidated Contr. Co.

PAKISTAN

CRESCENT PETROLEUM Co. Feasability study of 994 miles natural gas line from Doha, Qatar to Karachi.

PARCO. (Pak Arab Refinery Co. Ltd.) 217 miles, 16 in. product line extension into Lahore via Faisalabad in the engineering stage. Engr: OTP. Completion: 1995.

SUI SOUTHERN GAS Co. Ltd. 38 miles, 20 in. gas line from Shikarpur to Larkana, Sindh planned. Completion: June 1994.

75 miles, 24 in. gas line from Kandanwari' to Karachi, Sindh planned. Completion: July 1993.

180 miles, 20 in. gas line from Kandanwari to Karachi, Sindh planned. Completion: July 1994.

PERU

PETROLEOS DEL PERU. 364 miles, 26 in.; 300 miles, 10 in.; 64 miles, 8 in. gas lines from Camisea-Cuzco to Callao-Lima. Bidding. Completion: Mid 1993.

52 miles, 6 in. gas and product line from Aguaytia to Pucallpa-Campo Verde. Completion: 1993.

52 miles, 4 in. product line from Aguaytia to Pucallpa-Campo Verde. Completion: 1993.

30 miles, 3 in. product line from Aguaytia to Pucalipa-Campo Verde. Completion: 1993.

POLAND

*418 miles, gas pipeline system across Poland from Bovankovo and Kharasavei gas fields on Yamal Peninsula to Western Europe.

SAUDI ARABIA

SAUDI ARAMCO. 167 miles, 4-12 in. crude line under construction in the central region of Saudi Arabia. Contr: Suedrohrbau. Completion: September 1994.

210 miles, 24 in. crude flowline project from Hawtah oil field to pump station #3. Contr: Suedrohrbau. Completion: September 1994.

SPAIN

C.L.H. (formerly listed as Campsa) 90 miles, 1 0 in. products line from La Coruna to Vigo under construction. Contr: Tecnicas Reunidas/Heymo. Completion: 1994.

*55 miles, 10 in. product line from Cartagena to Alicante under construction. Completion: 1994.

EMPRESA NACIONAL DE GAS SA. 66 miles, 4-14 in. gas line from Oviedo to Tuy in the engineering stage. Distribution lines for Ferrol, Coruna and Santiago de Compostela. Contr: INITEC.

112 miles, 20 in. gas line from Oviedo to Tuy in the engineering stage. Contr: INITEC.

40 miles, 26 in. gas line from Ferrol to Villalba (Lugo) in the engineering stage. Contr: INITEC.

ENAGAS. 256 miles, gas line from Valencia to Alicante. Contr: Technicas Reunidas/ Heymo Ingenieria. Completion: 1994.

*107 miles, 8-12 in. gas line from Cordoba to Jaen-Granada in engr. stage. Contr: Tecnicas Reunidas/Heymo Ingenieria. Completion: December 1995.

*242 miles, 20 in. and 40 miles, 26 in. gas line in Galicia in engr. stage. Contr: Initec/ Intecsa. Completion: July 1997.

*180 miles, 48 in. gas line from Tarifa to Cordoba in engr. stage. Contr: Heymo Ingenieria/Mannesmann. (Maghreb Pipeline project) Completion: December 1995.

*50 miles, 16 in. line in Campo Gibraltar in engr. stage. Contr: Heymo Ingenieria. Completion: December 1995.

REPSOL PETROLEO SA. 218 miles, 22 in. crude line, and 10 in. gas and products line from Cartagena to Puertollano in the detail design stage. Engr/Const: INITEC. Completion: 1st Qtr. 1996.

SURINAME

STATE OIL Co. of SURINAME. 34.4 miles, 14 in. crude line form Catherina Sophia field to Tout Lui Faut terminal. Contr: Staatsolie.

SWITZERLAND

GASVERBUND OSTCHEWUIZ AG. 29 miles, 20 in. gas line from Ohringen (Winterthur) to Bischofszell. Completion: 1995.

2 miles, 10 in. gas line from Meftlen to Weinfelden. Completion: 1995.

TANZANIA

TAZAMA PIPELINES LTD. 908 miles, 8 in. and 400 miles, 12 in. crude line from Melela to Ndola. Completion: April 1994.

THAILAND

PETROLEUM AUTHORITY OF THAILAND. (PTT). 102 miles, 32 in. and 100 miles, 24 in. gas line, Bongkot-ErawanKhanom, Thailand project. Engr/Contr: Bechtel. Completion: Late 1993.

100.6 miles, 24 in. natural gas line from Erawan to Khanom district to Nakhon Si Thammarat province. Completion: 1994.

106.3 miles, 32 in. natural gas line from PTT's B structure gas field to Unocal Thailand Ltd's Erawan field. Completion: 1993.

146.3 miles, 20 in. oil product line from Sri Racha, Chonburi province to Saraburi province under study. Completion: 1993.

158.8 miles, 10-18-24 in. white products line from Sri Racha, Chonburi province to Saraburi province. Engr: John Brown. CS: Saipem. Completion: 1993. 264 miles, 36 in offshore pipeline and 105 miles, 28 in. onshore line in the Gulf of Thailand. Engr/PE/CS: Bechtel International. Completion: March 1996.

*680 miles, 34 in. and 106 miles, 28 in. natural gas parallel pipeline. Engr/PE/CS: Bechtel. Completion: March 1996.

TUNISIA

SOCIETE TUNISIENNE de L'ELECTRICITE. 82 miles, 20 in. and 66 miles, 24 in. gas line from M'Saken to Gabes projected. Completion: 1994.

SCOGAT. 228 miles, 48 in. gas line under construction. Algeria-Italy Transmediterranean gas pipeline expansion - Tunisia section. Contr: Snamprogetti. Completion: 1994.

UNITED KINGDOM

BP EXPLORATION. 36 in. pipeline to serve Forties field in the U.K. North Sea. Contractor: ETPM Services (U.K.) Ltd.

15 mile, 12 in. natural gas liquids pipeline linking Total Oil Marine plc's St. Fergus, Scotland, gas terminal to BP's Cruden Bay terminal.

BRITISH GAS. 8 miles, 36 in. gas line from Horndon to Tilbury. Contr: Alfred McAlpine Services & Pipelines Ltd. Completion: November 1993.

23 miles, 36 in. gas line from N. Morecambe Gas field to Barrow under construction. Contr: McDermotVETPM. Completion: October 1993.

29 miles, 42 in. gas line from Silk Willoughby to Peterborough. Completion: October 1993.

32 miles, 42 in. gas line from Skitter to Hatton. Completion: October 1993.

12 miles, 36 in. gas line from Huntingdon to St. Neots. Contr: Alfred McAlpine Services & Pipelines Ltd. Completion: October 1993.

CONOCO U.K. Ltd. 7 miles. 16 in. infield pipeline to move Caister gas to Murdock platform.

112 miles, 26 in. export platform from Murdock to Theddlethorpe.

VENEZUELA

CORPOVEN. 105 miles, 36 in crude line and a 20 in. product line planned.

YUGOSLAVIA

MAKPETROL. 62 miles, gas line from Kriva Palanka, U.S.S.R. near the Bulgarian border to the Macedonian republic capital of Skopje, Yugoslavia. Completion: March 1994.

ZIMBABWE

COMPANAI DO PIPELINE MOCAMBIQUE. 180 miles, 10 in. products line rehabilitation from Beira, Mozambique to Feruka, Zimbabwe under construction, Contr: John Brown. Completion: December 1994.