Gasco lets EPC contract for Abu Dhabi pipelines

Oct. 23, 2006
Abu Dhabi Gas Industries Ltd. (Gasco) has awarded National Petroleum Construction Co. (NPCC) an engineering, procurement, construction, and commissioning contract for Package 3 of the Offshore Associated Gases (OAG) project.

Eric Watkins
Senior Correspondent

LOS ANGELES, Oct. 23 -- Abu Dhabi Gas Industries Ltd. (Gasco) has awarded National Petroleum Construction Co. (NPCC) an engineering, procurement, construction, and commissioning contract for Package 3 of the Offshore Associated Gases (OAG) project.

The agreement calls for the construction by March 2009 of 90 km of 30-in. pipeline from Ras Al Qila to Habshan facilities, Habshan plant facilities, substations, equipment shelters, compressor shelter, and associated works.

The contract also covers the construction of 50 km of 36-in. pipeline from Bu Hasa to Habshan facilities, a chemical injection package at Bu Hasa, scraper receiver and slug catcher at Habshan facilities, and a control building at Habshan.

Contact Eric Watkins at [email protected].