Technology and Teamwork Achieve World Class Success for Shell Perdido

Perdido Spar at Technip's fabrication yard in Pari, Finland

In the high-risk ultra deepwater environment, success depends on two key components: technology and teamwork. Shell and Technip have applied innovative technologies and worked in concert as a team to achieve project success and set several world records for the Perdido Regional Host.

 

Resources for Results

 

Shell selected Technip to provide Engineering, Procurement and Construction (EPC) of the Perdido Spar hull and mooring system.

Shell’s choice of Technip as its EPC company is a natural outcome of their long-term working relationship and Technip’s extensive experience in Spar development. In fact, the Perdido Regional Host is the fourteenth Spar delivered by Technip. In 2004, Shell and Technip had accomplished the world’s first installation of steel catenary risers at 1,939 m (6,360 ft) for the Na Kika project.

Technip was able deliver the special aspects of the Perdido project because of its engineering design expertise, industrial assets (manufacturing plants, spoolbases, construction yard) on five continents, and its own fleet of specialized vessels for pipeline installation and subsea construction.

 

Spar at Record Ultra Deepwater Depth

 

Moored in close to 8,000 ft of water, the Perdido Spar is the deepest Spar production facility in the world and the first with DVA (direct vertical access), which will reduce drilling costs, simplify workovers, and facilitate access to subsea equipment. The Spar has a robust design that will help the facility weather extreme hurricanes better than other traditional production platforms.

Technip used its high-technology Deep Blue vessel to lay pipelines and risers for the Shell Perdido project.

Technip’s responsibilities encompassed Spar hull and mooring system design and fabrication, loading out onto a transportation vessel, transportation, and quayside delivery at a yard of the Gulf of Mexico. Technip’s operations and engineering center in Houston performed the overall project management and the global engineering design. The detailed hull design and fabrication was carried out by Technip’s yard in Pori, Finland. It should be noted that the Perdido project delivered the best safety performance to-date, for a Spar delivered from Pori, with no LTT’s in over 2.5 millions manhours worked.

 

Extended Length Flowline and Pipeline

 

Technip has helped set two new industry records associated with the flowlines and risers. Perdido is the deepest reeled flowline installation at a water depth of 2,961 m (9,713 ft). The facility also features the deepest reeled steel catenary riser installation at a water depth of 2,469 m (8,100 ft). The flowline and riser have a total length of 13.2 km (8.2 miles). The pipeline reached a maximum water depth of 9,713 ft along the route.

Perdido Spar as it is being transported to the final outfitting yard in the Gulf of Mexico.

Technip’s operating center in Houston executed the project. The pipeline was welded at the Group’s spoolbase in Mobile, Alabama. The offshore installation was performed using the Deep Blue, Technip’s deepwater pipelay vessel.

 

Umbilicals

 

Technip provided the engineering and manufacture of a total of four dynamic umbilicals, three static umbilicals, and two steel tube flying leads with associated topside and subsea hardware. Technip set another industry record for the umbilicals: the Perdido 1TOB umbilical is the deepest umbilical at 2,946 m (9,666 ft). The total umbilical length was approximately 51,729 m (169,723 ft). Prior to manufacture of themain umbilicals for the project, Technip’s DUCO division had built a prototype umbilical that was subjected to a series of qualification tests to prove the design for the challenging ultra deepwater environment.

Duco 1TOB 3 pass umbilical

 

Technology Driving Opportunity

 

Shell Perdido’s success is a testament to the leadership of both Shell and Technip in turning high risk challenges into safe and high-reward opportunities in the ultra deepwater subsea market. The Shell Perdido project is a great milestone for Technip towards achieving its goal to become a reference company for HS&E, on-time delivery and new technology.

Technip USA, Inc.
11700 Katy Freeway - Suite 150
Houston, Texas 77079
Tel: (281) 870-1111
Website: www.technip.com

Related Articles

Fabricating the Single-Lift Topsides

07/01/2010 The Perdido team faced a tough decision. A conventional topsides design required a series of modules that would have to be fabricated onshore, then...

The Bayou Companies provide welding, coating and insulation services around the world

04/01/2010 Straight on the heels of successfully fabricating and supplying pipe line end terminals (PLET) for Shell’s Ursa/Princess waterflood project, ...

Oceaneering Installs Record Diverless Deepwater HOOPS Tie-in

04/01/2010 Who would cut a perfectly good pipeline? Oceaneering worked with Shell to add a new tie-in for the Perdido oil export pipeline to the currently ope...

Kiewit Offshore Services experience and no surprises approach results in quality services for the offshore oil and gas industry

04/01/2010 KOS’ extensive experience in fabricating large, complex topsides enabled the company to meet the challenges associated with the multi-discipl...

SCHLUMBERGER PIONEERS RECORD DEEPWATER OPEN-HOLE GRAVEL PACK COMPLETIONS

04/01/2010 Two extremes define Perdido’s early development wells: The water is very deep, and the reservoirs are very shallow below the mudline. The dif...

Noble Corp.’s innovative engineering helps Shell to develop Perdido

04/01/2010 Long before the industry dared to dream that operating in the ultra-deepwater of the U.S. Gulf of Mexico could be possible, Noble took a bold and p...

H&Ps Rig 205 ready for Perdido Spar drilling, completions, interventions

04/01/2010

With special modifications, 20,000-ft SCR rig to tackle subsea wells located in up to 9,627 feet of water

HORNBECK OFFSHORE SHELTERED SOME OF PERDIDO’S MOST VALUABLE ASSETS

04/01/2010 As many as 220 people per shift came to work aboard the Perdido deepwater spar during the peak of commissioning and hookup, but it was a short comm...

Halliburton Providing Life-of-Field Solutions for Shell Perdido

04/01/2010 The Shell Perdido project represents an industry milestone in overcoming the technology challenges of ultra-deep waters, subsalt drilling, and comp...

White Papers

AVEVA NET Accesses and Manages the Digital Asset

Global demand for new process plants, power plants and infrastructure is increasing steadily with the ...
Sponsored by

AVEVA’s Approach for the Digital Asset

To meet the requirements for leaner project execution and more efficient operations while transferring...
Sponsored by

Diversification - the technology aspects

In tough times, businesses seek to diversify into adjacent markets or to apply their skills and resour...
Sponsored by

Engineering & Design for Lean Construction

Modern marketing rhetoric claims that, in order to cut out expensive costs and reduce risks during the...
Sponsored by

Object Lessons - Why control of engineering design at the object level is essential for efficient project execution

Whatever the task, there is usually only one way to do it right and many more to do it wrong. In the c...
Sponsored by

Plant Design for Lean Construction - at your fingertips

One area which can provide improvements to the adoption of Lean principles is the application of mobil...
Sponsored by

How to Keep Your Mud System Vibrator Hose from Getting Hammered to Death

To prevent the vibrating hoses on your oilfield mud circulation systems from failing, you must examine...
Sponsored by

Duty of Care

Good corporate social responsibility means implementing effective workplace health and safety measures...
Sponsored by

Available Webcasts


On Demand

Optimizing your asset management practices to mitigate the effects of a down market

Thu, Dec 11, 2014

The oil and gas market is in constant flux, and as the price of BOE (Barrel of Oil Equivalent) goes down it is increasingly important to optimize your asset management strategy to stay afloat.  Attend this webinar to learn how developing a solid asset management plan can help your company mitigate costs in any market.

register:WEBCAST


Parylene Conformal Coatings for the Oil & Gas Industry

Thu, Nov 20, 2014

In this concise 30-minute webinar, participants have an opportunity to learn more about how Parylene coatings are applied, their features, and the value they add to devices and components.

register:WEBCAST


Utilizing Predictive Analytics to Optimize Productivity in Oil & Gas Operations

Tue, Nov 18, 2014

Join IBM on Tuesday, November 18 @ 1pm CST to explore how Predictive Analytics can help your organization maximize productivity, operational performance & associated processes to drive enterprise wide productivity and profitability.

register:WEBCAST


US HYDROCARBON EXPORTS Part 3 — LNG

Fri, Nov 14, 2014

US LNG Exports, the third in a trilogy of webcasts focusing on the broad topic of US Hydrocarbon Exports.

A discussion of the problems and potential for the export of US-produced liquefied natural gas.

These and other topics will be discussed, with the latest thoughts on U.S. LNG export policy.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected