Strategic Development on the Outer Edge

When Shell acquired the ultra-deepwater leases for Perdido in 1996, the technology to develop them didn’t exist. There were other notable deepwater developments, of course. Each had pushed the boundaries of technology, but in solving Perdido’s many technical challenges, Shell has opened new frontiers for oil and gas exploration.

The Perdido oil and gas development covers a portion of the geological formation known as the Perdido Fold Belt. The producing reservoirs lie within the Paleogene or Lower Tertiary zone, a portion of the Gulf of Mexico that has not been produced before. The seabed there resembles a small version of the Grand Canyon, including cliffs with near vertical drops of up to 1,000 feet.

The hub of the Perdido development is some 200 miles due south of Freeport Texas. The nearest neighbor is the Hoover-Diana platform, about 60 miles to the north. Shell began 3D seismic surveys on Perdido in 1998. The discovery well was completed in 2002. Development drilling began in 2007 and is scheduled to continue through 2016.

“There is a lot of courage in this story,” says Bill Townsley, Perdido venture manager. “We purchased the Perdido leases in up to 10,000 feet of water at a time when the industry’s capability was barely 3,000 feet. One of our satellite wellheads will be installed at 9,627 feet.”

 

A workable plan

 

“I joined the project in January of 2005,” says Dale Snyder, Perdido project manager. “By the end of the year, we’d settled on a development concept and begun the front-end engineering and design.”

Dale Snyder, Perdido project manager
Safety, cost and functionality were the project team’s primary concerns. A large tension-leg platform – common on other deepwater developments – wouldn’t work at Perdido because of the extreme water depths. Whatever floats on the surface has to support the weight of everything below, so in Perdido’s case, just the weight of the mooring lines, risers and other equipment hanging from the platform would be overwhelming.

Engineers also had to design for the higher crushing pressures of depths greater than 9,000 feet, and other environmental forces such as storm-driven waves, hurricane-force winds and the Gulf of Mexico’s strong loop currents.

“The deeper you go, the bigger these structures get – unless you break the pattern,” Snyder says. “For Perdido, we also have reservoirs that are atypical for the Gulf of Mexico. Because of low reservoir pressures and the variety of our target zones, Perdido requires a lot of wells.”

There are up to 35 wells in the Perdido development plan. Twenty-two are directly under the spar. A conventional deepwater production system would require 22 risers with all their associated bulk and weight.

“Economically, we just couldn’t make that work,” Snyder says. “It is very expensive to solve the technical problems and operate things at extreme water depths. Beyond that, if you build a mammoth structure, the cost of construction becomes prohibitive. For Perdido, we wanted a new kind of deepwater platform, one that was light enough to be economical, yet big and sturdy enough to contain all the drilling and production equipment we needed to develop the field.”

The Perdido concept design team wanted a central platform with full drilling and production capability onboard. Before Perdido, the world’s deepest water depth for such a platform was 6,300 feet, but several emerging technologies, including direct vertical access to the wells (DVA) and a subsea boosting system allowed the engineering and design team to greatly reduce the size of the structure.

“We needed to be able to pump liquids from the seabed to the surface,” Snyder explains. “In shallower waters, that’s not a big issue, but when the water is a mile and a half deep, it takes a lot of pressure to move fluids up to the platform. Most new reservoirs have enough internal pressure to overcome the hydrostatic pressure above them and push fluids up the wellbore to the surface. Perdido’s reservoirs are relatively low pressure, so we needed a boosting system.”

The other significant challenge was the potential of forming hydrates – an icy mix of water and natural gas that can easily clog flowlines. The solution was to separate gas and liquids on the seabed, then let the subsea boosting system push them to the surface, each through different lines.

Photo provided by Noble Corporation

With that capability, the design team could comingle fluids from all the wells on the seafloor, before pumping it to the surface. It was part of the enabling technology. Instead of 22 production risers from 22 wells, they only needed five, and with just five risers, Perdido could be a much smaller platform.

 

Target Zero

 

From the beginning, the safety of the workforce was a critical design element for the engineering team. No project managers want to have injuries on the job, but the remoteness of the Perdido development presented some unique challenges.

“We started off in 2005 with the idea that Safety was the most important thing we would do on Perdido,” Snyder recalls. “We would get it right. We would be a world leader in safety, and we put tremendous effort into that.”

The design team named their safety program “Target Zero.” The core concept was that if you could convince someone to work safely for just one shift, then it was possible to do the entire project that way. In mid-November, 2009, Perdido reached the milestone of 10 million man hours without a lost-time injury. Even with the wide range of complex operations, high-risk activities and fabrication sites around the world, by the time Perdido reached first oil on March 31, 2010, there were still no known lost-time incidents.

“Of all our accomplishments,” Snyder says, “I am most proud of our safety performance. It shows the leadership and commitment of our teams to go after safety and make it the most important thing we do.”

 

A new frontier

 

As Perdido’s decision executive during the critical offshore installation phase, Lisa Johnson was responsible for integrated project delivery.
The Perdido project is remarkable for its own technical achievements, but there is an even wider significance for the petroleum industry. The Paleogene-era rock that Perdido is tapping is older and deeper that other producing formations that have made the region so prolific. Other operators in the gulf have also made recent discoveries in the Lower Tertiary, but Shell is the first to develop it.

“This is a whole new regime for the Gulf of Mexico,” Snyder says. “Not only have we paved the way by solving the biggest problems of an ultra-deepwater development, it is equally important that we’ve figured out how to produce from the Lower Tertiary. The whole industry is watching to see how we do, because many development companies see this as the next big opportunity.”

 “While the project had its share of inevitable setbacks, the team’s response was outstanding, says Lisa Johnson, who was the decision executive during offshore instllation. “There was always a healthy balance of support and challenge throughout the team, as well as with our Perdido partners.”

Particularly effective was an all-team meeting with the Perdido contractors. Held early in the project, it allowed everyone involved to review various aspects of their work and to identify any

Bill Townsley, Perdido Development venture manager

significant conflicts.

 

Building on a strong partnership

 

“I’ve dealt with a lot of partnerships in my career,” says Bill Townsley, Perdido Development venture manager. “The deepwater environment is no place to be arrogant about your skills. We have  two experienced partners on this project, so one of the things we’ve done is to be very open and transparent with our design and planning. The cooperation between partners has helped to keep us on track and deliver this project on time.”

Related Articles

Fabricating the Single-Lift Topsides

07/01/2010 The Perdido team faced a tough decision. A conventional topsides design required a series of modules that would have to be fabricated onshore, then...

Technology and Teamwork Achieve World Class Success for Shell Perdido

04/01/2010 In the high-risk ultra deepwater environment, success depends on two key components: technology and teamwork. Shell and Technip have applied innova...

The Bayou Companies provide welding, coating and insulation services around the world

04/01/2010 Straight on the heels of successfully fabricating and supplying pipe line end terminals (PLET) for Shell’s Ursa/Princess waterflood project, ...

Oceaneering Installs Record Diverless Deepwater HOOPS Tie-in

04/01/2010 Who would cut a perfectly good pipeline? Oceaneering worked with Shell to add a new tie-in for the Perdido oil export pipeline to the currently ope...

Kiewit Offshore Services experience and no surprises approach results in quality services for the offshore oil and gas industry

04/01/2010 KOS’ extensive experience in fabricating large, complex topsides enabled the company to meet the challenges associated with the multi-discipl...

Noble Corp.’s innovative engineering helps Shell to develop Perdido

04/01/2010 Long before the industry dared to dream that operating in the ultra-deepwater of the U.S. Gulf of Mexico could be possible, Noble took a bold and p...

SCHLUMBERGER PIONEERS RECORD DEEPWATER OPEN-HOLE GRAVEL PACK COMPLETIONS

04/01/2010 Two extremes define Perdido’s early development wells: The water is very deep, and the reservoirs are very shallow below the mudline. The dif...

H&Ps Rig 205 ready for Perdido Spar drilling, completions, interventions

04/01/2010

With special modifications, 20,000-ft SCR rig to tackle subsea wells located in up to 9,627 feet of water

HORNBECK OFFSHORE SHELTERED SOME OF PERDIDO’S MOST VALUABLE ASSETS

04/01/2010 As many as 220 people per shift came to work aboard the Perdido deepwater spar during the peak of commissioning and hookup, but it was a short comm...
White Papers

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by

What is System Level Thermo-Fluid Analysis?

This paper will explain some of the fundamentals of System Level Thermo-Fluid Analysis and demonstrate...

Accurate Thermo-Fluid Simulation in Real Time Environments

The crux of any task undertaken in System Level Thermo-Fluid Analysis is striking a balance between ti...

6 ways for Energy, Chemical and Oil and Gas Companies to Avert the Impending Workforce Crisis

As many as half of the skilled workers in energy, chemical and oil & gas industries are quickly he...
Sponsored by
Available Webcasts

On Demand

Global LNG: Adjusting to New Realities

Fri, Mar 20, 2015

Oil & Gas Journal’s March 20, 2015, webcast will look at how global LNG trade will be affected over the next 12-24 months by falling crude oil prices and changing patterns and pressures of demand. Will US LNG production play a role in balancing markets? Or will it add to a growing global oversupply of LNG for markets remote from easier natural gas supply? Will new buyers with marginal credit, smaller requirements, or great need for flexibility begin to look attractive to suppliers? How will high-cost, mega-projects in Australia respond to new construction cost trends?

register:WEBCAST


US Midstream at a Crossroads

Fri, Mar 6, 2015

Oil & Gas Journal’s Mar. 6, 2015, webcast will focus on US midstream companies at an inflection point in their development in response to more than 6 years shale oil and gas production growth. Major infrastructure—gas plants, gathering systems, and takeaway pipelines—have been built. Major fractionation hubs have expanded. Given the radically changed pricing environment since mid-2014, where do processors go from here? What is the fate of large projects caught in mid-development? How to producers and processors cooperate to ensure a sustainable and profitable future? This event will serve to set the discussion table for the annual GPA Convention in San Antonio, Apr. 13-16, 2015.

This event is sponsored by Leidos Engineering.

register:WEBCAST


The Future of US Refining

Fri, Feb 6, 2015

Oil & Gas Journal’s Feb. 6, 2015, webcast will focus on the future of US refining as various forces this year conspire to pull the industry in different directions. Lower oil prices generally reduce feedstock costs, but they have also lowered refiners’ returns, as 2015 begins with refined products priced at lows not seen in years. If lower per-barrel crude prices dampen production of lighter crudes among shale plays, what will happen to refiners’ plans to export more barrels of lighter crudes? And as always, refiners will be affected by government regulations, particularly those that suppress demand, increase costs, or limit access to markets or supply.

register:WEBCAST


Oil & Gas Journal’s Forecast & Review/Worldwide Pipeline Construction 2015

Fri, Jan 30, 2015

The  Forecast & Review/Worldwide Pipeline Construction 2015 Webcast will address Oil & Gas Journal’s outlooks for the oil market and pipeline construction in a year of turbulence. Based on two annual special reports, the webcast will be presented by OGJ Editor Bob Tippee and OGJ Managing Editor-Technology Chris Smith.
The Forecast & Review portion of the webcast will identify forces underlying the collapse in crude oil prices and assess prospects for changes essential to recovery—all in the context of geopolitical pressures buffeting the market.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected