Riser System at Perdido Features Newest GE Oil & Gas Tensioners

Top-tensioned production, drilling risers only alternative for record deepwater truss spar installation over DVA wells

In the post-Katrina/Rita Gulf of Mexico hurricane era, new met ocean criteria and acceptance requirements for “100-year and 1000 year” events calls for both new and improved elements to be incorporated into the design of deepwater drilling and production equipment.

Because the spar is the industry’s deepwater and ultra-deepwater floating production platform of choice, new changes are being made in the tensioning and motion compensation hardware necessary to stabilize risers on spars against heavy storm wave and wind forces. One such progression involves the choice of ram-type, or “push-up” tensioners for top-tensioned vertical production and drilling/workover risers. Shell Exploration & Development’s Perdido Regional Development Spar is equipped with this type of riser tensioning equipment supplied by GE Oil & Gas (formerly GE Vetco Gray).

Perdido spar riser tensioners in various stages of installation prior to installation of the topsides. The six tensioners are in two rows in the center square of the spar deck. The three units on the bottom row are installed complete and stroked down (closed) awaiting commissioning. The remaining units on the top row are in various stages of installation.

From the beginning Shell, as operator for BP and Chevron, planned to employ a direct vertical access (DVA) configuration at the Perdido spar’s host location in the Great White field in order to bring oil and natural gas production from the field’s subsea wet tree wells to the spar’s topsides for subsequent handling and export back to shore. This would be the first such DVA setup to be installed on a truss-type spar.

Top-tensioned risers were essential for the Perdido spar, at a record depth of some 7,820 ft (2,384m) from spar topsides to the sea floor. Buoyancy can tensioned risers employed on spar platforms in much shallower water would have been impracticable.

An assembled Perdido riser tensioner during factory acceptance testing, partially stroked out, but without the accumulators.

Additionally, instead of having a riser and dry tree for each well, the spar would be equipped with only six risers – five pipe-in-pipe risers for handling production from multiple subsea wells and one high-pressure riser for drilling and completions. Instead of being connected with individual wells, the production risers would be connected to five seafloor caisson/electric submersible pump (ESP) boosting stations that would handle flow from 22 subsea DVA wells and 11 subsea offset wells. In addition to increased efficiency due to lighter weight, having only six risers would help keep the spar’s topsides decks smaller and thus, less capital intensive.

The single, high-pressure DVA drilling riser would be used to allow a topside-mounted rig to drill, complete and to perform interventions on wells at significantly lower cost than employing deepwater mobile rigs for such purposes. In addition, the topside rig would use this riser to gain access to the seafloor booster stations for possible change-out of ESP equipment, should that become necessary.

 

First offshore installation

 

Six GE Oil & Gas hydraulic/pneumatic tensioners were installed to support the risers aboard the Perdido spar. The installation was made at the spar’s offshore site rather than the conventional installation at a shore base prior to float-out. This was the first time such a remote offshore ram riser tensioner installation has been made.

In general, riser tensioners are designed to provide the necessary interface to support riser weight and to compensate for relative motion due to spar offset, heave, thermal expansion, payload changes and subsidence. A typical MODU drilling riser tensioner consists of a hydraulic cylinder with sheaves at both ends. The cylinder is connected to a number of high-pressure gas bottles, or accumulators, via a medium separator. A wire rope is rigged in the cylinder with one end connected to the fixed part of the tensioner and the other end is connected to the riser.

Top-tensioned risers connected directly to the spar hull provide a range of stiffness at the hang-off point. This stiffness variation provides a tradeoff between riser stroke relative to the hull and the tension on the riser, and combined with lower operating costs, are the practical alternative to buoyancy can-supported riser systems.

The GE Oil & Gas ram-type riser tensioner configuration uses multiple (four) hydro-pneumatic compression cylinders that employ efficient, low-fluid volume to allow for large internal accumulator volumes that, depending upon the application, minimize the requirement for external accumulators while providing for the required range of stiffness. Combined with durable construction and relative low accumulator pressures, the GE Oil & Gas tensioners help reduce risk elements and increase tensioner life. Being small in footprint versus their capacity, they also allow for more available topsides deck space.

Each of the GE Oil & Gas tensioners is equipped with four hydro-pneumatic cylinders, each operating independent of the other but combined, constitute a “team.”. Should trouble be experienced with any one cylinder, it can be easily removed and either repaired at the site or sent to shore. Meanwhile, as evidenced by testing under load at GE’s Houston manufacturing center, the remaining three cylinders are capable of holding sufficient tension to continue required motion compensation.

 

Coating reliability enhanced

 

To help meet Shell’s 25-year lifespan design requirement and provide high reliability in a corrosive environment, the rods of the Perdido spar riser tensioners are protected with a newly developed coating that virtually eliminates the threat of degradation by acids contained in oilfield chemicals.

Tensioner pressure feedback is monitored and adjusted with equipment located in the Spar topsides control room.

Significant to its continued innovation and development of new hardware, GE Oil & Gas riser tensioner technology was a finalist for the Woelfel Best Mechanical Engineering Achievement Award at the 2009 Offshore Technology Conference.

GE Oil & Gas
4424 W. Sam Houston Parkway North
Suite 100
Houston, Texas 77041
Tel: 281-448-4410
Website: www.geoilandgas.com

Related Articles

Fabricating the Single-Lift Topsides

07/01/2010 The Perdido team faced a tough decision. A conventional topsides design required a series of modules that would have to be fabricated onshore, then...

Technology and Teamwork Achieve World Class Success for Shell Perdido

04/01/2010 In the high-risk ultra deepwater environment, success depends on two key components: technology and teamwork. Shell and Technip have applied innova...

The Bayou Companies provide welding, coating and insulation services around the world

04/01/2010 Straight on the heels of successfully fabricating and supplying pipe line end terminals (PLET) for Shell’s Ursa/Princess waterflood project, ...

Oceaneering Installs Record Diverless Deepwater HOOPS Tie-in

04/01/2010 Who would cut a perfectly good pipeline? Oceaneering worked with Shell to add a new tie-in for the Perdido oil export pipeline to the currently ope...

Kiewit Offshore Services experience and no surprises approach results in quality services for the offshore oil and gas industry

04/01/2010 KOS’ extensive experience in fabricating large, complex topsides enabled the company to meet the challenges associated with the multi-discipl...

Noble Corp.’s innovative engineering helps Shell to develop Perdido

04/01/2010 Long before the industry dared to dream that operating in the ultra-deepwater of the U.S. Gulf of Mexico could be possible, Noble took a bold and p...

SCHLUMBERGER PIONEERS RECORD DEEPWATER OPEN-HOLE GRAVEL PACK COMPLETIONS

04/01/2010 Two extremes define Perdido’s early development wells: The water is very deep, and the reservoirs are very shallow below the mudline. The dif...

H&Ps Rig 205 ready for Perdido Spar drilling, completions, interventions

04/01/2010

With special modifications, 20,000-ft SCR rig to tackle subsea wells located in up to 9,627 feet of water

HORNBECK OFFSHORE SHELTERED SOME OF PERDIDO’S MOST VALUABLE ASSETS

04/01/2010 As many as 220 people per shift came to work aboard the Perdido deepwater spar during the peak of commissioning and hookup, but it was a short comm...
White Papers

2015 Global Engineering Information Management Solutions Competitive Strategy Innovation and Leadership Award

The Frost & Sullivan Best Practices Awards recognise companies in a variety of regional and global...
Sponsored by

Three Tips to Improve Safety in the Oil Field

Working oil fields will always be tough work with inherent risks. There’s no getting around that. Ther...
Sponsored by

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by
Available Webcasts


Driving Growth and Efficiency with Deep Insights into Operational Data

When Wed, Aug 19, 2015

Capitalizing on today’s momentum in Oil & Gas requires operational excellence based on a clear view of what your business data is telling you. Which is why nearly half* of oil and gas companies have deployed SAP HANA or have it on their roadmap.

Join SAP and Red Hat to learn more about using data to drive process improvements and identify new opportunities with the SAP HANA platform running on Red Hat Enterprise Linux. This webinar will also show how your choice of infrastructure impacts the performance of core business applications and your ability to achieve data-driven insights quickly and reliably.

*48% use SAP, http://go.sap.com/solution/industry/oil-gas.html

register:WEBCAST



On Demand

OGJ's Midyear Forecast 2015

Fri, Jul 10, 2015

This webcast is to be presented by OGJ Editor Bob Tippee and Senior Economic Editor Conglin Xu.  They will summarize the Midyear Forecast projections in key categories, note important changes from January’s forecasts, and examine reasons for the adjustments.

register:WEBCAST


Predictive Analytics in your digital oilfield - Optimize Production Yield and Reduce Operational Costs

Tue, Jul 7, 2015

Putting predictive analytics to work in your oilfield can help you anticipate failures, plan and schedule work in advance, eliminate emergency work and catastrophic failures, and at the same time you can optimize working capital and improve resource utilization.  When you apply analytic capabilities to critical production assets it is possible to reduce non-productive time and increase your yield.

Learn how IBM's analytics capabilities can be applied to critical production assets with the goal of reducing non-productive time, increasing yield and reducing operations costs.

register:WEBCAST


Cognitive Solutions for Upstream Oil and Gas

Fri, Jun 12, 2015

The oil & gas sector is under pressure on all sides. Reserves are limited and it’s becoming increasingly expensive to find and extract new resources. Margins are already being squeezed in an industry where one wrong decision can cost millions. Analyzing data used in energy exploration can save millions of dollars as we develop ways to predict where and how to extract the world’s massive energy reserves.

This session with IBM Subject Matter Experts will discuss how IBM Cognitive Solutions contribute to the oil and gas industry using predictive analytics and cognitive computing, as well as real time streaming for exploration and drilling.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected