Oceaneering Installs Record Diverless Deepwater HOOPS Tie-in

The Oceaneering International, Inc. Olympic Intervention IV vessel working near the Shell Peridido spar. Shell and Oceaneering have a long-standing relationship that has achieved excellent results in subsea projects in the Gulf of Mexico and other deepwater regions throughout the world.

Who would cut a perfectly good pipeline? Oceaneering worked with Shell to add a new tie-in for the Perdido oil export pipeline to the currently operating Hoover Offshore Oil Pipeline System (HOOPS) pipeline. This is the first time in deepwater operations anywhere in the world that a flowing pipeline without a pre-existing connection has been shut-in and re-configured to tie-in a new pipeline.

The installation took place as the result of the partnership between Shell’s design team and Oceaneering’s installation team. Contributing to the remarkable success story were Oceaneering’s high-technology Olympic Intervention IV support vessel, remotely operated vehicles (ROVs), ROV simulation capabilities, and a diverless installation team that worked in concert to achieve the desired results with only a short, 17-day interruption of downstream production of the HOOPS pipeline.

 

Tie-in Concept

 

The Perdido host facility operates in ultra-deep waters of the Alaminos Canyon Block 857 that had no production export infrastructure. The closest tie-in opportunity was at HOOPS, which extends from the ExxonMobil Hoover platform to Freeport, Texas. HOOPS did not have a connection link so it was necessary to perform the deepwater installation of a connection point to a working pipeline with minimal production shut in. Based on its experience with the repair of the Mars pipeline after Hurricane Katrina, Shell designed the hardware and a subsea process for the Perdido tie-in. Oceaneering facilitated Shell’s design feasibility using diverless intervention with ROVs.

 Oceaneering’s scope for the tie-in consisted of fabricating and assembling the subsea hardware components, then performing system integration, operations planning, simulation, and subsea execution in 4500 fsw. Oceaneering’s Deepwater Technical Solutions (DTS) group developed many of the cleaning, clamping and cutting tools used in the Perdido operation.

 

Mission Simulation

 

Oceaneering used their onshore ROV simulator system to perform the preinstallation sequence. This process allowed the ROV pilots to become familiar with the tools they would be using and to practice installation procedures under true subsea conditions. Once the installation vessel mobilized, a portable ROV simulator system was used offshore on the job.

Oceaneering lifting the dual-hub connection assembly using the 150-mt active heave-compensated crane on the deck of the Olympic Intervention IV.

 

Olympic Intervention IV Vessel

 

The 312-ft Olympic Intervention IV subsea support vessel and crew performed the installation using built-in dual Millennium® Plus ROVs. The Olympic Intervention IV features a 150-mt active heave compensated crane that was used for overboarding the connection equipment. The vessel transmitted streaming video for real-time work observation by shore personnel during the job. The heave-compensated ROV launch and recovery system onboard the Olympic Intervention IV lowered the ROVs from the surface and transported the specialized tooling required for the job.

The weld seam and Fusion Bond Epoxy (FBE) removal tool used subsea to prepare the HOOPS pipeline for adding a tie-in connection. Photo courtesy of Shell.

 

ROV Operation

 

The two separate ROV systems were staffed with multiple crews for 24-hour operations and were utilized for around-the-clock subsea work. The two systems usually worked together to complete the required tasks. In many cases, one ROV would perform the work while the second ROV directed the task from a better position near the worksite. High-definition cameras allowed the pilots to view the hardware in finer detail than possible with conventional filming technology.

Two Millennium® Plus ROVs work in tandem to check pipeline ovality prior to pipeline cutting operations.

 

Subsea Execution

 

The Perdido tie-in was accomplished using an innovative 70-ft long, 14-ft high, 50-ton foundation, which served as a structural support and work table that provided the means to align the pipeline connection. The foundation remains in place on the sea floor, where it can be used for future repair and maintenance operations.

Two lift frames were used to raise the 18-in pipeline about 3 ft off the seabed. Using winches and buoyancy gauged to 60,000 lb, Oceaneering’s crew pulled the foundation into place between the lift frames. With the foundation in place, Oceaneering used an ROV-operated Fusion Bond Epoxy (FBE) and weld seam removal tool to clean the existing HOOPS pipe and prepare it for connector installation. The pipeline was then sealed off locally on each side using isotope-embedded pigs. An ROV verified the pig locations before a 28-ft section of pipe was cut and removed. Spool assemblies were then landed onto the foundation, rolled into place and connected to the pipelines, leaving vertical hubs to re-connect the existing pipeline via a pre-fabricated jumper and an additional hub to connect the Perdido Oil Export pipeline.

Millennium® Plus ROV surveys the completed jumper installation and subsea tie-in at 4500 fsw.

 

Success Story with No Ending

 

The HOOPs tie-in is only one of Oceaneering’s success stories for Perdido and many other deepwater projects. Whenever or wherever there is a challenging subsea opportunity, Oceaneering is always available with its intervention expertise and experience.

OCEANEERING® and MILLENNIUM® are registered trademarks of Oceaneering International, Inc.

Oceaneering International, Inc.
11911 FM 529, Houston, Texas 77041 U.S.A.
Tel: +1 (713) 329-4568
Fax: +1 (713) 329-4951
Website: www.oceaneering.com

Related Articles

Fabricating the Single-Lift Topsides

07/01/2010 The Perdido team faced a tough decision. A conventional topsides design required a series of modules that would have to be fabricated onshore, then...

Technology and Teamwork Achieve World Class Success for Shell Perdido

04/01/2010 In the high-risk ultra deepwater environment, success depends on two key components: technology and teamwork. Shell and Technip have applied innova...

The Bayou Companies provide welding, coating and insulation services around the world

04/01/2010 Straight on the heels of successfully fabricating and supplying pipe line end terminals (PLET) for Shell’s Ursa/Princess waterflood project, ...

Kiewit Offshore Services experience and no surprises approach results in quality services for the offshore oil and gas industry

04/01/2010 KOS’ extensive experience in fabricating large, complex topsides enabled the company to meet the challenges associated with the multi-discipl...

SCHLUMBERGER PIONEERS RECORD DEEPWATER OPEN-HOLE GRAVEL PACK COMPLETIONS

04/01/2010 Two extremes define Perdido’s early development wells: The water is very deep, and the reservoirs are very shallow below the mudline. The dif...

Noble Corp.’s innovative engineering helps Shell to develop Perdido

04/01/2010 Long before the industry dared to dream that operating in the ultra-deepwater of the U.S. Gulf of Mexico could be possible, Noble took a bold and p...

H&Ps Rig 205 ready for Perdido Spar drilling, completions, interventions

04/01/2010

With special modifications, 20,000-ft SCR rig to tackle subsea wells located in up to 9,627 feet of water

HORNBECK OFFSHORE SHELTERED SOME OF PERDIDO’S MOST VALUABLE ASSETS

04/01/2010 As many as 220 people per shift came to work aboard the Perdido deepwater spar during the peak of commissioning and hookup, but it was a short comm...

Halliburton Providing Life-of-Field Solutions for Shell Perdido

04/01/2010 The Shell Perdido project represents an industry milestone in overcoming the technology challenges of ultra-deep waters, subsalt drilling, and comp...

White Papers

AVEVA NET Accesses and Manages the Digital Asset

Global demand for new process plants, power plants and infrastructure is increasing steadily with the ...
Sponsored by

AVEVA’s Approach for the Digital Asset

To meet the requirements for leaner project execution and more efficient operations while transferring...
Sponsored by

Diversification - the technology aspects

In tough times, businesses seek to diversify into adjacent markets or to apply their skills and resour...
Sponsored by

Engineering & Design for Lean Construction

Modern marketing rhetoric claims that, in order to cut out expensive costs and reduce risks during the...
Sponsored by

Object Lessons - Why control of engineering design at the object level is essential for efficient project execution

Whatever the task, there is usually only one way to do it right and many more to do it wrong. In the c...
Sponsored by

Plant Design for Lean Construction - at your fingertips

One area which can provide improvements to the adoption of Lean principles is the application of mobil...
Sponsored by

How to Keep Your Mud System Vibrator Hose from Getting Hammered to Death

To prevent the vibrating hoses on your oilfield mud circulation systems from failing, you must examine...
Sponsored by

Duty of Care

Good corporate social responsibility means implementing effective workplace health and safety measures...
Sponsored by

Available Webcasts


On Demand

Optimizing your asset management practices to mitigate the effects of a down market

Thu, Dec 11, 2014

The oil and gas market is in constant flux, and as the price of BOE (Barrel of Oil Equivalent) goes down it is increasingly important to optimize your asset management strategy to stay afloat.  Attend this webinar to learn how developing a solid asset management plan can help your company mitigate costs in any market.

register:WEBCAST


Parylene Conformal Coatings for the Oil & Gas Industry

Thu, Nov 20, 2014

In this concise 30-minute webinar, participants have an opportunity to learn more about how Parylene coatings are applied, their features, and the value they add to devices and components.

register:WEBCAST


Utilizing Predictive Analytics to Optimize Productivity in Oil & Gas Operations

Tue, Nov 18, 2014

Join IBM on Tuesday, November 18 @ 1pm CST to explore how Predictive Analytics can help your organization maximize productivity, operational performance & associated processes to drive enterprise wide productivity and profitability.

register:WEBCAST


US HYDROCARBON EXPORTS Part 3 — LNG

Fri, Nov 14, 2014

US LNG Exports, the third in a trilogy of webcasts focusing on the broad topic of US Hydrocarbon Exports.

A discussion of the problems and potential for the export of US-produced liquefied natural gas.

These and other topics will be discussed, with the latest thoughts on U.S. LNG export policy.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected