Kiewit Offshore Services experience and no surprises approach results in quality services for the offshore oil and gas industry

KOS’ extensive experience in fabricating large, complex topsides enabled the company to meet the challenges associated with the multi-discipline Perdido Project. KOS’ topsides scope required the installation of 82,000 linear ft of piping, and over 800,000 linear ft of electrical cable. In addition, KOS fabricated 1,500 tons of skidshoes to support the structure during the construction, loadout and transportation phases. The 10,000 ton structure was completed in 24 months.

The fabrication sequence for constructing the topsides was designed to permit all craft disciplines to start work as early as possible, optimizing the number of craft on each component of the Perdido Project. The topsides were fabricated in three major sub-assemblies, or deck levels, and lifted into position using heavy lift cranes. The largest of these sub-assemblies weighed over 1,300 short tons and was lifted into place using twelve crawler cranes.

Perdido topside lift and spar hull at the KOS fabrication facility.

In addition to the Perdido topside fabrication, KOS facilitated the outfitting of the 22,000 ton spar hull for offshore installation. Utilizing KOS’ deep hole, the spar was offloaded from the heavy lift transport vessel, grillage and supports removed, motion dampening strakes installed and a dead weight survey conducted.

KOS’ third scope in the Perdido Project was the drill rig refurbishment, where the company focused on upgrading an existing rig’s capacity and equipment, as well as updating its hurricane tie down requirements. After pieces of the drill rig arrived at KOS, they were further dismantled and reconditioned. These components were assembled into modules and the drill rig was stacked, commissioned and function tested. Once testing was complete, the drill rig was dismantled, loaded out and shipped offshore to the spar hull.

The Perdido topside loadout at KOS’ facility.

KOS and its subcontractors worked over 2 million manhours on the Perdido Project, completing the job with only two incidents. As an OSHA Voluntary Protection Program (VPP) site, KOS is recognized as having one of the safest yards in the industry. It’s not just the company’s safety practices that make KOS stand alone, but the facility itself is truly impressive. Accessible by highway, rail and water, the KOS fabrication facility boasts more than 2,900 linear ft of high-capacity bulkhead. Water depths along the bulkhead range from 25-55 ft with the entire length supported by a continuous-pile-founded relieving platform. This allows for the docking of several large scale projects at the same time. For heavy lift vessel projects such as Perdido, KOS has a deep hole with water depths up to 78 ft. The facility also has unimpeded access to the Gulf of Mexico through the Corpus Christi and La Quinta shipping channels, and boasts the world’s only Heavy Lifting Device capable of lifting up to 13,000 tons. Projects like Perdido are executed successfully due to the extensive resources available at KOS and the talented people building them.

No job is too large or too complex for this leading fabricator for the oil and gas industry. KOS takes a “no surprises” approach to every project, enabling the company to plan ahead and mitigate risks. This mentality, coupled with their state-of-the-art facility, has enabled KOS to help its clients build the industry’s most well known projects such as Perdido.

Kiewit Offshore Services
2440 Kiewit Road, Ingleside, Texas 78362
Tel: 361-775-4300, Fax: 361-775-4433
Website: www.kiewit.com

Related Articles

Fabricating the Single-Lift Topsides

07/01/2010 The Perdido team faced a tough decision. A conventional topsides design required a series of modules that would have to be fabricated onshore, then...

Technology and Teamwork Achieve World Class Success for Shell Perdido

04/01/2010 In the high-risk ultra deepwater environment, success depends on two key components: technology and teamwork. Shell and Technip have applied innova...

The Bayou Companies provide welding, coating and insulation services around the world

04/01/2010 Straight on the heels of successfully fabricating and supplying pipe line end terminals (PLET) for Shell’s Ursa/Princess waterflood project, ...

Oceaneering Installs Record Diverless Deepwater HOOPS Tie-in

04/01/2010 Who would cut a perfectly good pipeline? Oceaneering worked with Shell to add a new tie-in for the Perdido oil export pipeline to the currently ope...

SCHLUMBERGER PIONEERS RECORD DEEPWATER OPEN-HOLE GRAVEL PACK COMPLETIONS

04/01/2010 Two extremes define Perdido’s early development wells: The water is very deep, and the reservoirs are very shallow below the mudline. The dif...

Noble Corp.’s innovative engineering helps Shell to develop Perdido

04/01/2010 Long before the industry dared to dream that operating in the ultra-deepwater of the U.S. Gulf of Mexico could be possible, Noble took a bold and p...

H&Ps Rig 205 ready for Perdido Spar drilling, completions, interventions

04/01/2010

With special modifications, 20,000-ft SCR rig to tackle subsea wells located in up to 9,627 feet of water

HORNBECK OFFSHORE SHELTERED SOME OF PERDIDO’S MOST VALUABLE ASSETS

04/01/2010 As many as 220 people per shift came to work aboard the Perdido deepwater spar during the peak of commissioning and hookup, but it was a short comm...

Halliburton Providing Life-of-Field Solutions for Shell Perdido

04/01/2010 The Shell Perdido project represents an industry milestone in overcoming the technology challenges of ultra-deep waters, subsalt drilling, and comp...

White Papers

What is System Level Thermo-Fluid Analysis?

This paper will explain some of the fundamentals of System Level Thermo-Fluid Analysis and demonstrate...

Accurate Thermo-Fluid Simulation in Real Time Environments

The crux of any task undertaken in System Level Thermo-Fluid Analysis is striking a balance between ti...

6 ways for Energy, Chemical and Oil and Gas Companies to Avert the Impending Workforce Crisis

As many as half of the skilled workers in energy, chemical and oil & gas industries are quickly he...
Sponsored by

AVEVA NET Accesses and Manages the Digital Asset

Global demand for new process plants, power plants and infrastructure is increasing steadily with the ...
Sponsored by

AVEVA’s Approach for the Digital Asset

To meet the requirements for leaner project execution and more efficient operations while transferring...
Sponsored by

Diversification - the technology aspects

In tough times, businesses seek to diversify into adjacent markets or to apply their skills and resour...
Sponsored by

Engineering & Design for Lean Construction

Modern marketing rhetoric claims that, in order to cut out expensive costs and reduce risks during the...
Sponsored by

Object Lessons - Why control of engineering design at the object level is essential for efficient project execution

Whatever the task, there is usually only one way to do it right and many more to do it wrong. In the c...
Sponsored by

Available Webcasts



The Future of US Refining

When Fri, Feb 6, 2015

Oil & Gas Journal’s Feb. 6, 2015, webcast will focus on the future of US refining as various forces this year conspire to pull the industry in different directions. Lower oil prices generally reduce feedstock costs, but they have also lowered refiners’ returns, as 2015 begins with refined products priced at lows not seen in years. If lower per-barrel crude prices dampen production of lighter crudes among shale plays, what will happen to refiners’ plans to export more barrels of lighter crudes? And as always, refiners will be affected by government regulations, particularly those that suppress demand, increase costs, or limit access to markets or supply.

register:WEBCAST


Oil & Gas Journal’s Forecast & Review/Worldwide Pipeline Construction 2015

When Fri, Jan 30, 2015

The  Forecast & Review/Worldwide Pipeline Construction 2015 Webcast will address Oil & Gas Journal’s outlooks for the oil market and pipeline construction in a year of turbulence. Based on two annual special reports, the webcast will be presented by OGJ Editor Bob Tippee and OGJ Managing Editor-Technology Chris Smith.
The Forecast & Review portion of the webcast will identify forces underlying the collapse in crude oil prices and assess prospects for changes essential to recovery—all in the context of geopolitical pressures buffeting the market.

register:WEBCAST



On Demand

Optimizing your asset management practices to mitigate the effects of a down market

Thu, Dec 11, 2014

The oil and gas market is in constant flux, and as the price of BOE (Barrel of Oil Equivalent) goes down it is increasingly important to optimize your asset management strategy to stay afloat.  Attend this webinar to learn how developing a solid asset management plan can help your company mitigate costs in any market.

register:WEBCAST


Parylene Conformal Coatings for the Oil & Gas Industry

Thu, Nov 20, 2014

In this concise 30-minute webinar, participants have an opportunity to learn more about how Parylene coatings are applied, their features, and the value they add to devices and components.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected