H&Ps Rig 205 ready for Perdido Spar drilling, completions, interventions

With special modifications, 20,000-ft SCR rig to tackle subsea wells located in up to 9,627 feet of water

When Shell Exploration and Production Co., as operator for the Perdido Regional Development Spar, decided to contract for a small-footprint, fit-for-purpose drilling rig in order to access 35 existing wells connected to the spar as well as to drill as many as nine additional wells from the spar itself, it chose Helmerich & Payne, Inc. (H&P), Tulsa, for the job.

With nearly four decades of platform drilling experience and more than two decades of experience working for Shell on a number of fixed and floating platforms both in the Gulf of Mexico and overseas, H&P assigned its Platform Rig 205 for the Perdido spar.

The self-erecting rig was modified for drilling, completions and well interventions specifically from a truss spar, and was mobilized to Perdido in summer, 2009. No stranger to drilling from both fixed and floating production facilities, H&P built Rig 205 in 2002. It was then used by Shell on its Cognac fixed and Ram Powell tension-leg platforms (TLP), both located in the deepwater Gulf.

 

Rig upgraded for spar topsides

 

According to Rig 205 superintendent Tom Freeny, the rig was upgraded due to the increased motion and acceleration forces affecting the Perdido spar, which is anchored in some 8,000 ft (2,383 m) of water. The rig’s drilling module is supported by a custom skid base that spans the spar’s 65-ft (19.8 m) capping beams and is designed to be assembled by the spar’s two pedestal cranes.

Rig 205 also has been upgraded in a number of other areas, Freeny said. These include draw works disc brakes, a 49-1⁄2-in. rotary table with PS-21 slips, a “Cyclone” Iron Roughneck, and a 16-3⁄4-in. x 5,000-psi BOP with setback dolly positioning, among others.

“Interfacing with Shell was required for installing and tying down several individual support packages,” he pointed out. These included a pipe rack module, with engines and the SCR house; a porch for the third mud pump, P-tanks, a diesel tank and four auxiliary mud tanks, among other attributes.

Helmerich & Payne’s offshore Rig 205 rests tightly atop the Perdido Spar.

Considerations for the design of a more robust hurricane tie-down system included anticipated spar accelerations due to high winds and sea states, said Freeny. For increased safety and environmental protection, the rig also features beefed-up systems for handling increased hook load and setback, as well as more user-friendly rig floor equipment to eliminate manual torque wrenches, hammers, etc.

The Perdido spar features the first application of wet tree, direct vertical access (DVA) wells from a spar-type floating production system. It is fitted with a single high-pressure drilling and completion riser suspended from the topsides for access to the 34 subsea trees, 22 of them located directly below the structure. This configuration will allow Rig 205 to use a surface blowout preventer (BOP) to drill, complete and later sidetrack those and subsequent individually drilled wells to 19,000 ft (5,795 m) or more.

Because the DVA configuration permits the rig to access a larger number of subsea completions, Shell anticipates the benefit of significant drilling and completions savings without loss of rig flexibility.

The rig also is equipped to install and intervene on the five electric submersible pumps contained in seafloor caissons that are used for the spar’s subsea separation and boosting system.

 

Close cooperation pays off

 

Freeny and his Rig Managers, Jimmy Welch and Tony Miller, were included in both preliminary planning and actual topsides design meetings by Shell, he said.

“It became necessary to add some unique features to the rig to meet Shell’s requirements,” said Freeny. “Without constant communications between both companies, working together as a cohesive team, there could have been delays. As it was, the rig was modified and ready for mobilization to the spar at the appointed time.”

 

 

 

 

Helmerich & Payne, Inc.
1437 South Boulder Ave., Tulsa, Oklahoma 74119
Tel: (918) 742-5531
Fax: (918) 742-0237
Website: www.hpinc.com

Related Articles

Fabricating the Single-Lift Topsides

07/01/2010 The Perdido team faced a tough decision. A conventional topsides design required a series of modules that would have to be fabricated onshore, then...

Technology and Teamwork Achieve World Class Success for Shell Perdido

04/01/2010 In the high-risk ultra deepwater environment, success depends on two key components: technology and teamwork. Shell and Technip have applied innova...

The Bayou Companies provide welding, coating and insulation services around the world

04/01/2010 Straight on the heels of successfully fabricating and supplying pipe line end terminals (PLET) for Shell’s Ursa/Princess waterflood project, ...

Oceaneering Installs Record Diverless Deepwater HOOPS Tie-in

04/01/2010 Who would cut a perfectly good pipeline? Oceaneering worked with Shell to add a new tie-in for the Perdido oil export pipeline to the currently ope...

Noble Corp.’s innovative engineering helps Shell to develop Perdido

04/01/2010 Long before the industry dared to dream that operating in the ultra-deepwater of the U.S. Gulf of Mexico could be possible, Noble took a bold and p...

Kiewit Offshore Services experience and no surprises approach results in quality services for the offshore oil and gas industry

04/01/2010 KOS’ extensive experience in fabricating large, complex topsides enabled the company to meet the challenges associated with the multi-discipl...

SCHLUMBERGER PIONEERS RECORD DEEPWATER OPEN-HOLE GRAVEL PACK COMPLETIONS

04/01/2010 Two extremes define Perdido’s early development wells: The water is very deep, and the reservoirs are very shallow below the mudline. The dif...

HORNBECK OFFSHORE SHELTERED SOME OF PERDIDO’S MOST VALUABLE ASSETS

04/01/2010 As many as 220 people per shift came to work aboard the Perdido deepwater spar during the peak of commissioning and hookup, but it was a short comm...

Halliburton Providing Life-of-Field Solutions for Shell Perdido

04/01/2010 The Shell Perdido project represents an industry milestone in overcoming the technology challenges of ultra-deep waters, subsalt drilling, and comp...
White Papers

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by

What is System Level Thermo-Fluid Analysis?

This paper will explain some of the fundamentals of System Level Thermo-Fluid Analysis and demonstrate...
Available Webcasts


The Alternative Fuel Movement: Four Need-to-Know Excise Tax Complexities

When Thu, Jun 4, 2015

Discussion on how to approach, and ultimately embrace, the alternative fuel market by pulling back the veil on excise tax complexities. Taxes may be an aggravating part of daily operations, but their accuracy is crucial in your path towards business success.

register:WEBCAST



On Demand

Prevention, Detection and Mitigation of pipeline leaks in the modern world

Thu, Apr 30, 2015

Preventing, detecting and mitigating leaks or commodity releases from pipelines are a top priority for all pipeline companies. This presentation will look at various aspects related to preventing, detecting and mitigating pipeline commodity releases from a generic and conceptual point of view, while at the same time look at the variety of offerings available from Schneider Electric to meet some of the requirements associated with pipeline integrity management. 

register:WEBCAST


Global LNG: Adjusting to New Realities

Fri, Mar 20, 2015

Oil & Gas Journal’s March 20, 2015, webcast will look at how global LNG trade will be affected over the next 12-24 months by falling crude oil prices and changing patterns and pressures of demand. Will US LNG production play a role in balancing markets? Or will it add to a growing global oversupply of LNG for markets remote from easier natural gas supply? Will new buyers with marginal credit, smaller requirements, or great need for flexibility begin to look attractive to suppliers? How will high-cost, mega-projects in Australia respond to new construction cost trends?

register:WEBCAST


US Midstream at a Crossroads

Fri, Mar 6, 2015

Oil & Gas Journal’s Mar. 6, 2015, webcast will focus on US midstream companies at an inflection point in their development in response to more than 6 years shale oil and gas production growth. Major infrastructure—gas plants, gathering systems, and takeaway pipelines—have been built. Major fractionation hubs have expanded. Given the radically changed pricing environment since mid-2014, where do processors go from here? What is the fate of large projects caught in mid-development? How to producers and processors cooperate to ensure a sustainable and profitable future? This event will serve to set the discussion table for the annual GPA Convention in San Antonio, Apr. 13-16, 2015.

This event is sponsored by Leidos Engineering.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected