FMC Technologies sets the global standard for advanced subsea technology

Shell’s Perdido project is FMC Technologies’ second full field development utilizing subsea oil and gas separation and boosting following the contract to supply trees and other equipment for Shell’s Parque das Conchas (formerly called BC-10) deepwater project offshore Brazil. Parque das Conchas is the first full field development utilizing subsea oil and gas separation and subsea pumping in Brazil. A number of new and advanced technologies and innovations were designed by FMC to meet Parque das Conchas’ numerous challenges. Many of those technologies are deployed in Shell’s Perdido field.

“Shell wanted to exploit subsea heavy oil reserves,” said Brad Beitler, FMC’s Vice President of Technology, explaining the similarities of the Perdido and Parque das Conchas fields. “Shell had experience with submersible pumps but not with seabed pumps.

A caisson separator being deployed in the Gulf of Mexico.

“Shell designed the systems and we worked with them as an alliance partner.”

FMC’s scope of work for Perdido included the supply of 17 subsea trees, two subsea manifolds, five subsea caisson separation and boosting systems, topside and subsea controls, and related subsea equipment. The project utilized FMC’s globally managed product standards, supporting manufacturing and supply networks and project management processes.

 

Record-setting innovative enhanced vertical deepwater trees

 

The Perdido field includes 17 of FMC’s Enhanced Vertical Deepwater Trees (EVDT) that provide added value by allowing customers to use the same standard tree design anywhere in the world. The added value brings versatility, installation savings and operational efficiency to ultra-deepwater fields. The EVDT earned FMC the 2008 Spotlight on Technology Award at that year’s Offshore Technology Conference. The trees are rated for high pressure conditions up to 10,000 psi.

The EVDT system also enables deepwater completions from a small drilling rig containing only a surface blowout preventer (BOP). This capability allows operators to eliminate the need for expensive deepwater rigs with a subsea BOP, resulting in significant time and cost savings.

The EVDT was used to set a subsea deepwater completion record of 9,356 ft installed in Shell’s Silvertip field, a part of the Perdido development. FMC set the previous water depth record of 8,995 ft, also in the Gulf of Mexico, in 2007. This record may be surpassed yet again during 2010 with a well planned for the Tobago field, also one of the fields feeding into the Perdido spar. This well would be in about 9,600 ft of water and will be completed using an EVDT system.

 

Subsea separation and boosting system

 

The Perdido project contains five caisson separators that were installed on the seabed. This innovative system separates gas and liquids before the hydrocarbons are pumped back to the surface, enabling increased oil recovery by removing about 2,000 psi of back pressure from the wells.

“Gas flows up the riser while liquid is boosted by the electrical submersible pumps using multiphase separation,” Beitler explained.

Utilizing the seabed separation system reduced the number of production risers to the spar to five, saving significant weight and cost.

FMC’s subsea systems encompass a wide range of equipment and technologies to explore, drill and develop offshore oil and gas fields. Whether it’s high-pressure/high-temperature (HP/HT) trees and wellheads, subsea controls and systems or production optimization services, FMC adds value to its customers throughout the life of the field.

FMC Technologies capitalized on the growing demand for deepwater oil and gas production with its subsea separation, boosting and processing systems. The company provides the technology to increase oil recovery for mature projects and develop new projects that may otherwise be considered economically unviable or inaccessible.

FMC Technologies
1803 Gears Rd., Houston TX 77067
Tel: 281 591 4000
Fax: 281 591 4102
Website: www.fmctechnologies.com

Related Articles

Fabricating the Single-Lift Topsides

07/01/2010 The Perdido team faced a tough decision. A conventional topsides design required a series of modules that would have to be fabricated onshore, then...

Technology and Teamwork Achieve World Class Success for Shell Perdido

04/01/2010 In the high-risk ultra deepwater environment, success depends on two key components: technology and teamwork. Shell and Technip have applied innova...

The Bayou Companies provide welding, coating and insulation services around the world

04/01/2010 Straight on the heels of successfully fabricating and supplying pipe line end terminals (PLET) for Shell’s Ursa/Princess waterflood project, ...

Oceaneering Installs Record Diverless Deepwater HOOPS Tie-in

04/01/2010 Who would cut a perfectly good pipeline? Oceaneering worked with Shell to add a new tie-in for the Perdido oil export pipeline to the currently ope...

Kiewit Offshore Services experience and no surprises approach results in quality services for the offshore oil and gas industry

04/01/2010 KOS’ extensive experience in fabricating large, complex topsides enabled the company to meet the challenges associated with the multi-discipl...

SCHLUMBERGER PIONEERS RECORD DEEPWATER OPEN-HOLE GRAVEL PACK COMPLETIONS

04/01/2010 Two extremes define Perdido’s early development wells: The water is very deep, and the reservoirs are very shallow below the mudline. The dif...

Noble Corp.’s innovative engineering helps Shell to develop Perdido

04/01/2010 Long before the industry dared to dream that operating in the ultra-deepwater of the U.S. Gulf of Mexico could be possible, Noble took a bold and p...

H&Ps Rig 205 ready for Perdido Spar drilling, completions, interventions

04/01/2010

With special modifications, 20,000-ft SCR rig to tackle subsea wells located in up to 9,627 feet of water

HORNBECK OFFSHORE SHELTERED SOME OF PERDIDO’S MOST VALUABLE ASSETS

04/01/2010 As many as 220 people per shift came to work aboard the Perdido deepwater spar during the peak of commissioning and hookup, but it was a short comm...

White Papers

AVEVA NET Accesses and Manages the Digital Asset

Global demand for new process plants, power plants and infrastructure is increasing steadily with the ...
Sponsored by

AVEVA’s Approach for the Digital Asset

To meet the requirements for leaner project execution and more efficient operations while transferring...
Sponsored by

Diversification - the technology aspects

In tough times, businesses seek to diversify into adjacent markets or to apply their skills and resour...
Sponsored by

Engineering & Design for Lean Construction

Modern marketing rhetoric claims that, in order to cut out expensive costs and reduce risks during the...
Sponsored by

Object Lessons - Why control of engineering design at the object level is essential for efficient project execution

Whatever the task, there is usually only one way to do it right and many more to do it wrong. In the c...
Sponsored by

Plant Design for Lean Construction - at your fingertips

One area which can provide improvements to the adoption of Lean principles is the application of mobil...
Sponsored by

How to Keep Your Mud System Vibrator Hose from Getting Hammered to Death

To prevent the vibrating hoses on your oilfield mud circulation systems from failing, you must examine...
Sponsored by

Duty of Care

Good corporate social responsibility means implementing effective workplace health and safety measures...
Sponsored by

Available Webcasts


On Demand

Optimizing your asset management practices to mitigate the effects of a down market

Thu, Dec 11, 2014

The oil and gas market is in constant flux, and as the price of BOE (Barrel of Oil Equivalent) goes down it is increasingly important to optimize your asset management strategy to stay afloat.  Attend this webinar to learn how developing a solid asset management plan can help your company mitigate costs in any market.

register:WEBCAST


Parylene Conformal Coatings for the Oil & Gas Industry

Thu, Nov 20, 2014

In this concise 30-minute webinar, participants have an opportunity to learn more about how Parylene coatings are applied, their features, and the value they add to devices and components.

register:WEBCAST


Utilizing Predictive Analytics to Optimize Productivity in Oil & Gas Operations

Tue, Nov 18, 2014

Join IBM on Tuesday, November 18 @ 1pm CST to explore how Predictive Analytics can help your organization maximize productivity, operational performance & associated processes to drive enterprise wide productivity and profitability.

register:WEBCAST


US HYDROCARBON EXPORTS Part 3 — LNG

Fri, Nov 14, 2014

US LNG Exports, the third in a trilogy of webcasts focusing on the broad topic of US Hydrocarbon Exports.

A discussion of the problems and potential for the export of US-produced liquefied natural gas.

These and other topics will be discussed, with the latest thoughts on U.S. LNG export policy.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected