Oneok to invest in Bakken, Woodford shale projects

May 3, 2010
Oneok Partners LP, Tulsa, will invest $405-470 million through yearend 2011 to expand gathering and processing in the Bakken shale in the Williston basin in North Dakota and the Woodford shale in Oklahoma.

Oneok Partners LP, Tulsa, will invest $405-470 million through yearend 2011 to expand gathering and processing in the Bakken shale in the Williston basin in North Dakota and the Woodford shale in Oklahoma. These projects are part of a previously announced $2.5-3.5 billion investment plan.

North Dakota

Included is construction of the 100-MMcfd Garden Creek gas processing plant in eastern McKenzie County, ND, and related expansions. Oneok estimates these expansions will cost $150-210 million and double the partnership's processing capacity in the Williston basin. Completion is expected in fourth-quarter 2011.

In addition to the plant, Oneok's gas gathering and processing segment will invest $200-205 million during 2010-11 for well connections, expansions, and upgrades to Bakken shale gas gathering.

These investments include expansion and upgrade of gas gathering and addition of compression to serve the Garden Creek plant; gas gathering and compression upgrades to bring the existing 100-MMcfd Grasslands gas plant in McKenzie County to full capacity by yearend; and $90 million to connect more than 300 wells in 2010 and about 400 wells in 2011 to the partnership's Williston basin gathering system.

In March 2009, Oneok completed a $46 million expansion of the Grasslands plant and since 2007 has invested more than $80 million in well connections and gas gathering upgrades.

Oneok COO Terry K. Spencer said producers with large acreage dedications to Oneok's assets "continue to aggressively develop these areas and need additional infrastructure." With a gathering system of more than 3,500 miles, Oneok says it is the largest independent operator of gas gathering and processing facilities in the Bakken shale.

Oklahoma

In 2010-11, Oneok will invest an additional $55 million in the Woodford shale on gas gathering and processing and NGL segments. These investments will connect the partnership's western Oklahoma gas gathering to its existing 135-MMcfd Maysville gas plant in Garvin County in central Oklahoma. The project is under construction and expected to be completed during this year's fourth quarter. These investments also include about $20 million for well connections in 2010-11 to gather more Woodford shale volumes.

In its NGL segment, spending plans include the expansion of the existing Oklahoma NGL gathering system to connect to the 200-MMcfd gas plant under construction by Devon in Canadian County, Okla. and expected to be completed by yearend or early 2011. This expansion will increase accessibility of this supply to the partnership's Arbuckle pipeline and Mont Belvieu, Tex., fractionation.

Since 2007, Oneok says, it has invested about $70 million in the Woodford shale.

More Oil & Gas Journal Current Issue Articles
More Oil & Gas Journal Archives Issue Articles
View Oil and Gas Articles on PennEnergy.com