Special Report: Composites provide repair to hot, high-pressure gas line

Aug. 19, 2002
Composite materials have been used on Amerada Hess Ltd.'s floating production platform AH001 to repair a high pressure, high temperature carbon-steel gas compression line. The platform is on the Ivanhoe field in the UK North Sea.

Composite materials have been used on Amerada Hess Ltd.'s floating production platform AH001 (Fig. 1) to repair a high pressure, high temperature carbon-steel gas compression line. The platform is on the Ivanhoe field in the UK North Sea.

Amerada Hess' AH001 works on the UK Continental Shelf producing oil from Ivanhoe, Rob Roy, and Hamish fields on 15/21A (Fig. 1).
Click here to enlarge image

The line had suffered severe localized wall thinning from external corrosion. A welded repair was not an option because the plant was live; complex geometries made a clamp impractical, according to composite supplier FD Alliance (FDA), a joint venture of DML Ltd. and Furmanite International Ltd.

Amerada Hess said a repair option was needed that would restore structural integrity of the damaged pipe for its expected 5-7 year lifespan. Composites could deal with the awkward geometry of the 8-in. to 4-in. reducing tee.

The gas line operates at 124° C. and 80 barg, which made the repair have to be cured at more than 20° C. above this temperature.

Composite material could be made to conform to the tight, irregular space in this repair of a badly corroded segment of high-pressure gas line aboard AH001 (Fig. 2).
Click here to enlarge image

The corrosion damage was fully assessed and the main area of corrosion identified at the 6 o'clock position on the 8-in. pipe, directly below the 4-in. branch (Fig. 2).

Production ongoing

Because no hotwork was required for the repair, production was able to continue with the gas flow diverted to a parallel line. For safety reasons, the damaged line was depressurized before the critical preparation stages of the repair.

Surface preparation is usually carried out by use of grit-blasting, requiring a finish of SA 2.5 (75 μm) for optimum bonding. For this repair, the required surface finish was achieved with wet quill blasting.

A fiberglass tie-coat was then applied, providing a high-quality interface between the pipe's surface and electrical insulation to avoid the possibility of galvanic reaction.

With these preparations in place, the resin-impregnated carbon fiber was applied. The resin matrix is precalculated and quality assessment checks were carried out at every stage of application.

Layers of composites were built up according to a specific design thickness, in this case 16 mm, achieving multi-axial strength. For the purposes of this project, the strength and stiffness derived from a composite repair (up to ten times the strength and twice the stiffness of steel) was a key benefit because the line operates at such high pressure.

Finally, a sacrificial peel ply layer was applied to remove excess resin and provide a surface finish ready to accept paint or any other finish that may be required.

Click here to enlarge image

Fig. 3 shows the various components of the composite repair.

For this specific project, the high operating temperatures required a specialist curing technique that actually used the pipe's heat to aid the cure.

To achieve the specified post-cure temperature, trace heating was applied to the pipe as it was brought back to full functionality. As the pipe began to re-pressurize and heat to operating temperature, the cure temperature remained constant at >20° C. above the pipe operating temperature, eventually achieving the required 144° C.

AH001 was able to remain at full production, some 17,000 b/d, during the period of the repair.