Jacket, wellhead platform installed in Madura BD field

Nov. 9, 2015
Husky Energy Inc. reported installation of the jacket and wellhead platform for Madura BD gas-condensate field offshore Indonesia.

Husky Energy Inc. reported installation of the jacket and wellhead platform for Madura BD gas-condensate field offshore Indonesia (OGJ Online, Oct. 29, 2010).

Development drilling in 35 m of water is expected to begin soon, with start of production expected in 2017.

Construction of a floating production, storage, and offloading vessel to process gas and liquids production is about 30% complete. Fixed price, set volume gas sales agreements are in place for Madura BD field.

Husky said other developments offshore Indonesia are expected to add production during 2017-19. They include the combined MDA-MBH fields and the MDK field, which is planned to be tied into the MDA-MBH field infrastructure.

A tendering process is under way for an FPSO for MDA-MBH, and a fixed price, set volume sales gas agreement is in place. A gas price/volume contract for MDK is being negotiated.

Husky has 40% interest in the Indonesia projects. CNOOC Ltd. is operator, and an affiliate of Samudra Energy Ltd. of Indonesia is a partner.