Contract let to return Nigerian refinery to nameplate capacity

Nigerian National Petroleum Corp. (NNPC), through a service provider, has let a contract to General Electric Co. to provide gas turbines to be used to generate a reliable, uninterrupted supply of power to NNPC’s refining complex in Port Harcourt, Nigeria, that would enable the complex to return to its full production capacity.

GE will deliver three, 25-Mw, trailer-mounted TM2500+ aeroderivative gas turbines to GEL Utility Ltd., a subsidiary of independent power producer Genesis Electricity Ltd., with whom NNPC signed a 20-year power purchase agreement in November 2013 for the Port Harcourt refinery, GE said in an Aug. 4 news release.

In addition to delivery of the gas turbines, whichwill provide both the baseload and backup power to support refining operations at Port Harcourt, the recent agreement also includes the future modernization of Nigeria’s other two existing refineries, GE said.

The installation of the mobile gas turbines at the Port Harcourt refinery, Nigeria’s largest, is intended to guarantee the plant has the power it needs to overcome chronic grid outages in the region that have presently reduced production at the Port Harcourt complex to 30% of its total maximum nameplate capacity of 210,000 b/d, according to GE.

The three gas turbine units are scheduled to enter commercial operation in August, at which time the Port Harcourt refinery will have the necessary power to return to its full operational capacity, GE said.

In addition to the Port Harcourt complex—which is comprised of two refineries that, together, have a combined installed capacity of 210,000 b/d—NNPC also owns two additional Nigerian refineries, including its 110,000-b/d refinery in Kaduna and a 125,000-b/d refinery in Warri.

All three refineries recently have operated below their installed nameplate capacities, according to the latest data available from NNPC.

During the month of March, crude oil throughputs at the Kaduna refinery averaged about 38,700 b/d, while the Warri refinery processed about 28,000 b/d of crude.

No crude throughputs were reported at the Port Harcourt refinery during March, according to NNPC’s latest data.

Related Articles

INTERNATIONAL BRIEFS

01/01/1990 WESTCOAST ENERGY INC., Vancouver, B.C., agreed to buy the utilities and propane business of Inter-City Gas Corp. (ICG), Winnipeg, Man., for $720 mi...

HOW INDEXES HAVE RISEN

01/01/1990 Continuing a trend starting in 1983, the Nelson-Farrar refinery construction index rose slowly, from 1106.2 in January 1987, to 1184.1 in December ...

OGJ NEWSLETTER

01/01/1990 Will oil price stability dominate the 1990s? Analyst Philip Verleger thinks so. Using a measure of market concentration the U.S. government uses t...

DOE PRESSES CLEAN COAL PROGRAM

01/01/1990 The U.S. Department of Energy has chosen 13 more clean coal technology (CCT) projects in its third round of competition. If private sponsors and DO...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected