Dana Gas lets contract for platform in Zora field

Dana Gas has let a $17 million contract for fabrication of a platform for the Zora gas field. The contract is with Adyard Abu Dhabi, a subsidiary of Interserve PLC.

Dana Gas in 2012 signed agreements with the governments of Sharjah and Ajman to develop the field offshore the two emirates.

The platform will be installed in 24 m of water. Dana Gas expects to start delivering 40 MMcfd in first-half 2015. Gas will be transported by a 35-km pipeline to an onshore processing facility in Sharjah.

“This contract is the first strategically significant development towards bringing the Zora gas field on stream,” said Patrick Allman-Ward, chief executive officer of Dana Gas. He anticipates capital investment of $160 million during the project execution phase.

Related Articles

BHI: US drilling rig count holds steady at 1,931

09/19/2014

The US drilling rig count was unchanged at 1,931 rigs working during the week ended Sept. 19, Baker Hughes Inc. reported.

Cenovus starts production from Phase F at Foster Creek oil sands project

09/19/2014 Cenovus Energy Inc., Calgary, started oil production earlier this month at its recently completed Phase F expansion at its Foster Creek oil sands p...

Inpex to increase recovery, lifespan at Minami-Nagaoka field

09/19/2014 Inpex Corp. plans to upgrade facilities at its Koshijihara plant to enhance natural gas and condensate recovery at Minami-Nagaoka gas field in Japan.

Wild Well completes second capping stack

09/18/2014 Wild Well Control Inc., a subsidiary of Superior Energy Services, has completed a subsea capping stack stationed in Singapore to serve the area dur...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected