KMEP, Valero start up Parkway Pipeline

Construction has been completed of the 141-mile, 16-in. Parkway Pipeline, a 50-50 joint venture of Kinder Morgan Energy Partners LP (KMEP) and Valero Energy Corp., and the line is now transporting petroleum products from refineries in Norco, La., to an existing petroleum transportation hub in Collins, Miss., owned by Plantation Pipe Line Co. KMEP owns 51% of Plantation Pipe Line Co. and operates the system.

From this hub, the products will be transported by multiple pipeline systems, including Plantation, that serve the eastern US. The $250 million pipeline system has an initial capacity of 110,000 b/d and can be expanded to more than 200,000 b/d.

At its peak construction time, Parkway generated 1,200 temporary jobs, KMEP said.

Construction on the pipeline began in August 2012 (OGJ Online, Aug. 23, 2012).

Related Articles

ETP unit gets FERC approval for gas exports to Mexico

03/21/2014 Energy Transfer Partners LP unit Houston Pipe Line Co. LP (HLPC) has received approval from the US Federal Energy Regulatory Commission to build a ...

Millennium Pipeline appoints president

03/20/2014 Millennium Pipeline Co. LLC has selected Joseph Shields as its president. He succeeds Rocco D’Alessandro, who held the position beginning in May 20...

Shah Deniz II, South Caucasus Pipeline contracts awarded

03/20/2014 The Shah Deniz and South Caucasus Pipeline consortia awarded project management and construction contracts for the development of Shah Deniz Stage ...

MARKET WATCH: NYMEX crude prices rise on Seaway pipeline expansion news

03/19/2014 Crude oil futures prices rose on the New York market Mar. 18 after Enterprise Products Partners LP told analysts and investors that an expanded Sea...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected