Genscape: TransCanada’s Gulf Coast Pipeline ‘slightly behind schedule’

Construction of TransCanada Corp.’s 36-in. OD, 485-mile, Keystone Gulf Coast Pipeline (KGCP) is slightly behind schedule, according to Genscape Inc.’s most recent aerial surveillance of the project Aug. 18. TransCanada described construction on Aug. 20 as more than 90% complete, with an expected in-service date of yearend. Genscape believes this estimate to be optimistic and sees first-quarter 2014 as more realistic. The bulk of work remaining on the project is centered on the Cushing pumping station and along the pipeline right-of-way, Genscape said.

At TransCanada’s Cushing terminal, four of the seven newly constructed tanks have hydrotested with a fifth tank currently hydrotesting. Mixer installation and tank pipeline connections, however, have yet to be completed for any of the seven new tanks, Genscape said. Genscape believes completed tank capacity and associated connections are necessary for KGCP’s 3.2-million bbl initial linefill and that it will take 40-60 days to fill the line once construction is complete. The terminal, when complete, will have 2.25-million bbl of storage.

Genscape observed exposed pipe near the Tupelo, Bryan, Delta, and Lake Tyler, Tex. sites. It observed crews working on pipeline connectivity along the ROW. The Cromwell, Bryan, and Winnsboro pumping stations each have four pumps installed, according to Genscape, and pipeline infrastructure looks to be nearing completion. Ground preparation continues at the Tupelo, Delta, and Lake Tyler facilities.

KGCP will ship oil from Cushing, Okla., to Nederland, Tex., with an initial capacity of 700 million b/d, expandable to 830 million b/d.

Related Articles

NGSA asks Congress to pass bills facilitating LNG exports

03/27/2014 The Natural Gas Supply Association called on Congress to support legislation that would facilitate more LNG exports. “Exporting LNG overseas will h...

US, European energy leaders to discuss gas diversification measures

03/27/2014 Top US government energy officials and their counterparts from other G7 nations will meet early next week to discuss reducing Europe’s heavy relian...

Santos buys gas reserves for Queensland LNG plant

03/27/2014 The WestSide Corp.-Mitsui joint venture has been let a contract to supply gas to the Santos Ltd.-led Gladstone LNG project for 20 years beginning i...

Total, CNOOC sign LNG cooperation agreement

03/26/2014 Total SA and China National Offshore Oil Corp. (CNOOC) have reached an LNG cooperation agreement that will expand upon the companies’ existing 15-y...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected