Operator okays Hangingstone SAGD project

The board of directors of Athabasca Oil Corp. has sanctioned the Hangingstone 1 steam-assisted gravity drainage oil sands project in the southern Athabasca region of Alberta and approved a $536 million (Can.) development budget for it (OGJ Online, Oct. 4, 2012).

The company plans a central processing facility and 20 SAGD well pairs drilled from four well pads. The board also approved spending of $27 million on construction of supporting infrastructure.

Drilling will begin in mid-2013. Start-up of the processing facility is scheduled for the fourth quarter of 2014. First steam is expected by the end of 204, with production starting in early 2015. Production capacity is 12,000 b/d of bitumen.

The company plans two other SAGD projects, which will bring potential production in the area to 80,000 b/d.

Related Articles

BHI: US drilling rig count holds steady at 1,931

09/19/2014

The US drilling rig count was unchanged at 1,931 rigs working during the week ended Sept. 19, Baker Hughes Inc. reported.

Cenovus starts production from Phase F at Foster Creek oil sands project

09/19/2014 Cenovus Energy Inc., Calgary, started oil production earlier this month at its recently completed Phase F expansion at its Foster Creek oil sands p...

Inpex to increase recovery, lifespan at Minami-Nagaoka field

09/19/2014 Inpex Corp. plans to upgrade facilities at its Koshijihara plant to enhance natural gas and condensate recovery at Minami-Nagaoka gas field in Japan.

Wild Well completes second capping stack

09/18/2014 Wild Well Control Inc., a subsidiary of Superior Energy Services, has completed a subsea capping stack stationed in Singapore to serve the area dur...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected