Hereema completes Andrew process module

Heerema Fabrication Group has completed the process module to be installed on BP PLC’s Andrew platform in the central North Sea to accommodate production from Kinnoull oil and gas field to be developed subsea.

The 750-tonne process module is 18 m long, 13 m wide, and 28 m high. It set sail for the field Oct. 4. A bolt-on installation will attach the module to the side of the Andrew platform.

Kinnoull is the largest of three reservoirs in BP’s Andrew area development project. Production from three subsea wells is to peak at 45,000 boe/d.

The development will extend Andrew area production beyond 2020. Andrew production is shut in during construction.

Related Articles

Baker Hughes: US drilling rig count declines to 1,854

05/02/2014

The US drilling rig count lost 7 units to settle at 1,854 rigs working during the week ended May 2, Baker Hughes Inc. reported.

Chevron 1Q profits plunge on lower oil production, prices

05/02/2014 Chevron Corp. reported earnings of $4.5 billion for this year’s first quarter compared with $6.2 billion for first-quarter 2013. Revenues in the fi...

Sen. Hoeven submits updated Keystone XL approval bill

05/01/2014 US Sen. John Hoeven (R-ND) submitted a fresh bill that would bypass the White House and congressionally approve the proposed Keystone XL crude oil ...

RWE Dea Egypt ramps up gas production at Disouq

04/30/2014 RWE Dea Egypt has ramped up natural gas production through its North West Khilala-1-4 (NWK-1-4) development well, which is part of the Disouq gas p...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected