Devon's Jackfish projects flow 51,000 b/d of bitumen

By OGJ editors

Devon Energy Corp., Oklahoma City, said production from its Jackfish 1 and 2 thermal projects in the southern Athabasca oil sands region of Alberta reached 51,000 b/d of bitumen in the second quarter, 63% above the year-earlier average (OGJ Online, Dec. 6, 2011).

The company said construction is about 40% at the Jackfish 3 project, where production is to begin late in 2014. Devon’s 100%-held Jackfish projects, 10 miles southeast of Conklin, Alta., use steam-assisted gravity drainage with saline water. Each phase is designed to produce 35,000 b/d.

Devon in June filed applications for the first phase of its Pike SAGD project on land adjacent to the Jackfish acreage. Targeted production is 105,000 b/d. Devon and BP Canada Energy hold 50% interests in Pike.

Related Articles

Sinopec reveals Fuling field production capacity goals

03/25/2014 Sinopec plans to develop Fuling shale gas field in southwestern China to a production capacity of 10 billion cu m (bcm)/year by 2017, the company s...

Santos brings Peluang gas development on stream

03/24/2014

Santos Ltd., Adelaide, has started natural gas production from its Peluang development offshore the Indonesian island of Java.

Baker Hughes: US drilling rig count drops to 1,803

03/21/2014 After consecutive weeks of significant gains, the US drilling rig count lost 6 units to 1,803 rigs working during the week ended Mar. 21, Baker Hug...

Cenovus gets AER approval for Grand Rapids oil sands project

03/21/2014 Cenovus Energy Inc. reported that it has received approval from the Alberta Energy Regulator (AER) for its wholly owned Grand Rapids thermal oil sa...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected