PHMSA sets conditions for Enbridge to restart failed pipeline

The US Pipeline and Hazardous Materials Administration prohibited Enbridge Energy Partners LP from restarting a shut-down crude oil pipeline in Wisconsin until it submits a restart plan for the US Department of Transportation agency’s approval.

PHMSA issued a corrective action order on July 31 requiring a restart plan for the entire 467-mile pipeline segment as well as mechanical and metallurgical testing and failure analysis of the ruptured pipe, evaluation of previous in-line inspection results, and submission of an integrity validation and remedial work plan.

The pipeline operator also will be required to have an independent evaluator investigate the company’s integrity management plan for Line 14, PHMSA said.

Enbridge said on July 30 that restarting the pipeline would be evaluated once repairs were completed, which could occur possibly as soon as July 31.

Contact Nick Snow at nicks@pennwell.com.

Related Articles

WINTER HITS U.S. INDUSTRY, STRAINS GAS SUPPLY

01/01/1990 A record breaking cold front before and during the weekend of Dec. 23 shut down several major refineries and petrochemical plants in the U.S. Gulf ...

TEX/CON, SPUN OFF FROM BP, UP AND RUNNING

01/01/1990 BP Exploration Western Hemisphere has spun off its U.S. Lower 48 onshore exploration/development and gas gathering, transportation, and marketing a...

SAMEDAN BUYS GULF OF MEXICO PRODUCTION

01/01/1990 Samedan Oil Corp. has expanded its inventory of producing leases in the Gulf of Mexico. The wholly owned subsidiary of Noble Affiliates Inc., Ardmo...

OIL FLOW RISING IN E. CHINA REGION

01/01/1990 Production is building from an oil producing area in the lower reaches of the Yangtze River in eastern China's Jiangsu Province. The northern J...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected