Penn Virginia to expand Marcellus gas gathering system

Penn Virginia Resource Partners will begin building natural gas pipeline extensions in the Marcellus shale in Pennsylvania, providing an outlet for producers to link to El Paso Corp.'s Tennessee Gas Pipeline and Williams Cos.’ Transcontinental pipeline for shipment to markets in the US Northeast. Penn Virginia reached transport agreements with Royal Dutch Shell PLC, Southwestern Energy, Range Resources Inc., and Inflection Energy, to underpin the extensions.

Penn Virginia plans to begin work on extending its 30-in. OD Lycoming West trunkline by 19 miles through Lycoming County and into Tioga County, Pa., within 2 weeks for completion by yearend. Penn Virginia also will build laterals for Shell and Range Resources to move gas from wellheads to Lycoming West for transport to the Transco line and by 2014 to Tennessee Gas Pipeline 300.

Under the 20-year Shell agreement, Penn Virginia will build a 24-in. OD lateral by this year’s fourth quarter, which will connect the Lycoming County system to Shell’s Texas Creek gathering system in Bradford County, Pa. Penn Virginia will complete another 16-in. OD lateral by yearend 2013 or early 2014, connecting the Lycoming County system to Shell’s Wellsboro Loop gathering system in Tioga County, Pa. Penn Virginia says these laterals will provide operational flexibility for Shell to move gas south to Transco, as well as the ability to move gas between the 24-in. lateral and Shell’s proprietary pipeline systems.

The Range Resources agreement provides for gathering, compression, and related services under terms similar to those of existing agreements, as well as construction of lateral lines and compression facilities, with a multiyear build-out schedule, staged to follow Range Resources’ drilling program.

The Inflection agreement dedicates defined acreage in Lycoming County, east of Penn Virginia’s existing Lycoming County system, to Penn Virginia, and provides Inflection with firm volume capacity and compression services, and a connection to Transco. Penn Virginia will build the gathering system in five phases designed to match Inflection’s drilling and production schedule, with construction of each subsequent phase tied to Inflection’s achieving certain well completion and production milestones.

Assuming all milestones are met, plans call for a total of 10 miles of 16-in. OD trunkline and 15 miles of lateral gathering lines, together with associated compressor stations, providing an expected total system capacity of 380 MMcfd by 2013.

The 15-year agreement with Southwestern provides for a firm take-or-pay capacity commitment in years 2 through 8, with an option to increase that commitment during this period. The agreement also provides Southwestern with interruptible capacity subject to availability.

Penn Virginia last month agreed to a $1 billion purchase of Chief Oil & Gas's Marcellus gas gathering assets (OGJ Online, Apr. 10, 2012). The company will spend about $380 million between 2012 and 2018 on natural gas infrastructure.

Contact Christopher E. Smith at chriss@ogjonline.com.

Related Articles

Shell cancels Arrow LNG project

01/30/2015

Royal Dutch Shell PLC has abandoned its plans for what would have been a fourth coal seam gas-LNG project at Gladstone in Queensland.

US Senate passes bill approving Keystone XL pipeline project

01/30/2015 The US Senate has passed a bill approving construction of the proposed Keystone XL crude oil pipeline by a 62-36 vote after 3 weeks of debate. Nine...

Douglas Channel LNG moves toward 2018 startup

01/29/2015 Exmar NV, EDF Trading, and AIJVLP, a joint venture of AltaGas Ltd. and Idemitsu Kosan Co. Ltd., have taken full ownership of the 550,000 tonne/year...

Mitsui charters two more LNG ships for Cameron export project

01/29/2015 Mitsui & Co., Ltd., Tokyo, reports contracts for chartering two new ships to transport LNG to Japan from the Cameron LNG export project in Loui...

US House approves bill aimed at increasing LNG exports

01/28/2015 The US House of Representatives passed a bill aimed at increasing US LNG exports by requiring the Department of Energy to determine whether a proje...

New Russia-Turkey gas pipeline route approved

01/28/2015

OAO Gazprom reported selection of a route for a gas pipeline across the Black Sea from Russia to Turkey.

PHMSA outlines community steps to reduce pipeline incident risks

01/27/2015 The US Pipeline and Hazardous Materials Safety Administration released a guide to best practices for communities to reduce risks from pipeline inci...

Knight Warrior Eaglebine-Woodbine crude pipeline advances

01/27/2015 Knight Warrior LLC has reached agreements to build its 160-mile, 100,000-b/d pipeline linking the East Texas Eaglebine-Woodbine crude oil play to H...

ETP, Regency to merge in $18-billion deal

01/26/2015 Energy Transfer Partners LP (ETP) and Regency Energy Partners have agreed to merge in a unit-for-unit transaction, plus a one-time cash payment to ...
White Papers

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by

The impact of aging infrastructure in process manufacturing industries

Process manufacturing companies in the oil and gas, utilities, chemicals and natural resource industri...
Sponsored by

What is System Level Thermo-Fluid Analysis?

This paper will explain some of the fundamentals of System Level Thermo-Fluid Analysis and demonstrate...

Accurate Thermo-Fluid Simulation in Real Time Environments

The crux of any task undertaken in System Level Thermo-Fluid Analysis is striking a balance between ti...
Available Webcasts


Prevention, Detection and Mitigation of pipeline leaks in the modern world

When Thu, Apr 30, 2015

Preventing, detecting and mitigating leaks or commodity releases from pipelines are a top priority for all pipeline companies. This presentation will look at various aspects related to preventing, detecting and mitigating pipeline commodity releases from a generic and conceptual point of view, while at the same time look at the variety of offerings available from Schneider Electric to meet some of the requirements associated with pipeline integrity management. 

register:WEBCAST



On Demand

Global LNG: Adjusting to New Realities

Fri, Mar 20, 2015

Oil & Gas Journal’s March 20, 2015, webcast will look at how global LNG trade will be affected over the next 12-24 months by falling crude oil prices and changing patterns and pressures of demand. Will US LNG production play a role in balancing markets? Or will it add to a growing global oversupply of LNG for markets remote from easier natural gas supply? Will new buyers with marginal credit, smaller requirements, or great need for flexibility begin to look attractive to suppliers? How will high-cost, mega-projects in Australia respond to new construction cost trends?

register:WEBCAST


US Midstream at a Crossroads

Fri, Mar 6, 2015

Oil & Gas Journal’s Mar. 6, 2015, webcast will focus on US midstream companies at an inflection point in their development in response to more than 6 years shale oil and gas production growth. Major infrastructure—gas plants, gathering systems, and takeaway pipelines—have been built. Major fractionation hubs have expanded. Given the radically changed pricing environment since mid-2014, where do processors go from here? What is the fate of large projects caught in mid-development? How to producers and processors cooperate to ensure a sustainable and profitable future? This event will serve to set the discussion table for the annual GPA Convention in San Antonio, Apr. 13-16, 2015.

This event is sponsored by Leidos Engineering.

register:WEBCAST


The Future of US Refining

Fri, Feb 6, 2015

Oil & Gas Journal’s Feb. 6, 2015, webcast will focus on the future of US refining as various forces this year conspire to pull the industry in different directions. Lower oil prices generally reduce feedstock costs, but they have also lowered refiners’ returns, as 2015 begins with refined products priced at lows not seen in years. If lower per-barrel crude prices dampen production of lighter crudes among shale plays, what will happen to refiners’ plans to export more barrels of lighter crudes? And as always, refiners will be affected by government regulations, particularly those that suppress demand, increase costs, or limit access to markets or supply.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected