Williams boosts capacity of Atlantic Access Transco expansion

Williams Partners LP’s discussions with potential shippers and other market inquiries regarding the Atlantic Access expansion of its Transco interstate pipeline have prompted it to increase the project’s capacity to 2.3 bcfd from 1.8 bcfd. Williams Partners also is offering additional firm transportation paths, and revising the proposed in-service date to December 2015 from late-2014.

Atlantic Access connects gas supplies in western West Virginia and Pennsylvania to the Northeast, Mid-Atlantic, Southeast, and Gulf Coast. It will transport gas from northern Pennsylvania bidirectionally along Transco’s existing Leidy Line to Leidy and other markets along the Atlantic seaboard (OGJ Online, Feb. 7, 2012).

Transco is now proposing a total of six firm transportation paths under Atlantic Access. In addition to the Natrium, Butler, and Rivervale paths described in the original open season announcement, Transco offering capacity through the Station 520 Path, the Station 517 Path, and the Leidy West Path.

The Station 520 Path will provide an incremental 250 MMcfd of year-round firm capacity from Transco's Zone 6 beginning at any receipt interconnection on Transco's Leidy Line between and including the existing Grugan Interconnect at MP 190.2 in Clinton County, Pa., and the existing Barto Interconnect near MP 140 in Lycoming County, Pa., and extending eastward along the Leidy Line to Transco's existing Station 210 and then southward on the mainline terminating at Transco's existing Station 85.

The Station 517 Path will provide an incremental 250 MMcfd of capacity from Transco's Zone 6 beginning at any existing receipt interconnection on Transco's Leidy Line between and including the proposed CNYOG Marc1 Interconnect near MP 136.2 in Lycoming County, Pa., and the existing Centerville Interconnect with Algonquin Gas Transmission at MP 13.7 in Somerset County, NJ, and extending eastward along the Leidy Line to Transco's existing Station 210 and then southward on the mainline terminating at Transco's existing Station 85.

The Leidy West Path will move an incremental 200 MMcfd in Transco's Zone 6 beginning at any existing interconnect on the Leidy Line west of the existing Station 515 at MP 68.9 in Luzerne County, Pa., and extending westward to existing interconnects with Dominion Transmission and National Fuel Gas and a proposed, new interconnect with Texas Eastern Transmission near Leidy Storage at MP 206.8 in Clinton County, Pa.

Transco received insufficient binding commitments in the original open season for the Natrium Path and continues to offer firm transportation capacity on it, reducing capacity for the supplemental open season to 700 MMcfd from 900 MMcfd. Natrium runs from Transco's Zone 6 to Transco's Zone 3 beginning at a proposed interconnection with Dominion Transmission's gas treatment plant near the existing Natrium plant in Marshall County, W.Va., and extending through a new line to be constructed by Transco eastward across southern Pennsylvania to an interconnection with Transco's mainline at Station 195 in York County, Pa., and then continuing southward on Transco's mainline to Transco's existing interconnection with Liberty Gas Storage at MP 469.4 in Beauregard Parish, La., the western-most nominatable point in Transco's Zone 3.

The Butler Path and Rivervale Path were fully subscribed during the original open season. Transco may, however, under terms of the original open season, allow shippers to voluntarily reduce or revise their requested transportation contract quantities (TCQ) on these paths to accommodate other shippers, starting with the shipper with the largest requested TCQ. Transco will therefore accept additional requests on these paths during the current open season, subject to the existing shippers voluntarily reducing their TCQs.

A shipper's TCQ under the project will be equal to the sum of the capacity subscribed on the various project paths.

Transco is also evaluating an extension of its existing Leidy Line westward to a point in Elk County, or an extension from its proposed Butler Lateral northward to a point in Elk County, to provide additional firm transportation to Transco markets. Timing and level of shipper interest will determine if Transco completes this project as part of the Atlantic Access or pursues it independently.

The Atlantic Access project will be subject to approval by the US Federal Energy Regulatory Commission and other agencies. The revised open season ends July 13.

Contact Christopher E. Smith at chriss@ogjonline.com.

Related Articles

West Cornwall Township hears from Sunoco Logistics

12/12/2014

Sunoco Logistics Partners outlined its safety systems during a West Cornwall Township meeting in Pennsylvania on Nov. 10.

ETP eyes larger capacity for planned Bakken pipe

12/12/2014 Energy Transfer Partners LP has launched a binding expansion open season to boost capacity on a planned pipeline system that would move oil from th...

Kinder Morgan to deliver natural gas to Corpus Christi Liquefaction

12/11/2014 Kinder Morgan Inc. (KMI) companies Kinder Morgan Texas Pipeline, Kinder Morgan Tejas Pipeline, and Tennessee Gas Pipeline Co. (TGP) have entered in...

Rosneft, Essar sign terms of oil supply agreement

12/11/2014 OAO Rosneft and Essar Energy PLC have signed key terms of an oil supply agreement in New Delhi. Rosneft said shipments to India may begin in 2015.

Barton introduces bill to remove US crude export limits

12/11/2014

US Rep. Joe Barton (R-Tex.) introduced legislation that would remove US crude oil export limits that have been in place for nearly 40 years.

BG agrees to sale of Australian gas pipeline to APA Group

12/10/2014

BG Group PLC agreed to sell its wholly owned subsidiary Queensland Curtis LNG Pipeline Pty. Ltd. (QCLNG) to APA Group for about $5 billion.

More West Texas gathering, processing to come onstream

12/09/2014 EagleClaw Midstream Services LLC, Midland, Tex., has bought natural gas gathering and processing in Reeves County, Tex. The company declined to ide...

Methane controls just part of complete climate strategy, speakers say

12/08/2014 Reducing oil and gas operations’ methane emissions is an essential, but far from the only, part of a comprehensive climate strategy, speakers at a ...

Rail tank car rule could cost economy billions, report says

12/08/2014 The US Pipeline and Hazardous Materials Safety Administration's (PHMSA) proposed rail tank car rule could cost the US economy as much as $60 billio...

White Papers

AVEVA NET Accesses and Manages the Digital Asset

Global demand for new process plants, power plants and infrastructure is increasing steadily with the ...
Sponsored by

AVEVA’s Approach for the Digital Asset

To meet the requirements for leaner project execution and more efficient operations while transferring...
Sponsored by

Diversification - the technology aspects

In tough times, businesses seek to diversify into adjacent markets or to apply their skills and resour...
Sponsored by

Engineering & Design for Lean Construction

Modern marketing rhetoric claims that, in order to cut out expensive costs and reduce risks during the...
Sponsored by

Object Lessons - Why control of engineering design at the object level is essential for efficient project execution

Whatever the task, there is usually only one way to do it right and many more to do it wrong. In the c...
Sponsored by

Plant Design for Lean Construction - at your fingertips

One area which can provide improvements to the adoption of Lean principles is the application of mobil...
Sponsored by

How to Keep Your Mud System Vibrator Hose from Getting Hammered to Death

To prevent the vibrating hoses on your oilfield mud circulation systems from failing, you must examine...
Sponsored by

Duty of Care

Good corporate social responsibility means implementing effective workplace health and safety measures...
Sponsored by

Available Webcasts


On Demand

Optimizing your asset management practices to mitigate the effects of a down market

Thu, Dec 11, 2014

The oil and gas market is in constant flux, and as the price of BOE (Barrel of Oil Equivalent) goes down it is increasingly important to optimize your asset management strategy to stay afloat.  Attend this webinar to learn how developing a solid asset management plan can help your company mitigate costs in any market.

register:WEBCAST


Parylene Conformal Coatings for the Oil & Gas Industry

Thu, Nov 20, 2014

In this concise 30-minute webinar, participants have an opportunity to learn more about how Parylene coatings are applied, their features, and the value they add to devices and components.

register:WEBCAST


Utilizing Predictive Analytics to Optimize Productivity in Oil & Gas Operations

Tue, Nov 18, 2014

Join IBM on Tuesday, November 18 @ 1pm CST to explore how Predictive Analytics can help your organization maximize productivity, operational performance & associated processes to drive enterprise wide productivity and profitability.

register:WEBCAST


US HYDROCARBON EXPORTS Part 3 — LNG

Fri, Nov 14, 2014

US LNG Exports, the third in a trilogy of webcasts focusing on the broad topic of US Hydrocarbon Exports.

A discussion of the problems and potential for the export of US-produced liquefied natural gas.

These and other topics will be discussed, with the latest thoughts on U.S. LNG export policy.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected