Lukoil starts West Qurna-2 drilling in Iraq

By OGJ editors

Lukoil has started drilling production wells and building the central processing facility at supergiant West Qurna-2 oil field in Iraq, where it targets production of 500,000 b/d by 2013-14 (OGJ Online, Mar. 22, 2012).

In the current project it plans to drill 23 directional wells with a sliding-rig system from five well pads. The company expects total investment in the West Qurna-2 project to reach $25 billion.

West Qurna-2, covering 340 sq km 65 km northwest of Basra, holds oil reserves estimated at 14 billion bbl.

Lukoil and Statoil won a contract for the project in January 2012 with a bid of a $1.15/bbl remuneration fee at a production level of 1.8 million b/d.

They will be able to recover expenses and receive remuneration once production reaches 150,000 b/d.

Interests are Lukoil 56.25%, state-owned North Oil Co. 25%, and Statoil 18.75%.

Related Articles

BHI: US drilling rig count holds steady at 1,931

09/19/2014

The US drilling rig count was unchanged at 1,931 rigs working during the week ended Sept. 19, Baker Hughes Inc. reported.

Cenovus starts production from Phase F at Foster Creek oil sands project

09/19/2014 Cenovus Energy Inc., Calgary, started oil production earlier this month at its recently completed Phase F expansion at its Foster Creek oil sands p...

Inpex to increase recovery, lifespan at Minami-Nagaoka field

09/19/2014 Inpex Corp. plans to upgrade facilities at its Koshijihara plant to enhance natural gas and condensate recovery at Minami-Nagaoka gas field in Japan.

Wild Well completes second capping stack

09/18/2014 Wild Well Control Inc., a subsidiary of Superior Energy Services, has completed a subsea capping stack stationed in Singapore to serve the area dur...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected