Vantage gains NEB approval of ethane pipeline

Vantage Pipeline Canada ULC has received National Energy Board approval of its Vantage Pipeline Project ethane line. The $240 million project will carry 45,000 b/d of liquid ethane from Hess Corp.’s natural gas processing plant near Tioga, ND, through Saskatchewan to interconnect with the Alberta Ethane Gathering System (AEGS) near Empress, Alta., for use in Alberta’s petrochemical industry.

The Canadian portion of the 700-km project will involve building and operating 578.3 km of new 273-mm OD, high-vapor pressure steel pipeline, from the Canada-US border near Beaubier, Sask., to the AEGS, crossing 573.8 km in Saskatchewan and 4.5 km in Alberta. Vantage has routed the pipeline so it will be within or alongside existing pipelines and road right-of-way for about 503.7 km.

Vantage’s capacity will be expandable to 60,000 b/d if warranted by production expansion in the Williston basin. Vantage expects to begin construction in this year’s first-half and finish late this year (OGJ Online, Feb. 14, 2011).

NEB accepted Vantage’s arguments that Alberta’s domestic ethane supply is declining and will continue to decline for some time and that there will be sufficient future ethane supplies and processing capacity available for the project to be viable over its economic life.

Contact Christopher E. Smith at chriss@ogjonline.com.

Related Articles

California lawmakers pass in-state gas system methane emissions bill

08/28/2014 The California Senate passed a bill aimed at curbing methane emissions from intrastate natural gas pipelines and local distribution systems. SB 137...

BG Group: Mzia DST supports potential hub development offshore Tanzania

08/27/2014 Results from the second drillstem test (DST) on the Mzia discovery on Block 1 offshore southern Tanzania indicated further support for a hub develo...

Dakota Gold to develop Bakken-Three Forks crude terminal

08/27/2014 Dakota Gold Transfer-Plaza LLC plans to develop a crude oil transload terminal in Mountrail County, ND. Sited on 350 acres in the eastern section o...

ExxonMobil Pipeline settles charges from 2012 Louisiana spill

08/27/2014 Exxon Pipeline Co. agreed to pay more than $1.4 million to resolve federal charges that a 2012 spill from the company’s North Line near Torbert, La...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected