North Dakota natural gas plant starts up

By OGJ editors

Oneok Partners LP, Tulsa, reported that its 100-MMcfd Garden Creek natural gas processing plant in eastern McKenzie County, ND, is receiving production from the Bakken shale.

Oneok Partners previously announced plans to invest $1.5-1.8 billion for projects in the Bakken shale during 2012-14 in its gas gathering and processing and NGL businesses. In addition to the Garden Creek plant, these investments include construction of the 500-mile Bakken pipeline and two additional 100-MMcfd gas processing plants: Stateline I and Stateline II in western Williams County, ND.

The Bakken pipeline is to be completed by first-half 2013; Stateline I and Stateline II plants are to be completed by third-quarter 2012 and first-half 2013, respectively.

Related Articles

Baker Hughes: US drilling rig count drops to 1,803

03/21/2014 After consecutive weeks of significant gains, the US drilling rig count lost 6 units to 1,803 rigs working during the week ended Mar. 21, Baker Hug...

Second small diesel refinery planned for North Dakota

03/21/2014 Quantum Energy Inc. (QEI), Tempe, Ariz., said it has secured land for the construction of a 20,000-b/d grassroots hydroskimming refinery in North D...

Cenovus gets AER approval for Grand Rapids oil sands project

03/21/2014 Cenovus Energy Inc. reported that it has received approval from the Alberta Energy Regulator (AER) for its wholly owned Grand Rapids thermal oil sa...

Ivanhoe halts Tamarack oil sands project citing lack of regulatory ‘clarity’

03/18/2014 Ivanhoe Energy Inc. has suspended activity on its Tamarack oil sands project pending approval for its thermal oil sands application from the govern...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected