Woodside releases Browse LNG project draft EIS

Woodside Petroleum Ltd. has released for public comment its draft environmental impact statement (EIS) for the proposed $30 billion (Aus.) Browse LNG project in Western Australia.

The project involves development of the Torosa (originally called Scott Reef), Brecknock, and Calliance (originally Brecknock South) gas-condensate fields found between 1971 and 2000 some 425 km north of Broome and 290 km off the Kimberley coast.

Collectively they are estimated to contain 13.3 tcf of recoverable gas and 360 million bbl of recoverable condensate. They lie in 400-700 m of water.

The EIS outlines a development that includes the drilling of 50-90 wells over the 50-year project life.

The wells will be connected to seabed manifolds (four at Torosa, the northern-most field, two at Calliance in the south, and one at Brecknock in the center) which in turn will each be connected through flowlines to their in-field platforms.

The field platforms will then be connected by subsea pipelines to a four-platform central processing facility closer to shore in 80-120 m of water.

Gas and condensate will be processed at this offshore facility before being sent by a 310-km trunk line to the LNG facility that will be built at the Western Australian government’s chosen LNG hub site at James Price Point some 60 km north along the coast from Broome.

Woodside notes in the EIS that most of the expected impacts of the scheme are classed as low risk, although local fisheries will face a medium risk through exclusion zones that will be placed around the platforms and drilling rigs. Even so, this total exclusion zone area will be small.

Tests to determine the impact of light from Torosa platform on marine turtles in an around Sandy Islet (which is the small surface expression of the nearby Scott Reef atoll) suggest that maximum light levels reaching the islet will be no more than a small lit object. This will not influence nesting behaviour of adult turtles.

Nevertheless, Woodside has begun a long-term monitoring program of turtles on the islet to identify any impacts from the proposed development.

The EIS also assessed noise levels produced during construction, vessel movements and operational activities. Most were found to be of low risk to cetaceans. The company will investigate insulation methods to reduce noise produced by fluids passing through the subsea choke valves.

In addition, the study looked at the potential for vessels and rigs introducing invasive species and the temporary changes in water quality due to elevated suspended sediment from pipeline trenching work.

Woodside said alternative development schemes were looked at and dropped. The Browse-to-Darwin pipeline option was too expensive. A liquefaction facility built on concrete foundations in the shallow water of the southern lagoon at Scott Reef was deemed environmentally unacceptable.

Floating LNG was dropped because of the need for multiple facilities to efficiently recover gas from the fields. Consideration of a Browse-to-Burrup Peninsula pipeline showed this to be the most viable alternative to James Price Point, but it raised the possibility of issues related to the cumulative impacts on the Burrup potentially presenting environmental challenges.

Overall the EIS represents 17 years of detailed research which Woodside says has shed new light on Western Australia’s northern offshore ecosystems.

Browse LNG is expected to contribute up to $50 billion (Aus.) to the Australian economy and create up to 8,000 jobs (6,000 onshore; 2,000 offshore) during the construction period.

The project is expected to produce 12 million tonnes/year of LNG. A final investment decision is scheduled for 2012 with the first LNG coming on stream in 2017.

The EIS will be open for public comment until Jan. 25, 2012.

Related Articles

PHMSA proposes pipeline accident notification regulations

07/02/2015 The US Pipeline and Hazardous Materials Safety Administration has proposed new federal oil and gas pipeline accident and notification regulations. ...

Quicksilver Canada gets LNG export approval

07/02/2015 Quicksilver Resources Canada Inc. has received approval from the National Energy Board of Canada to export 20 million tonnes/year of LNG from a pos...

Origin lets contract for Otway basin fields

07/02/2015 Origin Energy Ltd., Sydney, has let a $1.3 million (Aus.) contract to Wood Group Kenny for provision of a detailed engineering design for the onsho...

API to issue recommended practice to address pipeline safety

07/01/2015 The American Petroleum Institute expects to issue a new recommended practice in another few weeks that addresses pipeline safety issues, but the tr...

Shell Midstream Partners takes interest in Poseidon oil pipeline

07/01/2015 Shell Midstream Partners LP has completed its acquisition of 36% equity interest in Poseidon Oil Pipeline Co. LLC from Equilon Enterprises LLC, a s...

Shell makes FID on Appomattox deepwater development in Gulf of Mexico

07/01/2015 Royal Dutch Shell PLC has taken a final investment decision (FID) on the Appomattox deepwater development, authorizing construction and installatio...

Woodside-led Browse FLNG venture enters FEED phase

07/01/2015 The Woodside Petroleum Ltd.-led Browse LNG joint venture has entered the front-end engineering and design phase for a floating LNG (FLNG) developme...

Case for Keystone XL has grown stronger, TransCanada tells Kerry

06/30/2015 Canada is taking strong steps toward combating climate change, and the proposed Keystone XL pipeline crude oil pipeline remains in the US national ...

Construction begins on Chinese section of Russia-China Gas Pipeline

06/30/2015

Construction has begun on the Chinese section of the Russia-China Gas Pipeline, according to China National Petroleum Corp.

White Papers

2015 Global Engineering Information Management Solutions Competitive Strategy Innovation and Leadership Award

The Frost & Sullivan Best Practices Awards recognise companies in a variety of regional and global...
Sponsored by

Three Tips to Improve Safety in the Oil Field

Working oil fields will always be tough work with inherent risks. There’s no getting around that. Ther...
Sponsored by

Pipeline Integrity: Best Practices to Prevent, Detect, and Mitigate Commodity Releases

Commodity releases can have catastrophic consequences, so ensuring pipeline integrity is crucial for p...
Sponsored by

AVEVA’s Digital Asset Approach - Defining a new era of collaboration in capital projects and asset operations

There is constant, intensive change in the capital projects and asset life cycle management. New chall...
Sponsored by

Transforming the Oil and Gas Industry with EPPM

With budgets in the billions, timelines spanning years, and life cycles extending over decades, oil an...
Sponsored by

Asset Decommissioning in Oil & Gas: Transforming Business

Asset intensive organizations like Oil and Gas have their own industry specific challenges when it com...
Sponsored by

Squeezing the Green: How to Cut Petroleum Downstream Costs and Optimize Processing Efficiencies with Enterprise Project Portfolio Management Solutions

As the downstream petroleum industry grapples with change in every sector and at every level, includin...
Sponsored by

7 Steps to Improve Oil & Gas Asset Decommissioning

Global competition and volatile markets are creating a challenging business climate for project based ...
Sponsored by
Available Webcasts


OGJ's Midyear Forecast 2015

When Fri, Jul 10, 2015

This webcast is to be presented by OGJ Editor Bob Tippee and Senior Economic Editor Conglin Xu.  They will summarize the Midyear Forecast projections in key categories, note important changes from January’s forecasts, and examine reasons for the adjustments.

register:WEBCAST


Predictive Analytics in your digital oilfield - Optimize Production Yield and Reduce Operational Costs

When Tue, Jul 7, 2015

Putting predictive analytics to work in your oilfield can help you anticipate failures, plan and schedule work in advance, eliminate emergency work and catastrophic failures, and at the same time you can optimize working capital and improve resource utilization.  When you apply analytic capabilities to critical production assets it is possible to reduce non-productive time and increase your yield.

Learn how IBM's analytics capabilities can be applied to critical production assets with the goal of reducing non-productive time, increasing yield and reducing operations costs.

register:WEBCAST



On Demand

Cognitive Solutions for Upstream Oil and Gas

Fri, Jun 12, 2015

The oil & gas sector is under pressure on all sides. Reserves are limited and it’s becoming increasingly expensive to find and extract new resources. Margins are already being squeezed in an industry where one wrong decision can cost millions. Analyzing data used in energy exploration can save millions of dollars as we develop ways to predict where and how to extract the world’s massive energy reserves.

This session with IBM Subject Matter Experts will discuss how IBM Cognitive Solutions contribute to the oil and gas industry using predictive analytics and cognitive computing, as well as real time streaming for exploration and drilling.

register:WEBCAST


The Alternative Fuel Movement: Four Need-to-Know Excise Tax Complexities

Thu, Jun 4, 2015

Discussion on how to approach, and ultimately embrace, the alternative fuel market by pulling back the veil on excise tax complexities. Taxes may be an aggravating part of daily operations, but their accuracy is crucial in your path towards business success.

register:WEBCAST


Emerson Micro Motion Videos

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected