Vilje southern extension, offshore Norway, set for development

By OGJ editors

The Vilje partners plan a 1.1 billion kroner development of Vilje South, an extension of the main Vilje field.

Vilje is on Block 25/4 in the North Sea, production license 036D, 12 km north of Heimdal field in 120 m of water. Development of the southern extension was included in the original Vilje plan for development and operation.

The Vilje South development will include a standard subsea template with one well, tied back to the existing seabed structure on Vilje, which is tied back 19 km to the Marathon-operated Alvheim floating production, storage, and offloading vessel that also handles production from Kamelon (Block 24/6-2), Boa (Block 24/6-4), and Kneler (Block 25/4-7).

Statoil estimates the Vilje South, discovered in 2004, holds 7.6 million boe of recoverable reserves, mainly crude.

The company expects the extension to be on stream in 2013.

The Vilje template is under construction by Aker for installation in summer 2013, together with the rest of the subsea equipment. Estimated net oil production in 2014 from Vilje South is 5,000 b/d.

Statoil said the project is the smallest in its fast-track field development portfolio and the sixth fast-track investment decision made in 2011, leaving only a decision on Visund North to be made by yearend.

It noted that it has removed both the Snorre B template and Mikkel South from its fast-track portfolio. Snorre B because of adjustments to the plan for extending Snorre area production to 2040, and Mikkel South because of capacity limits in the Asgard transport gas pipeline.

New projects added to the portfolio are Fram H North and Svalin C.

Plans call for the first five fast-track projects to be brought on stream by yearend 2012 or in early 2013.

Operator Statoil holds a 28.5% interest in Vilje South. Partners are Marathon Petroleum Norge AS 49.9% and Total E&P Norge AS 24.24%.

Related Articles

Sinopec reveals Fuling field production capacity goals

03/25/2014 Sinopec plans to develop Fuling shale gas field in southwestern China to a production capacity of 10 billion cu m (bcm)/year by 2017, the company s...

Santos brings Peluang gas development on stream

03/24/2014

Santos Ltd., Adelaide, has started natural gas production from its Peluang development offshore the Indonesian island of Java.

Baker Hughes: US drilling rig count drops to 1,803

03/21/2014 After consecutive weeks of significant gains, the US drilling rig count lost 6 units to 1,803 rigs working during the week ended Mar. 21, Baker Hug...

Cenovus gets AER approval for Grand Rapids oil sands project

03/21/2014 Cenovus Energy Inc. reported that it has received approval from the Alberta Energy Regulator (AER) for its wholly owned Grand Rapids thermal oil sa...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected