IHS CERA: State Department's Keystone XL delay creates new uncertainties

The US Department of State’s Nov. 10 decision to delay a final recommendation on the proposed Keystone XL crude oil pipeline’s cross-border permit application so alternative routes can be considered will create new uncertainties for Canadian heavy oil producers as well as US refiners, an IHS CERA specialist said.

“In the next few years, existing US Midwestern markets for Canadian oil sands will reach the saturation point,” Jackie Forrest, oil sands dialogue senior director at IHS CERA, said on Nov. 11. “By 2015, without new pipeline solutions to bring oil sands barrels to markets outside the Midwest (such as the US Gulf Coast), oil sands production growth could stall for lack of new demand.”

The State Department said the delay effectively postpones into early 2013 any approval or rejection of TransCanada Corp.’s application, which President Barack Obama previously said he would handle personally. Forrest said it would take about 2 years to build the $7 billion project and put it into service if it’s approved.

“However, in the 2 years leading up to the in-service date of the pipeline, oil sands producers would continue to face steeper and steeper price discounts for their crudes, as oil sands production growth will outstrip new demand in existing markets,” she said.

Keystone XL’s permit delay increases the possibility that other projects to transport oil recovered from Alberta’s oil sands to US Gulf Coast refiners will move forward, Forrest continued. The most prominent is Enbridge Inc.’s proposed Wrangler pipeline which, combined with the Calgary company’s Flanagan South project and existing Alberta Clipper pipeline, could serve a function similar to Keystone XL’s, she said.

Enbridge’s plans

In its Nov. 9 report of financial results for the third quarter and 9 months ended Sept. 30, Enbridge said expansion of Enbridge Energy Partners LP’s Line 5 and reversal of the segment of Enbridge's Line 9 from Sarnia to Westover, announced in early October, would provide increased access to US Upper Midwest and Ontario refineries Canada for light crude produced in western Canada and the US.

It said Wrangler, which it announced in late September as a proposed joint venture with Enterprise Product Partners, would transport crude from the Cushing, Okla., hub to Texas Gulf Coast refineries. Enbridge is also developing the proposed Flanagan South Project to add capacity to Cushing from its Flanagan, Ill., terminal, Enbridge said.

“Potentially, all legs of this project could be in service by 2014,” Forrest said. “Even in this scenario, oil sands producers would face steeper price discounts for their crudes, a full year longer than a scenario where the decision on Keystone XL is not being postponed.”

Pipeline capacity also is needed to move light crude produced from North Dakota’s Bakken shale and other US Midcontinent tight oil formations, she continued. “Based on our view of growth in Canadian oil sands and tight oil production, over the next 5 years North America will need both the Keystone XL and the Enbridge projects in order to create enough takeaway capacity to prevent bottlenecks,” Forrest said.

“If no pipeline solutions occur in the next few years, we are likely to see a very significant build out of rail capacity, which has higher transportation cost than pipelines, to bring Canadian oil sands and Midcontinent tight oil to new markets,” she added.

Contact Nick Snow at nicks@pennwell.com.

Related Articles

BHI: Texas anchors 90-unit plunge in US rig count

01/30/2015 The US drilling rig count plunged 90 units—a majority of which were in Texas—to settle at 1,543 rigs working during the week ended Jan. 30, Baker H...

Oxy cuts capital budget by a third

01/30/2015 In the midst of falling oil prices, Occidental Petroleum Corp., Houston, expects to reduce its total capital spending for 2015 to $5.8 billion from...

Cenovus trims additional $700 million from capital budget

01/28/2015 Cenovus Energy Inc., Calgary, will defer $700 million in additional capital expenditures originally planned for 2015 until crude oil prices recover...

Pengrowth cuts capital spending due to declining oil prices

01/23/2015 The recent “rapid” decline in world oil prices is the main reason given by Pengrowth Energy Corp., Calgary, for setting its 2015 capital budget at ...

Syncrude files applications for Mildred Lake extensions

01/20/2015

Syncrude Canada Ltd. has filed applications with Alberta Energy Regulator for two extensions to the Mildred Lake oil sands production area.

Take that, Canada!

01/12/2015 Mexican President Enrique Pena Nieto needs a warning about how the US treats friends nowadays. On the day of his chummy, Dec. 6, 2014, meeting with...

Cenovus trims budget, slows oil sands work

12/22/2014 Cenovus Energy Inc., Calgary, is trimming its capital spending in response to falling crude prices and will slow development of some of its thermal...

Cenovus trims budget, slows oil sands work

12/16/2014 Cenovus Energy Inc., Calgary, is trimming its capital spending in response to declining crude oil prices and will slow development of some of its t...

Pengrowth starts commercial steam operations at Lindbergh thermal project

12/16/2014 Pengrowth Energy Corp., Calgary, reported the startup of commercial steam operations at Phase 1 of its Lindbergh thermal project in the Cold Lake a...

White Papers

What is System Level Thermo-Fluid Analysis?

This paper will explain some of the fundamentals of System Level Thermo-Fluid Analysis and demonstrate...

Accurate Thermo-Fluid Simulation in Real Time Environments

The crux of any task undertaken in System Level Thermo-Fluid Analysis is striking a balance between ti...

6 ways for Energy, Chemical and Oil and Gas Companies to Avert the Impending Workforce Crisis

As many as half of the skilled workers in energy, chemical and oil & gas industries are quickly he...
Sponsored by

AVEVA NET Accesses and Manages the Digital Asset

Global demand for new process plants, power plants and infrastructure is increasing steadily with the ...
Sponsored by

AVEVA’s Approach for the Digital Asset

To meet the requirements for leaner project execution and more efficient operations while transferring...
Sponsored by

Diversification - the technology aspects

In tough times, businesses seek to diversify into adjacent markets or to apply their skills and resour...
Sponsored by

Engineering & Design for Lean Construction

Modern marketing rhetoric claims that, in order to cut out expensive costs and reduce risks during the...
Sponsored by

Object Lessons - Why control of engineering design at the object level is essential for efficient project execution

Whatever the task, there is usually only one way to do it right and many more to do it wrong. In the c...
Sponsored by

Available Webcasts



The Future of US Refining

When Fri, Feb 6, 2015

Oil & Gas Journal’s Feb. 6, 2015, webcast will focus on the future of US refining as various forces this year conspire to pull the industry in different directions. Lower oil prices generally reduce feedstock costs, but they have also lowered refiners’ returns, as 2015 begins with refined products priced at lows not seen in years. If lower per-barrel crude prices dampen production of lighter crudes among shale plays, what will happen to refiners’ plans to export more barrels of lighter crudes? And as always, refiners will be affected by government regulations, particularly those that suppress demand, increase costs, or limit access to markets or supply.

register:WEBCAST



On Demand

Oil & Gas Journal’s Forecast & Review/Worldwide Pipeline Construction 2015

Fri, Jan 30, 2015

The  Forecast & Review/Worldwide Pipeline Construction 2015 Webcast will address Oil & Gas Journal’s outlooks for the oil market and pipeline construction in a year of turbulence. Based on two annual special reports, the webcast will be presented by OGJ Editor Bob Tippee and OGJ Managing Editor-Technology Chris Smith.
The Forecast & Review portion of the webcast will identify forces underlying the collapse in crude oil prices and assess prospects for changes essential to recovery—all in the context of geopolitical pressures buffeting the market.

register:WEBCAST


Optimizing your asset management practices to mitigate the effects of a down market

Thu, Dec 11, 2014

The oil and gas market is in constant flux, and as the price of BOE (Barrel of Oil Equivalent) goes down it is increasingly important to optimize your asset management strategy to stay afloat.  Attend this webinar to learn how developing a solid asset management plan can help your company mitigate costs in any market.

register:WEBCAST


Parylene Conformal Coatings for the Oil & Gas Industry

Thu, Nov 20, 2014

In this concise 30-minute webinar, participants have an opportunity to learn more about how Parylene coatings are applied, their features, and the value they add to devices and components.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected