OGX expects to reach 1.4 million boe/d in Brazil by 2019

Guntis Moritis
OGJ Production Editor

HOUSTON, June 21 -- In its recently released business plan, OGX Petroleo e Gas Participacoes SA said production may reach 1.4 million boe/d by 2019 from its shallow-water blocks in the Campos basin and the onshore Parnaiba basin, based on a potential resource estimate of 10.8 billion boe.

At that time, it expects to have in its Campos basin blocks 19 floating production, storage, and offloading vessels; 24 wellhead platforms; and 5 tension-leg wellhead platforms.

To date, it said it has discovered 4.2 billion boe in the two basins. This resource could support production of 730,000 boe/d by yearend 2015.

The company noted that it had drilled 52 wells in the past 20 months with an overall success rate exceeding 90%.

In the Campos basin, OGX expects production to begin in October from its first project (Waimea complex) at a rate of 20,000 bo/d from Well OGX-26. Its second project (Waikiki complex) is set to start production in fourth-quarter 2013.

In 2013, the company plans to have three FPSOs (OSX-1, OSX-2, and OSX-3) and two wellhead platforms (WHP-1 and WHP-2) in place with a total of 10 horizontal wells producing 150,000 bo/d from these two projects.

In addition to these three FPSOs, OSX has acquired two very large crude carriers for conversion into two FPSOs (OSX-4 and OSX-5). OGX will lease these FPSOs and expects delivery in 2014. Both FPSOs will have about 1.3 million bbl of storage capacity and a 100,000 b/d oil processing capacity.

OGX expects gas production ramp-up from the Parnaiba basin to begin in second-half 2012. The company has one project covering two accumulations in the PN-T-68 block, which is 46.7% owned by OGX. OGX expects a gross production of about 200 MMcfd (about 36,000 boe/d) in 2013 for the block.

OGX explained that its general development concept for the Campos basin shallow waters envisions each development well to have dry-completions from a wellhead platform tied to an FPSO. It said to expedite the drilling and accelerate production ramp-up, it has a strategy of predrilling with a semisubmersible drilling rig an average of five horizontal wells per accumulation prior to the installation of the wellhead platform. The remainder of the wells will be drilled from the wellhead platform.

OGX expects to produce 4.1 billion bbl from the several oil accumulations it has discovered in the Campos basin and will install 12 FPSOs and 11 wellhead platforms on the blocks.

Its planned production profile is ramp-up during three quarters, 4-year plateau production, and 20-22 year production decline.

Because of the low-GOR, the company plans to use all produced gas for operations and energy generation on the platforms.

OGX expects average field life capital expenditure will be about $2/bbl and operating expenditures will be less than $16/bbl.

Other of its costs estimates include:

• $50 million for predrilling a well from a semisubersible rig.

• $20 million for drilling a well from a wellhead platform in 75 days.

• $15 million for completing a well from a wellhead platform well in 30 days.

• $65 million for subsea flowlines, including production, electrical, gas lift, service, water injection, and test lines.

• $350,000/day for one leased FPSO.

• $160,000/day for one leased wellhead platform

• $85,000/day for operating and maintenance mostly related to an FPSO.

• $3.50/bbl variable unit cost.

• $100 million abandonment cost.

Waimea complex
The Waimea complex is on Block BM-C-41, which is 100% owned by OGX, in 140 m of water and about 80 km from shore. OGX expects to have 3 FPSOs and 2 wellhead platforms operating at the Waimea complex with 28 producing and 14 injection wells.

In 2013, OGX plans to have in operation the FPSOs OSX-1 and OSX-2, as well as the WHP-1, all of which have been secured.

The company said that it had acquired all production equipment for the initial production at the Waimea complex, including wet christmas trees and flexible lines. OGX plans to initially produced 10,000-20,000 b/d/well from three subsea completed horizontal wells to FPSO OSX-1. Two subsea injection wells also will be connected to the FPSO.

It expects production to start in October through an extended well test at Well OGX-26. Before the installation of WHP-1 in first-quarter 2013 and FPSO OSX-2 in second-quarter 2013, it will produce three horizontal subsea wells and four predrilled horizontal production wells during 2012 and 2013.

OGX expects to start operations from FPSO OSX-2 in third-quarter 2013 and have 180,000 b/d processing capacity installed. At that time, it will have seven horizontal production wells on‐stream, with three producing to FPSO OSX-1 and four producing to FPSO OSX-2.

Waikiki complex
The Waikiki complex on Blocks BM-C-39 and BM-C-40, both of which are 100% owned by OGX, is in 100 m of water about 90 km from shore. OGX expects to produce this complex with 1 FPSO, 1 wellhead platform, 14 producing wells, and 8 injection wells.

It said that it has secured FPSO OSX-3 and WHP-2 for this project and expects each of the wells to have a 15,000-20,000 b/d productivity.

Production is to begin in fourth-quarter 2013.

OGX intends to predrill five horizontal production wells during 2012 and 2013, prior to the installation of the WHP-2 in second-quarter 2013 and FPSO OSX-3 in third-quarter 2013.

The company expects that the complex will have a 100,000 b/d installed production capacity in 2013.

Parnaiba basin
To develop its discovered gas in the onshore Parnaiba basin, OGX plans to use vertical wells connected to a gathering system that will transport the gas to a gas processing unit designed for dry gas.

Its first project will bring on stream the Gaviao Azul and Gaviao Real fields in second-half 2012, with production reaching 200 MMscfd in 2013.

OGX expects to connect the gas treatment facility to gas thermal power plants that its affiliate MPX plans to build. MPX holds a 23.3% stake in the concession.

OGX has declared the commerciality of two accumulations (California and Sao Jose) in the PNT-68 block. OGX holds a 46.7% interest in each.

The plan for Project 1 includes 23 production wells, some with recompletions during the production period, at an estimated cost of $340 million (including recompletion costs) and an estimated drilling and completion time of 55 days/well.

The company estimates a $110 million cost for the facilities including a gathering system (lines and manifolds), a production facility for dry gas, and a very short pipeline.

Average operating cost for the field life including operation and maintenance of production facilities, lines, gas pipelines, wells and gas variable costs will be less than 30¢/Mscf, according to OGX.

OGX plans to have 18 production wells on stream in 2013.

Contact Guntis Moritis at guntism@ogjonline.com.

Related Articles

US Forest Service takes no stance on fracturing in national forest

12/12/2014

The US Forest Service has dropped a proposal that would have banned hydraulic fracturing in the George Washington National Forest.

Frac ban exemption made in Broomfield

12/12/2014 A Colorado District Court judge has ruled that a hydraulic fracturing ban in Broomfield, Colo., does not apply to an operator that entered into an ...

OSHA seeks to limit silica exposure for oil workers, Proposed rules target frac sand mining, fracturing

12/12/2014 The rapid growth in oil and gas production from shale and tight oil formations in the US is generating a boom in a related industry: frac sand. San...

Study links methane contamination in water wells to poor well construction-not fracing-in Marcellus

12/12/2014 A new study found that fugitive gas contamination at eight clusters of water wells in the Marcellus and Barnett shale regions might be linked to we...

Weak crude prices could threaten Bakken production growth

12/12/2014 Bakken shale production set another record in August, but weakening crude prices and flaring reduction efforts threatened to temper production grow...

Husky reports start of steam operations at Sunrise oil sands project

12/12/2014

Husky Energy, Calgary, reported the start of steam operations at the in situ Sunrise Oil Sands Project in northeastern Alberta.

TAEP: TPI still peaking, but ‘contraction unavoidable’ as oil prices fall

12/12/2014 The Texas Petro Index (TPI), a composite index based on a comprehensive group of upstream economic indicators released by the Texas Alliance of Ene...

US needs more data before ending crude export ban, House panel told

12/11/2014 Much more environmental impact information is needed before the US can reasonably remove crude oil export limits, a witness told a House Energy and...

BOEM raises offshore oil spill liability limit to $134 million

12/11/2014 The US Bureau of Ocean Energy Management increased the liability limit for oil-spill related damages from offshore operations to $134 million from ...

White Papers

AVEVA NET Accesses and Manages the Digital Asset

Global demand for new process plants, power plants and infrastructure is increasing steadily with the ...
Sponsored by

AVEVA’s Approach for the Digital Asset

To meet the requirements for leaner project execution and more efficient operations while transferring...
Sponsored by

Diversification - the technology aspects

In tough times, businesses seek to diversify into adjacent markets or to apply their skills and resour...
Sponsored by

Engineering & Design for Lean Construction

Modern marketing rhetoric claims that, in order to cut out expensive costs and reduce risks during the...
Sponsored by

Object Lessons - Why control of engineering design at the object level is essential for efficient project execution

Whatever the task, there is usually only one way to do it right and many more to do it wrong. In the c...
Sponsored by

Plant Design for Lean Construction - at your fingertips

One area which can provide improvements to the adoption of Lean principles is the application of mobil...
Sponsored by

How to Keep Your Mud System Vibrator Hose from Getting Hammered to Death

To prevent the vibrating hoses on your oilfield mud circulation systems from failing, you must examine...
Sponsored by

Duty of Care

Good corporate social responsibility means implementing effective workplace health and safety measures...
Sponsored by

Available Webcasts


On Demand

Optimizing your asset management practices to mitigate the effects of a down market

Thu, Dec 11, 2014

The oil and gas market is in constant flux, and as the price of BOE (Barrel of Oil Equivalent) goes down it is increasingly important to optimize your asset management strategy to stay afloat.  Attend this webinar to learn how developing a solid asset management plan can help your company mitigate costs in any market.

register:WEBCAST


Parylene Conformal Coatings for the Oil & Gas Industry

Thu, Nov 20, 2014

In this concise 30-minute webinar, participants have an opportunity to learn more about how Parylene coatings are applied, their features, and the value they add to devices and components.

register:WEBCAST


Utilizing Predictive Analytics to Optimize Productivity in Oil & Gas Operations

Tue, Nov 18, 2014

Join IBM on Tuesday, November 18 @ 1pm CST to explore how Predictive Analytics can help your organization maximize productivity, operational performance & associated processes to drive enterprise wide productivity and profitability.

register:WEBCAST


US HYDROCARBON EXPORTS Part 3 — LNG

Fri, Nov 14, 2014

US LNG Exports, the third in a trilogy of webcasts focusing on the broad topic of US Hydrocarbon Exports.

A discussion of the problems and potential for the export of US-produced liquefied natural gas.

These and other topics will be discussed, with the latest thoughts on U.S. LNG export policy.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected