Iraq's Baiji refinery due control upgrade

By OGJ editors
HOUSTON, June 1
-- North Refineries Co. of Iraq named Honeywell the main engineering, procurement, and construction contractor for an upgrade of automation systems at its 310,000-b/d hydroskimming and hydrocracking refinery in Baiji.

Honeywell will fully automate the refinery, replacing a 30-year-old single-loop instrument control system. The contractor said the project, in addition to improving productivity, will offer “full scalability to support future technology upgrades.”

Built in 1982, the Baiji refinery has these processing capacities: catalytic reforming 46,000 b/d, catalytic hydrocracking 38,000 b/d, and catalytic hydrotreating 182,000 b/d.

It has design capacity to produce 64 MMcfd of hydrogen, 5,000 b/d of lube oils, and 26,000 b/d of asphalt.

Related Articles

Ineos lets contract for Grangemouth ethane terminal

03/28/2014 Ineos Europe AG, Switzerland, said it has reached the latest milestones in its $500 million survival plan to import US shale gas to its 210,000-b/d...

Maintenance underway at Jamnagar refinery

03/27/2014 Reliance Industries Ltd. (RIL) has shut down one of three paraxylene units for planned maintenance at its 660,000-b/d Jamnagar refinery at Gujarat,...

Petronas progresses on RAPID project

03/27/2014 BMT Asia-Pacific Pte. Ltd. (BMT), a subsidiary of BMT Group Ltd., has completed a concept design for the material offloading facility (MOLF) at sta...

ENOC lets contract for Jebel Ali refinery upgrade

03/27/2014 Emirates National Oil Co. (ENOC) has let a front-end engineering and design (FEED) contract to KBR for the upgrade of its 120,000-b/d condensate re...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected