BP mulls $15 billion investment in Omani 'tight gas' fields

Eric Watkins
OGJ Oil Diplomacy Editor

LOS ANGELES, June 20 -- BP PLC is considering an investment of $15 billion over a 10-year period for the full-field development of its Block 61 tight gas fields in Oman, according to a senior executive of the firm.

“This will be a very large project…and will require approximately $15 billion in capital investment from BP to make that happen,” said Jonathan Edwards, vice-president of BP Oman.

“About $10 billion of that will go into the drilling of wells and the rest will go for surface facilities,” Evans said.

“We are proposing for the full field development of a gas processing plant with a capacity to process 1.2 bcfd, which will need 330 wells, and about 600 km of gathering system to connect all those wells,” Evans said.

“We have not yet reached an agreement with the government,” Evan said, adding that, “We have to submit a field development plan to the government, which we plan to do early next year.”

Evans noted that on the basis of field development plan, BP will negotiate commercial terms with the government. “The government has to agree for the scale of development that we are talking about,” he said.

If everything goes well, the first production of gas on commercial basis from the field is expected in late 2016 or early 2017. “We need 60 wells to start commercial production and thereafter, we will drill 20 wells every year for 10 years,” Evans said.

Evans’ remarks followed an announcement by BP of the successful completion of an extended well testing project, with the anticipated commercial gas production from its Khazzan and Makarem fields expected at about 1.2 bcfd.

“We are encouraged by the results of the extended well tests,” said Evans, who explained that the tests, “will help us as we now work towards declaration of commercialization by 2012-end.”

"We have already drilled eight wells and a ninth one is being drilled at the moment,” said Evans, who added that the stimulation and testing of the first three wells have been completed.

Evans said that teams in London and Muscat are working with the government of Oman to agree on the development concept for the Khazzan project, which will form the first phase of development on Block 61.

“This includes designs for wells and surface facilities,” said Evans, who added that BP had begun producing 60 MMcfd of gas from the test wells. He said seven wells have been successfully tested, with BP Oman planning to add two more wells by yearend.

Under the terms of the exploration and production-sharing agreement signed in January 2007, BP is required to submit a full field development plan to the government. “We plan to do this early next year, and on the basis of that, we will then negotiate commercial terms,” Evans said.

The agreement covers a 2,800 sq km area in central Oman, including the Khazzan and Makarem gas fields, which were discovered in 1993 but had remained undeveloped due to what BP called “the complexity of their tight gas reservoirs.”

At the time, BP said it signed “a major production-sharing agreement that will give the company access to two Middle East fields and associated accumulations that could yield resources of some 20-30 tcf of natural gas.”

In November 2009, BP completed drilling five of eight appraisal wells as part of its development program for the reserves on Block 61.

“BP will drill eight appraisal wells in total by 2011,” according to Jonathan Evans, BP Oman general manager. “So far we've done five wells, which have provided a lot of useful information on the nature and the scale of the reservoirs (OGJ Newsletter, June 7, 2010).”

BP has a 100% stake in Block 61, but Oman’s government may take 20% equity in the project at the time of commerciality.

Contact Eric Watkins at hippalus@yahoo.com.

Related Articles

Lone Star begins construction on third Mont Belvieu frac unit

11/06/2014 Lone Star NGL LLC, a joint venture of Energy Transfer Partners LP (70%) and Regency Energy Partners LP (30%), both of Dallas, has begun constructio...

AMP acquires Costar Midstream for $470 million

10/15/2014 American Midstream Partners LP (AMP), Denver, has acquired Costar Midstream LLC from Energy Spectrum Partners VI LP and Costar management for $470 ...

Exterran joins Woodford Express to build Oklahoma gas plant

10/14/2014 Exterran Holdings, Houston, will join Woodford Express LLC, a subsidiary of Xplorer Midstream LLC, Oklahoma City, to build a 210-MMcfd natural gas ...

EIA: US industrial gas demand to rise 4% in 2015

10/03/2014 Relatively low prices of natural gas have contributed to steady increases in US industrial gas consumption since 2009, especially as a feedstock fo...

Bill Barrett to divest Powder River, Piceance properties

09/16/2014 Bill Barrett Corp., Denver, reported that it has agreed with several undisclosed buyers to sell the majority of its Powder River basin acreage and ...

AAPG ICE: Turkey sees early shale oil development

09/15/2014 Turkey is slightly larger than the state of Texas geographically, yet the country has only seen 4,400 wells drilled since 1940. While Texas’ oil hi...

AAPG ICE: ExxonMobil outlines international approach to unconventional development

09/15/2014 Global energy demand is expected to increase 35% to 2040, translating to 120 billion boe/year, or nearly 350 million boe/d, stated Rocky Becker, vi...

WRI: Shale oil, gas face tight competition for water

09/03/2014 Governments and businesses trying to develop tight oil and gas resources could face intense competition for water that would be used in hydraulic f...

Canadian firms plan BC gas plant, target LNG export

08/19/2014 AltaGas Ltd. and Painted Pony Petroleum Ltd., both of Calgary, have agreed to develop processing and marketing of natural gas and NGLs for Painted ...

White Papers

AVEVA NET Accesses and Manages the Digital Asset

Global demand for new process plants, power plants and infrastructure is increasing steadily with the ...
Sponsored by

AVEVA’s Approach for the Digital Asset

To meet the requirements for leaner project execution and more efficient operations while transferring...
Sponsored by

Diversification - the technology aspects

In tough times, businesses seek to diversify into adjacent markets or to apply their skills and resour...
Sponsored by

Engineering & Design for Lean Construction

Modern marketing rhetoric claims that, in order to cut out expensive costs and reduce risks during the...
Sponsored by

Object Lessons - Why control of engineering design at the object level is essential for efficient project execution

Whatever the task, there is usually only one way to do it right and many more to do it wrong. In the c...
Sponsored by

Plant Design for Lean Construction - at your fingertips

One area which can provide improvements to the adoption of Lean principles is the application of mobil...
Sponsored by

How to Keep Your Mud System Vibrator Hose from Getting Hammered to Death

To prevent the vibrating hoses on your oilfield mud circulation systems from failing, you must examine...
Sponsored by

Duty of Care

Good corporate social responsibility means implementing effective workplace health and safety measures...
Sponsored by

Available Webcasts


On Demand

Optimizing your asset management practices to mitigate the effects of a down market

Thu, Dec 11, 2014

The oil and gas market is in constant flux, and as the price of BOE (Barrel of Oil Equivalent) goes down it is increasingly important to optimize your asset management strategy to stay afloat.  Attend this webinar to learn how developing a solid asset management plan can help your company mitigate costs in any market.

register:WEBCAST


Parylene Conformal Coatings for the Oil & Gas Industry

Thu, Nov 20, 2014

In this concise 30-minute webinar, participants have an opportunity to learn more about how Parylene coatings are applied, their features, and the value they add to devices and components.

register:WEBCAST


Utilizing Predictive Analytics to Optimize Productivity in Oil & Gas Operations

Tue, Nov 18, 2014

Join IBM on Tuesday, November 18 @ 1pm CST to explore how Predictive Analytics can help your organization maximize productivity, operational performance & associated processes to drive enterprise wide productivity and profitability.

register:WEBCAST


US HYDROCARBON EXPORTS Part 3 — LNG

Fri, Nov 14, 2014

US LNG Exports, the third in a trilogy of webcasts focusing on the broad topic of US Hydrocarbon Exports.

A discussion of the problems and potential for the export of US-produced liquefied natural gas.

These and other topics will be discussed, with the latest thoughts on U.S. LNG export policy.

register:WEBCAST


Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected