Technip to expand CNRL's Horizon upgrader

By OGJ editors
HOUSTON, May 2
-- Canadian Natural Resources Ltd. has let an engineering, procurement, and construction support services contract to Technip for expansion of the delayed coking unit at its Horizon bitumen upgrader in Fort McMurray, Alta.

Technip said value of the contract is about €100 million. Work is to be complete in 2013.

CNRL is expanding the Horizon oil sands mining and bitumen extraction project, now with capacity to produce 110 million b/d of 34° gravity synthetic crude oil (SCO), in phases to 232,000-250,000 million b/d.

In work it describes as reliability projects, it is adding 5,000 b/d of SCO capacity through 2014, this year completing a third ore preparation plant, hydro transport, and tank expansion.

The coker expansion, coupled with debottlenecking, will add 10,000 b/d of SCO capacity by 2014.

Future work will include a fourth ore preparation plant, vacuum distillation, and gas-oil hydrotreatment, combining for 45,000 b/d of incremental SCO capacity, followed by a fifth ore preparation plant, a third and fourth extraction unit, a combined hydrotreater, and sulfur recovery, adding 80,000 b/d of SCO capacity.

CNRL estimates proved and probable reserves at the Horizon project at 2.9 billion bbl of SCO and bitumen initially in place at 14.3 billion bbl.

Related Articles

Cenovus gets AER approval for Grand Rapids oil sands project

03/21/2014 Cenovus Energy Inc. reported that it has received approval from the Alberta Energy Regulator (AER) for its wholly owned Grand Rapids thermal oil sa...

Ivanhoe halts Tamarack oil sands project citing lack of regulatory ‘clarity’

03/18/2014 Ivanhoe Energy Inc. has suspended activity on its Tamarack oil sands project pending approval for its thermal oil sands application from the govern...

CAPP: Emissions monitoring Continues in Alberta oil sands

03/10/2014 Alberta's oil sands producers have monitored emissions for potential public health impacts with the province's government for a while, the Canadian...

Keystone XL national interest comments deadline approaches

03/06/2014 Groups on both sides said support has grown for their positions as the US Department of State’s Mar. 7 deadline approached for comments on whether ...

Careers at TOTAL

Careers at TOTAL - Videos

More than 600 job openings are now online, watch videos and learn more!

 

Click Here to Watch

Other Oil & Gas Industry Jobs

Search More Job Listings >>
Stay Connected